about CIVL1810
01 · Exam map COURSE.JSON · BRIEF
| Assessment | Wt |
|---|---|
| Early Feedback Task | 0% |
| Assignment 1: Technical Drawing and Research | 10% |
| In Class Quiz 1 / Quiz 2 | 10% + 10% |
| Technical Report | 20% |
| Final Exam | 50% |
Permitted materials: not confirmed for this offering in the course materials we hold — check the exam instructions on the LMS.
FINAL SHAPE Recent papers use a 50-mark total: one multi-part surveying computation, a formwork calculation with equations/coefficient table supplied, then construction process questions where labelled sketches carry marks.
02 · Project decisions CH 1
Project = unique purpose + temporary start/finish + resources from several areas + uncertainty. Stakeholder includes anyone involved or positively/negatively affected.
| Gate result | Decision rule |
|---|---|
| Go | authorise next stage |
| No go | eliminate from further review |
| Hold | wait for external technical/market/environment change |
| Recycle | return deliverables for refinement/resubmission |
ANSWER STEM Check: prior stage complete? business case still sound quantitatively and qualitatively? credible plan? Then name one decision and eliminate the other three.
Charter, plan, control
| Item | What it does |
|---|---|
| Business case | documents economic feasibility before commitment |
| Project charter | formally authorises work and gives the project manager authority to commit organisational resources; authorised outside the delivery team |
| CPMP | sets how the construction job is run, monitored, controlled and closed; must be bought into, approved, realistic and formal |
03 · Estimate + control CH 2
| Method | Use / trade-off |
|---|---|
| Analogous | actual cost of similar job; top-down, cheaper, less precise |
| Parametric | statistical fit to past records/variables; accuracy follows model + data quality |
| Bottom-up | price work packages then roll up; most accurate, most costly |
| Three-point | exposes uncertainty/asymmetry |
Scope definition controls accuracy. Estimates sharpen through the life cycle because less work remains undescribed. A material take-off counts drawing content; the bill of quantities is the itemised labour/equipment/material schedule tendered against.
Integrated change control reviews, decides, manages and communicates changes so scope/schedule/cost baselines remain meaningful. Corrective action addresses divergence already present; preventive action protects future alignment.
04 · Site + plant chooser CH 3
| Plant | Best fit / limit |
|---|---|
| Power shovel | cuts a face/bank; rock/stone; cannot work flat surface |
| Backhoe | works below machine; ordinary excavation/trenches; reach limits wide digs |
| Dragline | stands beside wide open cut; long reach |
| Clamshell | deep small footprint; all soils except rock |
| Scraper | excavate + load + haul + dump; long open haul |
| Dozer | clearing/levelling; pair haul separately if needed |
Clearance numbers
Topsoil 300 mm; sapling limit 300 mm girth measured 1 m above ground; rubbish 50 m beyond periphery. Roots: deepest of 600 mm below existing surface, 300 mm below formation, 150 mm below subgrade; refill, ram, level. Existing services: reroute/remove only on site engineer’s instruction.
Two independent cost questions
Commence the site in order
05 · Foundation decision CH 4
Choose from soil · building load · design · cost · technology. Shallow systems spread load directly below column/wall; piles penetrate incompetent upper material to competent soil/rock.
| Type | Selection rule |
|---|---|
| Pad | single column; most subsoils; not loose sand/gravel or fill |
| Strip | continuous below wall; modest loads on nearly any subsoil |
| Raft | wide base for low bearing capacity or heavy column loads; fails if weak layer continues deep |
| Grade beam | gathers wall load to spaced supports such as pile caps |
| Piles | reach past incompetent upper material; driven or bored |
thickness 50–75 mm · strength ≈ 5–10 MPa
Purpose: clean, level, dry platform; fill soft spots; separate bars/fresh structural concrete from soil so designed cover survives. Strength is not the objective.
Driven piles
- Excavate to pile-cap level; remove spoil.
- Lift preformed pile by lifting lug; position vertical.
- Drive by drop hammer to refusal or specified depth; cast cap over group. Driving displaces soil; bored piles remove it.
06 · Load path CH 5
| Element | Typical dimension |
|---|---|
| Concrete span | 5–12 m |
| Slab thickness | 160–250 mm |
| Column width | 200–1000 mm |
| Wall thickness | 150–400 mm |
Selection answer scaffold
- Name the ground profile and competent founding layer.
- Test pad/strip/raft against soil and load; say exactly why one fails.
- Ask whether a thin poor layer can be excavated through economically.
07 · Slab-on-ground sequence CH 5
| # | Action | Reason / check |
|---|---|---|
| 1 | excavate, level, set out; remove organic matter | cut/fill creates natural + placed founding materials |
| 2 | backhoe trenches, hand clean | edge beams only on natural soil or controlled fill |
| 3 | allow services | pipe outside middle third → deepen/add steel/both |
| 4 | form wet-area recess | top set down 40–50 mm; preserve footing thickness |
| 5 | peg/fix formwork | pegs plumb, outside line by board thickness |
| 6 | screed + compact sand | accurate level; firm, non-puncturing base |
| 7 | lay/hold/seal membrane | laps ≥200 mm; seal penetrations |
| 8 | fix steel on tied chairs | pre-cut mesh; maintain cover |
| 9 | place concrete | do not flatten chairs or tear membrane |
| 10 | screed + finish | work between level dots before initial set |
| 11 | moist cure | hessian/water spray; gain strength, durability, watertightness |
SEQUENCE ANSWER Use six moves: platform → trench → services/recesses → form/bed/seal → steel/cover → pour/finish/cure. Attach a reason to each; a list of verbs is not enough.
08 · Middle-third rule CH 5
Pipe outside band: relocate or increase beam depth/reinforcement, or both. Wet-area recess must not thin the footing beneath it.
Consequences under a word limit
| Change | Ultimate + serviceability response |
|---|---|
| span too long | moment/shear rise; deflection and cracking rise; deepen/add supports/revise system |
| floor load too high | member capacity and punching/shear challenged; vibration/deflection worsen |
| column will not fit plan | replace point support with a wall/transfer arrangement only after load path is re-established |
09 · Concrete numbers bank CH 6
| Property | Value / consequence |
|---|---|
| Aggregate | 65–80% of mix volume |
| Water/cement | about 0.4–0.6; extra water ↑workability but ↓strength/durability |
| Initial set | 30 min–1 h: placing/finishing window ends |
| Solid | about 10 h |
| Dense mass | 7 days |
| Full maturity | around 28 days |
| Compression | 30–50 MPa; up to 100 MPa high performance |
| Tension | only 3–5 MPa → steel carries tension |
| Deformed bar | nominal yield 500 MPa |
Reduce variability before raising the mean: tighter batching/moisture control raises f′c without adding cement to every cubic metre.
Sampling logic
Required count scales through three volume bands: three, six or twelve samples. Take specimens from different mixers; deliver to a certified laboratory within 20–32 h. A result is representative only if both conditions hold.
TRAP Curing is not drying. Water reacts with cement. Keep concrete moist; hot/windy conditions shorten finishing time and then accelerate water loss.
10 · RC drawing rules CH 7
| Mark | Meaning |
|---|---|
| solid line | slab edge or change in slab top |
| dashed line | change in soffit/bottom of slab |
| column mark | cross-reference to size, vertical bars, ties, type, strength in schedule |
| O / U | element continues over / under level shown |
| void symbol | requires trimmer bars per legend |
incremental deflection ≤ span/500
Drawing cross-reference routine
Reinforcement consequences
11 · Levelling method CH 10
Field procedure
- Record every staff reading in the field book.
- Equalise BS and FS distances so collimation errors cancel in subtraction.
- Keep sights under 100 m; use a firm, defined change point.
- Start and finish on a known datum/benchmark; close the traverse.
| Rise & fall | Height of collimation |
|---|---|
| Compare consecutive readings within each setup. Prior − next >0 = rise; <0 = fall. | HC = known RL + BS. Every point RL = HC − reading; recompute after move. |
| Slower; includes IS in three-way check. | Faster; only two agreeing quantities, so an IS arithmetic slip may escape. |
Arithmetic closure proves the reduction, not the observation. A settled CP, staff off vertical, long sight, or collimation with unequal distances can leave the sums correct yet the benchmark closure wrong.
MISCLOSURE If within the job’s specified allowance, distribute (commonly by setup count); otherwise re-observe. Never invent a tolerance.
12 · Fast recall CH 6 · 8 · 9
| If you see… | Recall |
|---|---|
| plain concrete in tension | 3–5 MPa only → reinforcement |
| lap joint | one shear plane; P across it; eccentric |
| two cover plates | two planes; P/2 each; symmetric |
| rigid vs flexible pavement | where load distribution occurs, not a strength ranking |
| cracks at 3.7–6.1 m | contraction-joint spacing |
Pavement layer decision
Assess subgrade by strength, gradation and drainage when wet. Remove, replace or stabilise poor material. Quality grades upward: fine subbase → coarse base → wearing surface. Spread wheel stress below every layer’s strength.