BUSI70223 Chap.6 NPV Versus the IRR Rule
NPV Versus the IRR Rule
NPV Versus the IRR Rule examines the most popular rival to NPV. The internal rate of return is the discount rate that makes NPV zero, and accepting projects whose IRR exceeds the cost of capital usually agrees with NPV.
It fails in three ways the module names: for borrowing-type projects the rule must be reversed, projects whose cash flows change sign more than once can have several IRRs or none, and for mutually exclusive projects of different size the higher IRR can belong to the project with the lower NPV. The chapter draws NPV profiles to see each failure and fixes the ranking problem with the IRR on incremental cash flows.
An NPV profile makes every failure visible. A lending project has a profile that falls as the rate rises, a borrowing project has one that rises, and a project with an outflow at both ends can rise and then fall, crossing zero twice. For two projects of different size, the profiles cross at the crossover rate: below it the larger project has the higher NPV, above it the smaller one does.
Reading those shapes takes less time than computing several IRRs.
What this chapter covers
- 01
Internal rate of return
- 02
NPV profiles
- 03
Lending versus borrowing projects
- 04
Multiple IRRs
- 05
Mutually exclusive projects
- 06
Scale and crossover rates
- 07
Incremental IRR
Worked example · free
Rank two projects of different size
- 2IRRs: L earns 20% and S earns 30%, so IRR prefers S.
- 2NPVs at 10%: L = -50,000 + 60,000 / 1.1 = £4,545; S = -10,000 + 13,000 / 1.1 = £1,818.
- 2Incremental flows L minus S are -40,000 and +47,000, an IRR of 17.5%, above 10%, so take L.
Key terms
- Internal rate of return
- The discount rate at which a project's NPV equals zero.
- NPV profile
- A graph of a project's NPV against the discount rate.
- Crossover rate
- The discount rate at which two projects have equal NPVs.
- Incremental cash flows
- The differences between the cash flows of two alternative projects.
NPV Versus the IRR Rule FAQ
Why can a project have two IRRs?
Each change of sign in the cash flows can create another root. A project with an outflow, then an inflow, then a final outflow can have NPV zero at two different rates, so the IRR rule gives no clear answer.
What is the borrowing problem with IRR?
A project that receives cash first and pays later is like a loan. For such a project a higher IRR is worse, so accepting when IRR exceeds the cost of capital rejects good deals and accepts bad ones.
Can IRR ever rank mutually exclusive projects correctly?
Yes, if you apply it to the incremental cash flows of the larger project over the smaller one. Accept the larger project when the incremental IRR exceeds the cost of capital.
What is the crossover rate?
It is the discount rate at which two projects have equal NPVs, and equivalently the IRR of their incremental cash flows. At rates below it the larger project wins; above it the smaller one does.
Is IRR useless then?
No. For a single conventional project with one sign change, IRR and NPV give the same accept or reject answer. It becomes unreliable for borrowing projects, multiple sign changes and choices between projects of different scale.
Why does the borrowing problem reverse the IRR rule?
For a project that receives cash first and pays later, a higher discount rate makes the later payment cheaper in present value, so NPV rises with the rate. Accepting when IRR is above the cost of capital therefore picks the wrong side of the decision.
Exam move
Sketch NPV profiles for a lending project, a borrowing project and a two-root project until you can recognise each shape from the cash-flow signs alone. For every mutually exclusive pair, compute both NPVs, both IRRs and the crossover rate. The example exams pair a calculation with a short explanation of which IRR problem applies, so practise naming the problem in one sentence.
Make a habit of counting sign changes in a cash-flow series before computing an IRR; more than one change warns of multiple roots. For ranking questions, write the incremental flows of the larger project over the smaller one on a separate line and compute their IRR, which settles the choice in one step. Under time pressure, compute NPV first and use IRR only to answer the part of the question that asks for it.
Working through NPV Versus the IRR Rule in BUSI70223? Sia is AskSia’s AI Finance tutor — ask any BUSI70223 NPV Versus the IRR Rule question and get a clear, step-by-step explanation grounded in how BUSI70223 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.