University of Melbourne · FACULTY OF IT PROJECT MANAGEMENT

ISYS90050 · It Project and Change Management

- one subject, every graph, every model, every mark
IT Project Management14 Chapters10-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 7 of 13 · ISYS90050

Cost Estimation & Budgeting

Week 6 covers budgets and the cost taxonomy — tangible/intangible, direct/indirect and sunk costs — the defect-cost escalation curve, and the three estimation techniques: analogous (top-down), activity-based (bottom-up) and parametric. The examinable calculation is costing a task with overhead and personal-time loading, plus reconciling top-down and bottom-up estimates by iterative negotiation. Cost types and the loaded-cost calculation appear in short-answer and scenario items.

In this chapter

What this chapter covers

  • 01Budget = a plan for allocating resources and a control baseline; project cost management = estimating, budgeting, controlling
  • 02Cost types: tangible vs intangible, direct vs indirect, sunk cost (ignore in future decisions), overhead
  • 03Defect-cost escalation across the SDLC (requirements 1x rising to post-release ~30x)
  • 04Estimate accuracy bands: ROM (-50/+100%), budgetary (-10/+25%), definitive (-5/+10%)
  • 05Analogous / top-down: expert judgment from a similar past project; quick, less accurate
  • 06Activity-based / bottom-up: estimate each WBS activity and sum; accurate but time-intensive
  • 07Parametric: a statistical rate (e.g. $ per line of code) times a parameter
  • 08Costing a task: duration x rate x (1 + overhead%) x (1 + personal-time%); iterative budgeting by negotiation (R vs r)
Worked example · free

Fully-loaded cost of a task with overhead and personal time

Q [3 marks]. A developer task is estimated at 40 hours at a base rate of $25/hour. The organisation loads an overhead of 60% and, because nobody works a fully productive 8-hour day, adds a personal-time allowance of 10%. Find the base cost (with overhead) and the fully-loaded cost. (3 marks)
  • +1Base cost with overhead = hours x rate x (1 + overhead). = 40 x 25 x 1.60. First 40 x 25 = $1,000; then x 1.60 = $1,600.
  • +1Apply the personal-time allowance to the loaded base: fully-loaded = base x (1 + personal-time) = 1,600 x 1.10 = $1,760.
  • +1Interpret. The raw effort ($1,000) understates the true cost by 76% once overhead and personal time are counted; budgeting on the raw rate alone would leave the task under-funded. The personal-time factor exists because an 8-hour day is not 8 productive hours.
Base cost with overhead = 40 x 25 x 1.60 = $1,600; fully-loaded cost = 1,600 x 1.10 = $1,760.
Sia tip — Apply the multipliers in order: raw effort (hours x rate), then x (1 + overhead), then x (1 + personal-time). Convert each percentage to a multiplier (60% -> 1.60, 10% -> 1.10) before you multiply, and keep the two factors separate so you can show both the loaded base and the final figure.
Glossary

Key terms

Sunk cost
Money already spent that cannot be recovered. It should not influence future invest-or-continue decisions — do not keep funding a failing project just because much has already been spent.
Direct vs indirect cost
Direct costs are tied to producing the project's products (salaries, project-specific hardware); indirect costs are incurred in doing the work but not tied to it (rent, electricity). Overhead spreads indirect costs across all work.
Analogous (top-down) estimation
An estimate based on expert judgment and the actual cost of a similar past project. Quick and inexpensive but less accurate; broken down top-to-bottom.
Activity-based (bottom-up) estimation
Estimating each work activity following the WBS and summing to a project total. More accurate when the team is experienced, but time-intensive and expensive to compile.
Parametric estimation
A statistical estimate using a rate per unit of a parameter (e.g. cost per line of code, adjusted for language and complexity) multiplied by the expected quantity.
Iterative budgeting by negotiation
Reconciling a PM's top-down requirement R with a team member's bottom-up estimate r (typically R << r): the PM is educated upward, the member relinquishes some padding, and both look for a more efficient method to close the gap.
FAQ

Cost Estimation & Budgeting FAQ

Why load a task cost with overhead and personal time?

Because the raw hours x rate figure understates what the task really costs. Overhead spreads indirect costs (rent, power, shared services) across the work, and the personal-time allowance recognises that an 8-hour day is not 8 productive hours (breaks, admin). Loading both gives a realistic cost = duration x rate x (1 + overhead) x (1 + personal-time).

Should a sunk cost affect whether we continue a project?

No. A sunk cost is money already spent and unrecoverable, so it should be ignored in any forward-looking decision. Continuing a failing project merely because a lot has already been invested is the sunk-cost fallacy; base the decision on future costs and benefits.

When would I use top-down versus bottom-up estimation?

Use analogous (top-down) early, when detail is thin and you can lean on a similar past project — it is quick but less accurate. Use activity-based (bottom-up) once the WBS is detailed and the team is experienced — it is more accurate but time-consuming. In practice the two are reconciled through iterative budgeting by negotiation.

Can AI help me with cost estimation in ISYS90050?

Yes, as a study aid. Sia can drill loaded-cost calculations, quiz you on the cost taxonomy and estimate-accuracy bands, and rehearse the top-down/bottom-up reconciliation. Use it to learn the method; it does not do your graded assessment, and University of Melbourne academic-integrity rules apply — confirm details on Canvas.

Study strategy

Exam move

Make the loaded-cost calculation reflexive — hours x rate, then x (1 + overhead), then x (1 + personal-time) — and be able to show both the loaded base and the final figure. Memorise the cost taxonomy (tangible/intangible, direct/indirect, sunk, overhead) and the three estimation techniques with one advantage and one drawback each, since these are staple short-answer items. Keep the estimate-accuracy bands and the defect-cost escalation shape ready as supporting facts, and be able to explain iterative budgeting by negotiation. For the closed-book exam, rehearse the arithmetic without a calculator crutch and convert percentages to multipliers cleanly.

Working through Cost Estimation & Budgeting in ISYS90050? Sia is AskSia’s AI IT Project Management tutor — ask any ISYS90050 Cost Estimation & Budgeting question and get a clear, step-by-step explanation grounded in how ISYS90050 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 14 of your University of Melbourne subjects - and 1,000+ Bibles across every Australian university.
Sia - your ISYS90050 tutor, unlimited, worked the way the exam marks it
The full 10-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$25/ month
30-day money-back · cancel in one tap · how it works
Unlock the full ISYS90050 Bible + 14 University of Melbourne subjects解锁完整 ISYS90050 Bible + University of Melbourne 14 门科目
$25/mo