University of Sydney · S2 2026 · FACULTY OF PROJECT MANAGEMENT

PMGT5889 Project Controls

- one subject, every graph, every model, every mark
12 Chapters33-page Bible
Our own words - no uploaded lecturer files
Built to mirror S2 2026 · updated this semester
The Complete Study & Assessment Guide · S2 2026

PMGT5889 Overview

Project Controls
— A source-grounded PMGT5889 guide to 1/10/19/30/5/35 architecture, project control cycle, 85% attendance expectation and the complete published assessment structure.
  • The University of Sydney
  • Semester 2, 2026
  • a postgraduate Project Management unit
  • 6 credit points

PMGT5889 Project Controls integrates scope, schedule, cost, finance, earned value and performance reporting into a controllable project baseline. It is taught within University of Sydney School of Project Management, Faculty of Engineering. It is a postgraduate Project Management unit. It carries 6 credit points.

  • PMGT5889 grading Early Feedback Test 1% · Assignment 1 10% · Online Test 19% · 3 more published item(s)
  • PMGT5889 task mode Plan around this operating format: No final examination appears in the official 2026 PMGT5889 table.
  • PMGT5889 pressure point The main transfer challenge is this: Keeping the scope, schedule and cost baselines internally consistent as assumptions change.
Why read this guide

What you get in the full PMGT5889 Study & Assessment Guide

  1. 12 chapters, 33 pages — every assessed topic
  2. 15 original practice questions, each with a model answer
  3. 12 worked examples, solved the way PMGT5889 marks
  4. 22 computed figures, redrawn from the course’s own numbers
  5. Before-you-submit checklist for the Assignment 3 (35%) — what markers reward, what costs marks

Free on this page: assessment table, chapter map, one worked example, key terms, FAQ. The rest is in the full study & assessment guide.

PMGT5889 · The University of Sydney
An independent, AskSia-authored study guide. AskSia is not affiliated with, endorsed by, or sponsored by The University of Sydney; the course code and name are used for identification only.
Assessment

How PMGT5889 is assessed

ComponentWeightFormat
Early Feedback Test1%Individual online quiz in Week 3
Assignment 110%Group charter, work breakdown structure and estimating task
Online Test19%Individual 45-minute knowledge test in Week 8
Assignment 230%Group integrated scope, cost, time and earned-value control report
Group Presentation5%Group presentation of no more than 15 minutes
Assignment 335%Individual application and reflection task

The six official weights total 100%. Attendance sources conflict: the 2026 S2 outline states at least 85%, while the captured unit introduction states an expected minimum of 90%; students must confirm the operative threshold in the current LMS or with the teaching team.

Other students are asking · PMGT5889

What other students are asking about PMGT5889

Where can I find lecture notes or study guides for PMGT5889 at USyd?
The PMGT5889 study guide in AskSia Library covers Project Controls in 12 chapters, with the assessment table, a chapter-by-chapter topic map, key terms and a worked example, free to read on this page.
Is there a final exam in PMGT5889?
No final exam is listed in the offering this AskSia Library guide is built from; PMGT5889 is assessed by Early Feedback Test 1%, Assignment 1 10%, Online Test 19%, Assignment 2 30%, Group Presentation 5%, Assignment 3 35%.
What does PMGT5889 cover on integrated project controls and governance?
In AskSia Library's PMGT5889 guide, the Integrated Project Controls and Governance chapter explains integrated project control · control account · governance threshold · assign each control signal to an owner, baseline and escalation threshold.
What does PMGT5889 cover on charter, scope and work breakdown structure?
In AskSia Library's PMGT5889 guide, the Charter, Scope and Work Breakdown Structure chapter explains project charter · scope baseline · work breakdown structure · decompose a deliverable until responsibility, estimate and completion evidence can be assigned.
What does PMGT5889 cover on network logic and the critical path?
In AskSia Library's PMGT5889 guide, the Network Logic and the Critical Path chapter explains activity network · critical path · total float · calculate earliest and latest times and explain which dependency or duration drives completion.
Weights, dates and every chapter are set out with their sources further down this page.
Current dates · verify in LMS

Current PMGT5889 dates

DateItemControl
23 Aug 2026 · 23:59Early Feedback Test1% in-class quiz
13 Sep 2026 · 23:59Assignment 110% group start-up assignment
27 Sep 2026 · 23:59Online Test19% 45-minute knowledge test
1 Nov 2026 · 23:59Assignment 230% detailed group application
8 Nov 2026 · 23:59Group Presentation and Assignment 35% presentation and 35% individual assignment share the published deadline

Dates are as published in the current course materials. Confirm exact deadlines and submission settings in the live LMS.

Contents · every chapter, one map

What PMGT5889 covers

Build the course in three arcs: Integrated Baselines, Assessment Milestones and Control establishes the frame, Financial Appraisal and Funding Decisions deepens it, and Control Plan, Presentation and Individual Synthesis tests the complete method.

01

Integrated Baselines, Assessment Milestones and Control

1/10/19/30/5/35 architecture · project control cycle · 85% attendance expectation · link every task to a control-cycle decision and keep group evidence separate from individual judgement

Define 1/10/19/30/5/35 architecture

Integrated Baselines, Assessment Milestones and Control frames a decision through 1/10/19/30/5/35 architecture, project control cycle and 85% attendance expectation.

  • 1/10/19/30/5/35 architecture
  • project control cycle
  • 85% attendance expectation
  • Applying 1/10/19/30/5/35 architecture
  • Limits of project control cycle and 85% attendance expectation
In the full guide: 3 pages · 1 practice question · 1 figure
02

Integrated Project Controls and Governance

integrated project control · control account · governance threshold · assign each control signal to an owner, baseline and escalation threshold

Define integrated project control

Integrated Project Controls and Governance frames a decision through integrated project control, control account and governance threshold.

  • integrated project control
  • control account
  • governance threshold
  • Applying integrated project control
  • Limits of control account and governance threshold
In the full guide: 2 pages · 1 practice question · 1 figure
03

Charter, Scope and Work Breakdown Structure

project charter · scope baseline · work breakdown structure · decompose a deliverable until responsibility, estimate and completion evidence can be assigned

Define project charter

Charter, Scope and Work Breakdown Structure frames a decision through project charter, scope baseline and work breakdown structure.

  • project charter
  • scope baseline
  • work breakdown structure
  • Applying project charter
  • Limits of scope baseline and work breakdown structure
In the full guide: 3 pages · 1 practice question · 1 figure
04

Network Logic and the Critical Path

activity network · critical path · total float · calculate earliest and latest times and explain which dependency or duration drives completion

Define activity network

Network Logic and the Critical Path frames a decision through activity network, critical path and total float.

  • activity network
  • critical path
  • total float
  • Applying activity network
  • Limits of critical path and total float
In the full guide: 2 pages · 1 practice question · 2 figures
05

Estimating Duration, Effort and Uncertainty

bottom-up estimate · three-point estimate · estimating contingency · compare estimate methods and expose the assumption that contributes most to uncertainty

Define bottom-up estimate

Estimating Duration, Effort and Uncertainty frames a decision through bottom-up estimate, three-point estimate and estimating contingency.

  • bottom-up estimate
  • three-point estimate
  • estimating contingency
  • Applying bottom-up estimate
  • Limits of three-point estimate and estimating contingency
In the full guide: 2 pages · 1 practice question · 2 figures
06

Budgeting, Cash Flow and Cost Baseline

project budget · time-phased cost baseline · project cash flow · reconcile work-package estimates, contingency, funding timing and the performance baseline

Define project budget

Budgeting, Cash Flow and Cost Baseline frames a decision through project budget, time-phased cost baseline and project cash flow.

  • project budget
  • time-phased cost baseline
  • project cash flow
  • Applying project budget
  • Limits of time-phased cost baseline and project cash flow
In the full guide: 3 pages · 1 practice question · 2 figures
07

Financial Appraisal and Funding Decisions

net present value · discount rate · funding constraint · compare project cash flows on one valuation date and test the decision under a changed rate

Define net present value

Financial Appraisal and Funding Decisions frames a decision through net present value, discount rate and funding constraint.

  • net present value
  • discount rate
  • funding constraint
  • Applying net present value
  • Limits of discount rate and funding constraint
In the full guide: 3 pages · 1 practice question · 2 figures
08

Baseline Integration and Status Data

performance measurement baseline · status date · progress measurement rule · validate that scope, schedule, budget and progress rules refer to the same work and reporting date

Define performance measurement baseline

Baseline Integration and Status Data frames a decision through performance measurement baseline, status date and progress measurement rule.

  • performance measurement baseline
  • status date
  • progress measurement rule
  • Applying performance measurement baseline
  • Limits of status date and progress measurement rule
In the full guide: 3 pages · 1 practice question · 1 figure
09

Earned Value, Cost and Schedule Performance

planned value · earned value · actual cost · calculate variances and indices, then explain the baseline relationship that each comparison measures

Define planned value

Earned Value, Cost and Schedule Performance frames a decision through planned value, earned value and actual cost.

  • planned value
  • earned value
  • actual cost
  • Applying planned value
  • Limits of earned value and actual cost
In the full guide: 2 pages · 1 practice question · 2 figures
10

Forecasting Estimate at Completion

estimate at completion · estimate to complete · to-complete performance index · select a forecast formula by stating whether current efficiency is expected to persist

Define estimate at completion

Forecasting Estimate at Completion frames a decision through estimate at completion, estimate to complete and to-complete performance index.

  • estimate at completion
  • estimate to complete
  • to-complete performance index
  • Applying estimate at completion
  • Limits of estimate to complete and to-complete performance index
In the full guide: 2 pages · 1 practice question · 2 figures
11

Variance Diagnosis, Change and Communication

variance analysis · integrated change control · performance report · move from variance signal to cause, forecast, options, approval path and stakeholder message

Define variance analysis

Variance Diagnosis, Change and Communication frames a decision through variance analysis, integrated change control and performance report.

  • variance analysis
  • integrated change control
  • performance report
  • Applying variance analysis
  • Limits of integrated change control and performance report
In the full guide: 2 pages · 1 practice question · 1 figure
12

Control Plan, Presentation and Individual Synthesis

control plan · team evidence trail · reflective application · present one integrated control decision and then distinguish team output from individual learning

Define control plan

Control Plan, Presentation and Individual Synthesis frames a decision through control plan, team evidence trail and reflective application.

  • control plan
  • team evidence trail
  • reflective application
  • Applying control plan
  • Limits of team evidence trail and reflective application
In the full guide: 3 pages · 1 practice question · 2 figures

It is positioned as a project controls unit in the Master of Project Management suite.

Assessment follows the control cycle itself: define the charter and work breakdown structure, estimate and baseline the work, measure performance through earned value, communicate variance, and reflect on application.

Group artefacts and individual judgement are both visible in the final result.

Assessment in PMGT5889 is distributed as follows: Early Feedback Test 1%, group Assignment 1 10%, Online Test 19%, group Assignment 2 30%, Group Presentation 5%, and individual Assignment 3 35%

The operational assessment conditions matter here. No final examination appears in the official 2026 PMGT5889 table.

The 19% online knowledge test runs in Week 8 under the mode-specific instructions published for the enrolled class.

What makes PMGT5889 demanding is concrete: Keeping the scope, schedule and cost baselines internally consistent as assumptions change.

Earned-value numbers are easy to compute mechanically; the difficult part is tracing each variance to the baseline, forecasting its consequence and recommending a control action that does not hide uncertainty.

Two current sources publish different attendance figures: the official 2026 S2 outline states at least 85% and says failure may result in a fail grade, while the captured unit introduction states an expected minimum of 90%.

No weighted assessment is labelled as a component hurdle.

Students must confirm the operative attendance threshold in the current LMS or with the teaching team.

For enrolment planning, The 2026 unit outline publishes no prerequisite.

Build the course in three arcs: Integrated Baselines, Assessment Milestones and Control establishes the frame, Financial Appraisal and Funding Decisions deepens it, and Control Plan, Presentation and Individual Synthesis tests the complete method.

Coverage note: the attendance consequence is conditional and is not assigned to an invented assessment row.

Worked example · free

Read earned-value signals before recommending control

Q [4 marks]. At the status date PV is 120, EV is 100 and AC is 125. Calculate the core variance and index signals, then identify what remains unknown.
Figure.Figure. 1/10/19/30/5/35 architecture, project control cycle and 85% attendance expectation lead to a chapter-specific link individual judgement.1/10/19/30/5/35architectureprojectcontrol cycle85% attendanceexpectationlinkindividual judgement
Figure. 1/10/19/30/5/35 architecture, project control cycle and 85% attendance expectation lead to a chapter-specific link individual judgement.
  • 1Calculate cost variance and schedule variance.
  • 1Calculate CPI and SPI from the same status date.
  • 1Interpret the four signs against the approved baseline.
  • 1Name the causal evidence needed before recommending corrective action.
CV = −25 and SV = −20; CPI = 0.80 and SPI ≈ 0.83. The project has earned less budgeted value than both its actual cost and planned value at the status date. The metrics flag a problem but do not identify its cause, so the next step is to trace the affected work packages, progress rule, cost records and authorised changes.
Sia tip — Never turn an earned-value signal into a cause without checking the baseline and status data.
Glossary

Key terms

Earned value management
A project-control method integrating planned value, earned value and actual cost to measure performance and forecast outcomes against a baseline.
Work breakdown structure
A hierarchical decomposition of the complete project scope into manageable deliverables and work packages used for planning and control.
Critical path
The longest-duration path through a project network that determines the earliest possible completion under the stated schedule assumptions.
Cost baseline
The time-phased approved project budget used as the reference for measuring and controlling cost performance.
Cost performance index
The ratio of earned value to actual cost, indicating the amount of budgeted value earned per unit of cost spent.
Schedule performance index
The ratio of earned value to planned value, indicating progress against the time-phased value baseline at the status date.
Estimate at completion
A forecast of total project cost at completion derived from current actual cost, remaining work and explicit performance assumptions.
Change control
A governed process for evaluating, approving, documenting and implementing changes to project scope, schedule, cost or other baselines.
FAQ

PMGT5889 FAQ

Which current PMGT5889 dates are captured?

Early Feedback Test: 23 Aug 2026 · 23:59; Assignment 1: 13 Sep 2026 · 23:59; Online Test: 27 Sep 2026 · 23:59; Assignment 2: 1 Nov 2026 · 23:59. Confirm any change and the exact submission setting in the live LMS.

How is PMGT5889 assessed?

Early Feedback Test 1%, group Assignment 1 10%, Online Test 19%, group Assignment 2 30%, Group Presentation 5%, and individual Assignment 3 35%

Where do students usually lose marks in PMGT5889?

Keeping the scope, schedule and cost baselines internally consistent as assumptions change. Earned-value numbers are easy to compute mechanically; the difficult part is tracing each variance to the baseline, forecasting its consequence and recommending a control action that does not hide uncertainty.

How does cost performance index appear in PMGT5889?

Cost performance index equals earned value divided by actual cost. A value below one indicates less budgeted value was earned per dollar spent than planned, but diagnosis still requires the baseline, measurement date and cause of the variance.

Does PMGT5889 have a hurdle or component-level pass rule?

Two current sources publish different attendance figures: the official 2026 S2 outline states at least 85% and says failure may result in a fail grade, while the captured unit introduction states an expected minimum of 90%. No weighted assessment is labelled as a component hurdle. Students must confirm the operative attendance threshold in the current LMS or with the teaching team.

What is the PMGT5889 final assessed-task format?

No final examination appears in the official 2026 PMGT5889 table. The 19% online knowledge test runs in Week 8 under the mode-specific instructions published for the enrolled class.

Is this PMGT5889 resource an official university guide?

No. It is an independent PMGT5889 study resource; current institutional instructions remain authoritative for assessment operation.

Chapter questions

Questions students ask in each PMGT5889 chapter

What is the main task in Integrated Baselines, Assessment Milestones and Control?
Link every task to a control-cycle decision and keep group evidence separate from individual judgement. Chapter 01 · Integrated Baselines, Assessment Milestones and Control
What is the main task in Integrated Project Controls and Governance?
Assign each control signal to an owner, baseline and escalation threshold. Chapter 02 · Integrated Project Controls and Governance
What is the main task in Charter, Scope and Work Breakdown Structure?
Decompose a deliverable until responsibility, estimate and completion evidence can be assigned. Chapter 03 · Charter, Scope and Work Breakdown Structure
What is the main task in Network Logic and the Critical Path?
Calculate earliest and latest times and explain which dependency or duration drives completion. Chapter 04 · Network Logic and the Critical Path
What is the main task in Estimating Duration, Effort and Uncertainty?
Compare estimate methods and expose the assumption that contributes most to uncertainty. Chapter 05 · Estimating Duration, Effort and Uncertainty
What is the main task in Budgeting, Cash Flow and Cost Baseline?
Reconcile work-package estimates, contingency, funding timing and the performance baseline. Chapter 06 · Budgeting, Cash Flow and Cost Baseline
What is the main task in Financial Appraisal and Funding Decisions?
Compare project cash flows on one valuation date and test the decision under a changed rate. Chapter 07 · Financial Appraisal and Funding Decisions
What is the main task in Baseline Integration and Status Data?
Validate that scope, schedule, budget and progress rules refer to the same work and reporting date. Chapter 08 · Baseline Integration and Status Data
What is the main task in Earned Value, Cost and Schedule Performance?
Calculate variances and indices, then explain the baseline relationship that each comparison measures. Chapter 09 · Earned Value, Cost and Schedule Performance
What is the main task in Forecasting Estimate at Completion?
Select a forecast formula by stating whether current efficiency is expected to persist. Chapter 10 · Forecasting Estimate at Completion
What is the main task in Variance Diagnosis, Change and Communication?
Move from variance signal to cause, forecast, options, approval path and stakeholder message. Chapter 11 · Variance Diagnosis, Change and Communication
What is the main task in Control Plan, Presentation and Individual Synthesis?
Present one integrated control decision and then distinguish team output from individual learning. Chapter 12 · Control Plan, Presentation and Individual Synthesis
Study strategy

How to prepare for the assessments

Retrieve the course map, practise the recurring method—define the approved scope, schedule and cost baseline, measure status consistently, diagnose variance, forecast consequence and recommend a governed control action—on changed scenarios, and verify every operational assessment detail in the live institutional system.

Study PMGT5889 with AI

Your AI Project Management tutor for PMGT5889

Stuck on a hard PMGT5889 question? Sia is AskSia’s AI Project Management tutor — ask any PMGT5889 Project Controls question and get a clear, step-by-step explanation grounded in how the course is actually taught and assessed. Read this whole study guide free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 202 of your subjects at University of Sydney, plus 1,000+ more Bibles across the AskSia library.
Sia - your PMGT5889 tutor, unlimited, worked the way the exam marks it
The full 33-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works