1 · Exam mapCourse data · Brief
| Component | Wt | Output |
|---|---|---|
| Tutorial participation + discussion | 5% | active, constructive |
| Discussion questions | 20% | 8 applied activities |
| Assignment | 25% | case report ≤1,500 words |
| Final Exam | 50% | individual; two hours |
Permitted materials: not confirmed for this offering in the course materials we hold — check the exam instructions on the LMS. [Brief]
2 · The answer spineC1 · Strategy
Risk = effect of uncertainty on an objective. Start with the objective; otherwise “risk” becomes a list of generic bad events.
| Separate | Meaning | Exam consequence |
|---|---|---|
| Risk / uncertainty | effect on objective / information gap | name objective first |
| Peril / hazard | loss cause / condition | control the right mechanism |
| Pure / speculative | loss-or-none / gain possible | insurance fits pure risk more readily |
| Systemic / specific | broad / idiosyncratic | diversification weak / useful |
| Static / dynamic | exists without change / arises from change | history is less dependable when conditions shift |
| Control / financing | changes loss / ensures funds after loss | do not mistake payment for prevention |
High-scoring risk statement
“Because [uncertainty/peril] can affect [objective] through [consequence], [owner] should [control/finance], monitor [indicator] and reconsider at [trigger]; [residual] remains.” One event may need several statements where service, privacy, regulation and cash flow are different objectives with different owners.
3 · Treatment chooserC1 · C2
| Tool | What changes | What remains |
|---|---|---|
| Avoid | do not start/stop exposure | lost benefit/opportunity |
| Reduce | frequency and/or severity | control failure, residual loss |
| Transfer | specified financial consequence/owner | peril, exclusions, deductible, counterparty |
| Retain | fund loss internally | volatility + liquidity need |
Control changes loss; financing makes funds available. Compare options on the same objective, horizon and boundary; add cost, feasibility, new dependencies and residual risk.
4 · Pooling + insuranceC2
E[L] = n × p × severity
Expected-loss contribution = E[L] ÷ n
Premium = expected claims + expenses + contingency + capital/profit loading.
Pooling assumptions
| Test | If weak |
|---|---|
| large enough pool | relative variability stays high |
| similar/measurable exposures | classification and price distort |
| sufficient independence | one event hits many; concentration |
| stable probabilities/severity | history misstates forward loss |
| defined event/interest/period/amount | claim disputes; uncertain capital |
Adverse selection: higher-risk applicants seek/retain more cover when classification is weak. Moral hazard: behaviour changes after protection, raising loss borne by another.
5 · Insurance operationsC3
| Structure | Capital / purpose |
|---|---|
| Mutual | members own; surplus supports members/reserves |
| Stock | investor equity; shareholders claim result |
| Government | fundamental risk, compulsion or equity |
| Lloyd’s market | specialist underwriting marketplace |
Reinsurance layer
Primary payment = retention + any amount above exhaustion (subject to terms).
Reinsurance can expand capacity, reduce capital strain, spread catastrophe exposure and stabilise results. It adds cost, wording/aggregation dependence and counterparty risk.
Underwriting ratios
Expense ratio = underwriting expense ÷ written premium [course method]
Combined ratio = loss ratio + expense ratio.
A combined ratio below 100% indicates underwriting margin for that period before investment/other results. It does not prove reserve adequacy, liquidity, asset quality or capital safety. Keep earned and written bases distinct.
| Ratio worsens | Check first | Action path |
|---|---|---|
| Loss | frequency, severity, reserve development, mix, inflation | wording, selection, price, claims, reinsurance |
| Expense | acquisition/admin cost + denominator | process/channel/scale |
Invested funds: premiums arrive before many claims. Asset return can support total profitability, but yield-seeking can add market, credit and liquidity risk; persistent underwriting weakness is not safely repaired by volatile investment income.
7 · Life + longevityC4
PV growing contribution = C₁ × [1 − ((1+g)/(1+r))ⁿ] ÷ (r−g)
One-period net premium = benefit × mortality probability ÷ (1+r), if paid at period end.
| Choice | Fit | Trap |
|---|---|---|
| Term | temporary debt/income horizon | renewal cost and expiry |
| Permanent | enduring need/estate liquidity/lifelong dependant | complexity, cost, guarantees |
| Death risk | support ends too soon | under-insurance |
| Longevity | resources end too soon | survival beyond funding horizon |
Use one valuation date; state nominal/real assumptions; do not double-count assets. A net premium is expected claim cost—not the final charged premium.
8 · Financial institutionsC5
Approx. Δ net interest income = gap × Δ rate.
| Gap / rate | Income direction |
|---|---|
| positive / rates ↑ | tends to rise |
| negative / rates ↑ | tends to fall |
| positive / rates ↓ | tends to fall |
| negative / rates ↓ | tends to rise |
Liquidity = meet obligations when due without unacceptable cost/loss. Solvency = economic assets sufficient for liabilities. A solvent institution can still fail when cash is unavailable; forced sale discounts can convert timing pressure into capital loss.
9 · Governance + countryC6
| Role | Accountability |
|---|---|
| Board | oversight; approve appetite and major decisions |
| Business | owns risks and first controls created by its decisions |
| Risk function | framework, analytics and independent challenge |
| Internal audit | independent assurance; does not own risk |
Appetite = broad amount/type willingly pursued or retained. Tolerance/limit = measurable boundary with owner, data, frequency, escalation and breach action. Exceptions need authority, maximum exposure, expiry, compensating controls and active renewal.
Monitor reserves, external debt, exchange-rate pressure, fiscal capacity, political disruption and payment restrictions. A ratio is evidence, not a complete country decision.
Portfolio test: aggregate common geography, currency, supplier, industry and scenario. Standalone-limit compliance can coexist with excess correlated exposure.
10 · VaR + credit lossC7
Always attach currency + holding period + confidence + portfolio boundary + modelling assumptions. A one-day 95% VaR of $2m means modelled losses exceed $2m on about 5% of trading days under stated conditions—not that $2m is the maximum.
Expected credit loss = PD × LGD × EAD.
Expected loss is a modelled mean for pricing, allowance and planning. Unexpected variation, default dependence and concentration call for limits, stress and economic capital. Keep PD, LGD and EAD on the same horizon/facility basis.
11 · Operational controlsC8
| Control | Job | Evidence |
|---|---|---|
| Preventive | stop error/event before consequence | configuration, approval, validation |
| Detective | find event/failure promptly | alert, reconciliation, exception log |
| Corrective | restore service/repair impact | recovery test, verified fix |
Separate event, impact, root cause and control gap; “human error” is rarely deep enough. Design asks whether a control could achieve its objective; operation asks whether it ran consistently with reliable inputs and follow-up.
Near miss: chance prevented full loss. KRI: timely indicator tied to mechanism, owner, threshold and response. A supplier contract does not remove the organisation’s accountability.
Closure test Implemented action + enough cycles + sampled evidence + exceptions followed up + authorised challenge + updated residual risk. A closed ticket is not proof.
12 · Regulation + capitalC9
Capital ratio = eligible capital ÷ RWA
Headroom = actual/forecast ratio − applicable threshold.
Build the weighted denominator before dividing. Then compare with the relevant minimum, internal target and trigger; name the exposure/capital change that consumes headroom and a feasible action.
| Layer | What it adds |
|---|---|
| Minimum | point-in-time quantitative constraint |
| Buffer/trigger | room and early escalation before breach |
| ICAAP | full risk profile, strategy, projections and board-approved plan |
| Stress | severe plausible loss path + timing + second-order effects |