MATH10065 Chap.2 Critical Paths and Project Timing
Critical Paths and Project Timing
Encode precedence before timing
The critical path method begins with a network whose links express required ordering. A forward pass finds earliest event times. At a merge, all required predecessors must finish, so the earliest time is the maximum incoming completion.
The final earliest time gives project duration.
Protect the finish backwards
Set the final latest time equal to project duration, then move backwards. A predecessor with several successors must satisfy every outgoing requirement, so take the minimum successor latest time minus duration.
Total slack is latest timing minus earliest timing under a consistent event or activity convention.
Interpret zero slack carefully
Zero-slack activities form at least one critical path. Critical means a delay transfers to completion under current durations and dependencies; it does not mean costly or technically difficult.
Tied longest paths can create multiple critical routes, and shortening one route may not reduce the project duration while another route still controls completion.
Choose one network convention
Activity-on-node and activity-on-arc drawings place durations differently, yet either supports the timing logic when used consistently. Label every dependency before calculating.
A missing predecessor creates an artificially early start, while an accidental dependency can create a false critical path. Correct arithmetic cannot repair a network that misstates the project.
Read slack as a scheduling resource
Total slack measures delay possible without moving project completion. Free slack measures delay possible without moving the earliest start of an immediate successor.
These quantities can differ. When explaining a change, name the slack measure being used rather than claiming that an activity has spare time in an unspecified sense.
Handle changes directionally
A duration increase changes forward times only along successor paths. Latest-time effects can travel backwards through predecessors when the finish constraint is reconsidered.
Mark the reachable subnetwork, recalculate and identify whether the old critical route remains controlling, a former non-critical route ties it or total duration moves. Report the revised critical set with the new finish time.
What this chapter covers
- 01
Precedence network
- 02
Forward pass
- 03
Backward pass
- 04
Project duration
- 05
Total slack
Worked example · free
Time a parallel merge
- 2Find merge time.
- 1Add successor duration.
- 2Compute parallel slack.
Key terms
- Critical Path
- A Critical Path is a longest precedence route that controls project duration under the current activity times, with zero total slack on its activities and the possibility of tied controlling routes.
- Earliest Time
- Earliest Time is the first feasible occurrence time under predecessor requirements, calculated forward by waiting for the latest required incoming completion at each merge.
- Total Slack
- Total Slack measures permissible activity delay without moving the currently calculated project completion time.
Critical Paths and Project Timing FAQ
Why is the forward merge a maximum?
Every required predecessor must be complete before the merged event can occur. The event therefore waits for the latest incoming completion. A minimum would release the successor after only one predecessor and would contradict the precedence network.
Can a project have several critical paths?
Yes. Two or more routes can tie for the longest duration, giving zero slack along each controlling route. Shortening only one tied route may leave total project duration unchanged because another critical path still reaches the finish at the same time.
Does a critical activity stay critical?
Not necessarily. Critical status follows the current network and duration estimates. A changed duration, added dependency or removed dependency can alter earliest and latest times, move slack between activities and produce a different controlling route.
Exam move
Draw a small activity network, perform the forward pass in one colour and the backward pass in another, then label slack. Change one duration and predict the new critical route before recalculating. Alternate a single critical path with a tied-path network so that zero slack is not treated as unique. For each merge, explain why a maximum is used; for each backward split, explain why a minimum protects every successor.
Keep event times and activity durations in different columns with explicit units. After calculating total slack, compute free slack for one non-critical activity and compare their interpretations. Introduce a delay smaller than total slack, equal to it and greater than it, predicting the effect before updating times. Close each drill with project duration, the complete critical set and one sentence about what changed.
This makes the network a scheduling argument rather than a collection of isolated numbers. Redraw one activity-on-node network using an activity-on-arc convention and confirm project duration is unchanged. Deliberately omit a predecessor, observe the falsely early result and restore the dependency. This negative control reinforces that precedence comes from the model description, not from the visual spacing of nodes.
Practise reporting a tied critical set without singling out only the first longest route found.
Working through Critical Paths and Project Timing in MATH10065? Sia is AskSia’s AI Mathematics tutor — ask any MATH10065 Critical Paths and Project Timing question and get a clear, step-by-step explanation grounded in how MATH10065 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.