University of Sydney · FACULTY OF PROJECT MANAGEMENT

PMGT1860 · Project Initiation and Scope

- one subject, every graph, every model, every mark
Project Management14 Chapters11-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 7 of 11 · PMGT1860

Schedule, Budget, Resources, Quality, Risk & Procurement

Week 7 covers establishing the project's resources: estimating time, cost and resources and the methods of estimation, plus first principles of quality, risk and procurement management, and the RACI matrix for clarifying responsibility. The RACI, risk register and estimation logic strengthen the resourcing sections of the group initiation plan, and the RACI roles and estimation methods are common quiz items.

In this chapter

What this chapter covers

  • 01Estimate defined (PMBOK) — a quantitative assessment of likely cost, resources, effort or duration; duration vs effort
  • 02Methods of estimation — analogous (top-down), parametric (unit rate), bottom-up (roll up work packages), three-point (PERT), Wideband Delphi
  • 03Quality in projects — plan quality → manage/assure quality → control quality; conformance, verification vs validation
  • 04Risk defined — an uncertain event with a positive (opportunity) or negative (threat) effect on objectives
  • 05Risk process — identify → analyse (probability × impact; Expected Monetary Value) → plan responses → monitor
  • 06Threat responses (avoid, mitigate, transfer, escalate, accept) and opportunity responses (exploit, enhance, share, escalate, accept)
  • 07Contingency reserve (known risks) vs management reserve (unknown work); procurement planning and contract types
  • 08The RACI matrix — Responsible, Accountable (exactly one), Consulted, Informed
Worked example · free

Applied: choose an estimation method, size a risk, and read a RACI cell

Q [5 marks]. (a) A team must estimate a bespoke build with detailed work packages already defined and wants the most accurate figure — which estimation method fits, and which method is fastest but least accurate early on? (b) A risk has a 20% chance of a $50,000 loss — what is its Expected Monetary Value, and name one threat-response strategy? (c) In a RACI matrix, how many people can be Accountable for a single task, and what does Consulted mean? (5 marks, illustrative application of the Week 7 material.)
  • +1(a) Bottom-up estimating fits — it estimates each work package and rolls them up, giving the most accurate figure at the cost of most effort, and it builds directly on the WBS.
  • +1The fastest but least accurate early method is analogous (top-down) estimating, which uses actuals from a similar past project when little detail exists.
  • +1(b) Expected Monetary Value = probability × monetary impact = 0.20 × $50,000 = $10,000 (a threat, so a negative expected value).
  • +1A valid threat-response strategy is any of: avoid, mitigate, transfer, escalate or accept. (Opportunities instead use exploit, enhance, share, escalate, accept.)
  • +1(c) Exactly one person can be Accountable for a task (the single owner who approves). Consulted means someone who provides input through two-way communication (distinct from Informed, who is only kept up to date one-way).
(a) Bottom-up is most accurate; analogous (top-down) is fastest but least accurate early. (b) EMV = 0.20 × $50,000 = $10,000; a threat response is avoid/mitigate/transfer/escalate/accept. (c) Exactly one Accountable per task; Consulted = provides input via two-way communication.
Sia tip — The RACI rule most often tested: there is exactly one Accountable per task, and Consulted (two-way) differs from Informed (one-way). For estimation, remember the accuracy/effort trade-off: analogous is quick and rough, bottom-up is slow and precise. Ask Sia to quiz you on the response strategies; it checks your reasoning, not your graded work.
Glossary

Key terms

Estimation methods
Analogous/top-down (from a similar past project — fast, rough), parametric (a unit rate × quantity), bottom-up (estimate each work package and roll up — most accurate), three-point/PERT (E = (O + 4M + P) ÷ 6), and Wideband Delphi (expert consensus over anonymous rounds).
Duration vs effort
Duration = the total number of work periods to complete an activity; effort = the number of labour units required. They differ when more or fewer resources work in parallel.
Quality management
Plan quality (set standards/metrics) → manage/assure quality (audit processes) → control quality (inspect deliverables). Verification checks against specification; validation checks it meets stakeholder needs.
Project risk
An uncertain event or condition that, if it occurs, has a positive (opportunity) or negative (threat) effect on project objectives. Managed by identify → analyse (probability × impact, EMV) → plan responses → monitor.
Contingency vs management reserve
Contingency reserve is time/money set aside for known risks with active responses; management reserve is for unknown, unforeseen in-scope work.
RACI matrix
A responsibility-assignment grid mapping tasks (rows) to roles (columns): Responsible (does the work), Accountable (ultimately answerable/approves — exactly one per task), Consulted (input, two-way) and Informed (kept up to date, one-way).
FAQ

Schedule, Budget, Resources, Quality, Risk & Procurement FAQ

Which estimation method should I use — and which is most accurate?

It depends on how much detail you have. Analogous (top-down) estimating is fast and useful early when little is known, but least accurate; parametric uses a unit rate; bottom-up estimates each work package and rolls them up for the most accurate figure with the most effort; three-point (PERT) blends optimistic, most-likely and pessimistic estimates. Once your WBS has defined work packages, bottom-up is the accurate choice.

What is Expected Monetary Value and how do I calculate it?

EMV is a quantitative risk measure: probability multiplied by the monetary impact. A risk with a 20% chance of a $50,000 loss has an EMV of 0.20 × $50,000 = $10,000. It lets you compare and prioritise risks in money terms; for threats it is negative, for opportunities positive.

What do the four RACI letters mean, and what's the one strict rule?

Responsible does the work, Accountable is ultimately answerable and approves it, Consulted provides input through two-way communication, and Informed is kept up to date one-way. The strict rule is that exactly one person is Accountable for each task — split accountability is the classic RACI error. It maps tasks to roles to remove ambiguity over who does what.

What's the difference between contingency reserve and management reserve?

Contingency reserve is time or money set aside for known, identified risks that have active response plans. Management reserve is for unknown, unforeseen in-scope work that could not be identified in advance. Distinguishing them shows you understand that some risk is anticipated and planned for, while some is genuinely unexpected.

Study strategy

Assessment move

Organise this week around three quick-win concepts: the estimation methods (know the accuracy/effort trade-off and the PERT formula), the risk process (identify → analyse with probability × impact/EMV → respond → monitor, plus the threat and opportunity response lists), and the RACI matrix (exactly one Accountable; Consulted two-way vs Informed one-way). Sketch a small RACI for a project you know and a two-row risk register with EMV. Note the contingency-vs-management-reserve distinction. Add a journal line on estimating under uncertainty, and confirm quiz timing on Canvas.

Working through Schedule, Budget, Resources, Quality, Risk & Procurement in PMGT1860? Sia is AskSia’s AI Project Management tutor — ask any PMGT1860 Schedule, Budget, Resources, Quality, Risk & Procurement question and get a clear, step-by-step explanation grounded in how PMGT1860 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 12 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT1860 tutor, unlimited, worked the way the exam marks it
The full 11-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$25/ month
30-day money-back · cancel in one tap · how it works
Unlock the full PMGT1860 Bible + 12 University of Sydney subjects解锁完整 PMGT1860 Bible + University of Sydney 12 门科目
$25/mo