University of Melbourne · FACULTY OF IT PROJECT MANAGEMENT

ISYS90050 · It Project and Change Management

- one subject, every graph, every model, every mark
IT Project Management14 Chapters9-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 8 of 13 · ISYS90050

Earned Value Management (EVM)

Week 6's second calculation topic integrates scope, schedule and cost. It teaches the three elements — Planned Value, Actual Cost and Earned Value — the variances (CV = EV - AC, SV = EV - PV), the indices (CPI = EV/AC, SPI = EV/PV) and forecasting with ETC and EAC. A full EVM snapshot with interpretation and a forecast is the signature calculation of the subject and a near-certain exam long-answer.

In this chapter

What this chapter covers

  • 01Three elements: PV = (planned % complete) x BAC; AC = actual cost incurred; EV = (actual % complete) x BAC
  • 02BAC = Budget at Completion (total budgeted spend); at start BAC = EAC and CPI = 1
  • 03Schedule Variance SV = EV - PV (>0 ahead, <0 behind); Cost Variance CV = EV - AC (>0 under, <0 over)
  • 04Schedule Performance Index SPI = EV / PV (<1 behind); Cost Performance Index CPI = EV / AC (<1 over budget)
  • 05Interpretation: negative variance = bad, index below 1 = bad, zero/one = on plan
  • 06Estimate to Complete ETC = (BAC - cum EV) / cum CPI
  • 07Estimate at Completion EAC = cum AC + (BAC - cum EV) / cum CPI
  • 08Variance at Completion VAC = BAC - EAC
Worked example · free

Full EVM snapshot with an ETC/EAC forecast

Q [5 marks]. An 8-month software project has a Budget at Completion (BAC) of $80,000, planned evenly. At the end of month 3 the actual cost is $25,000 and the work is 25% complete. Compute PV, EV, the cost and schedule variances, both indices, and forecast the Estimate to Complete and the Estimate at Completion. (5 marks)
  • +1The three elements. PV = (planned % complete) x BAC = (3/8) x 80,000 = 0.375 x 80,000 = $30,000. EV = (actual % complete) x BAC = 0.25 x 80,000 = $20,000. AC = $25,000 (given).
  • +1Variances (dollars). CV = EV - AC = 20,000 - 25,000 = -$5,000 (over budget). SV = EV - PV = 20,000 - 30,000 = -$10,000 (behind schedule).
  • +1Indices (ratios). CPI = EV / AC = 20,000 / 25,000 = 0.80 (only $0.80 of value per $1 spent). SPI = EV / PV = 20,000 / 30,000 = 0.667 -> about 0.67 (only 0.67 of planned work done).
  • +1Estimate to Complete. ETC = (BAC - cum EV) / cum CPI = (80,000 - 20,000) / 0.80 = 60,000 / 0.80 = $75,000 needed to finish the remaining work at the current cost efficiency.
  • +1Estimate at Completion. EAC = cum AC + (BAC - cum EV) / cum CPI = 25,000 + 75,000 = $100,000. The project is forecast to finish at $100,000 against an $80,000 budget — about 25% over (VAC = BAC - EAC = -$20,000).
PV = $30,000, EV = $20,000, AC = $25,000; CV = -$5,000 (over), SV = -$10,000 (behind); CPI = 0.80, SPI = 0.67; ETC = $75,000; EAC = $100,000 (about 25% over budget).
Sia tip — Compute EV first — it appears in every formula. Variances subtract (EV minus PV or AC) and carry a sign; indices divide (EV over PV or AC). For the forecast, ETC is the remaining work recalculated at the running CPI, and EAC = AC + ETC. A negative variance and an index below 1 both mean the same trouble.
Glossary

Key terms

Planned Value (PV)
The approved budgeted value of the work planned as of a status date: PV = (planned % complete) x BAC. It is the schedule baseline in dollars.
Earned Value (EV)
The budgeted value of the work actually completed to date: EV = (actual % complete) x BAC. It is the pivot of every EVM formula.
Actual Cost (AC)
The total cost actually incurred for the work completed to date, read from the project's financials — there is no formula for it.
Cost / Schedule Variance
CV = EV - AC (positive = under budget, negative = over budget); SV = EV - PV (positive = ahead of schedule, negative = behind). Both are dollar figures.
CPI / SPI
Performance indices: CPI = EV / AC (value earned per dollar spent) and SPI = EV / PV (work done per dollar planned). Below 1 is bad, above 1 is good, exactly 1 is on plan.
ETC / EAC
Forecasts: Estimate to Complete ETC = (BAC - cum EV) / cum CPI is the money still needed; Estimate at Completion EAC = cum AC + (BAC - cum EV) / cum CPI is the forecast total cost. VAC = BAC - EAC.
FAQ

Earned Value Management (EVM) FAQ

What is the difference between a variance and an index in EVM?

A variance is a dollar gap — CV = EV - AC and SV = EV - PV — so its sign tells you the size and direction of the problem (negative = over budget or behind). An index is a ratio — CPI = EV/AC and SPI = EV/PV — that tells you efficiency (below 1 = trouble, above 1 = good). Variances say how much; indices say how efficiently.

How do I forecast the final cost of a project with EVM?

Use the Estimate at Completion: EAC = cum AC + (BAC - cum EV) / cum CPI. The second term is the Estimate to Complete — the remaining budgeted work recalculated at the project's running cost efficiency (CPI). Comparing EAC with BAC (VAC = BAC - EAC) tells you the forecast overrun or underrun.

Why is EV the key number in every formula?

Earned Value is the budgeted value of the work truly finished, so it is the honest measure of progress. Comparing EV with what you planned to have done (PV) reveals schedule performance, and comparing it with what you actually spent (AC) reveals cost performance. Get EV wrong and every variance, index and forecast is wrong.

Can AI help me with EVM in ISYS90050?

Yes, as a study aid. Sia can generate fresh EVM snapshots, walk you through PV/EV/AC to the variances, indices and ETC/EAC forecasts, and check each line and interpretation. Use it to rehearse for the closed-book exam; it does not do your graded assessment, and University of Melbourne academic-integrity rules apply — confirm details on Canvas.

Study strategy

Exam move

EVM is the signature calculation of the subject, so drill a full snapshot until it flows: PV and EV from the percentages and BAC, AC from the figures, then CV/SV, CPI/SPI, and the ETC/EAC forecast. Anchor the sign rules once — negative variance bad, index below 1 bad, zero/one on plan — and always add the plain-English reading because the exam rewards interpretation, not just numbers. Memorise every formula for the closed-book paper and practise the forecasting step, which students most often drop. Rehearse two or three complete instances with fresh numbers under time pressure so the method, not the arithmetic, is what you are thinking about in the exam.

Working through Earned Value Management (EVM) in ISYS90050? Sia is AskSia’s AI IT Project Management tutor — ask any ISYS90050 Earned Value Management (EVM) question and get a clear, step-by-step explanation grounded in how ISYS90050 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 14 of your University of Melbourne subjects - and 1,000+ Bibles across every Australian university.
Sia - your ISYS90050 tutor, unlimited, worked the way the exam marks it
The full 9-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$25/ month
30-day money-back · cancel in one tap · how it works
Unlock the full ISYS90050 Bible + 14 University of Melbourne subjects解锁完整 ISYS90050 Bible + University of Melbourne 14 门科目
$25/mo