University of Adelaide · S1 2026 · FACULTY OF ENGINEERING

ENGI5003 · Professional Engineering Management

- one subject, every graph, every model, every mark
50% final exam · hurdle14 Chapters8-page Bible
Our own words - no uploaded lecturer files
Built to mirror S1 2026 · updated this semester
Chapter 8 of 8 · ENGI5003

Project Control: EVM, Closure & Reflection

This is the flagship quantitative chapter of ENGI 5003: it covers Earned Value Management — turning the three inputs PV, EV and AC into the four control numbers CV, SV, CPI and SPI — plus schedule modifications, completion forecasts, and the standard ways projects are formally closed and reflected on. Almost every Part-C long-answer question is an EVM table you must build then interpret, so the rule negative variance or index below 1 = bad, reported for both cost and schedule, is the single highest-value thing to lock in before a closed-book exam.

In this chapter

What this chapter covers

  • 01The three EVM inputs: PV (budget x scheduled%), EV (budget x actual%), AC (cash paid)
  • 02The four metrics: CV = EV-AC, SV = EV-PV, CPI = EV/AC, SPI = EV/PV
  • 03Sign & index rules + the four-quadrant cost/schedule verdict
  • 04The completion family: BAC, ETC, EAC, VAC and Management Reserve
  • 05Schedule modifications & forecasts: EAC two ways, TCPI, SPI time update
  • 06Milestone Trend Analysis as a schedule-only check
  • 07Larson & Gray's five closure types and the closure tasks
  • 08Critical reflection: What/So-what/Now-what and the 4 Rs
Worked example · free

EVM snapshot — read CV, SV, CPI and SPI from a task table

Q [6 marks]. At the audit date a small fit-out package has three tasks. Task A: budget $20k, scheduled 100%, actual 100%, paid $22k. Task B: budget $15k, scheduled 100%, actual 60%, paid $10k. Task C: budget $10k, scheduled 80%, actual 40%, paid $6k. Compute PV, EV and AC, then the four control metrics and state the verdict.
  • +1Planned Value (budget x scheduled%): PV = 20(1.0) + 15(1.0) + 10(0.8) = 20 + 15 + 8 = $43k.
  • +1Earned Value (budget x actual%): EV = 20(1.0) + 15(0.6) + 10(0.4) = 20 + 9 + 4 = $33k.
  • +1Actual Cost (cash paid): AC = 22 + 10 + 6 = $38k.
  • +1Schedule: SV = EV - PV = 33 - 43 = -$10k; SPI = EV/PV = 33/43 = 0.77 — both say behind schedule (negative, <1).
  • +1Cost: CV = EV - AC = 33 - 38 = -$5k; CPI = EV/AC = 33/38 = 0.87 — both say over budget (negative, <1).
  • +1Verdict: negative variances and indices below 1 on both axes — the package is behind schedule AND over budget (bottom-left quadrant); recommend a recovery plan and re-baseline review.
PV = $43k, EV = $33k, AC = $38k; SV = -$10k, SPI = 0.77, CV = -$5k, CPI = 0.87 — behind schedule and over budget.
Glossary

Key terms

Planned Value (PV)
The budgeted cost of the work scheduled by the audit date — how much value the baseline said you should have produced. PV = task budget x scheduled % complete.
Earned Value (EV)
The budgeted cost of the work actually performed, priced at plan. EV = task budget x actual % complete, and an activity's EV can never exceed its own budget (PV).
Cost Performance Index (CPI)
CPI = EV / AC, the value earned per dollar spent. CPI > 1 is efficient/under budget; CPI < 1 is wasteful/over budget; the dollar form is CV = EV - AC.
Schedule Performance Index (SPI)
SPI = EV / PV, the value earned per dollar of planned work. SPI > 1 is ahead of schedule; SPI < 1 is behind; the dollar form is SV = EV - PV (measured in dollars, not weeks).
Estimate At Completion (EAC)
The forecast final cost. EAC_O = BAC - CV assumes remaining work runs to plan (optimistic); EAC_R = BAC / CPI assumes today's cost performance continues (usually more realistic). VAC = BAC - EAC.
Closure types (Larson & Gray)
The five standard ways a project ends: Normal (delivered as planned), Premature (deliberately cut short with partial scope), Perpetual (never truly ends from scope creep), Failed (abandoned, cannot meet objectives), Changed-priority (resources pulled by the organisation).
FAQ

Project Control: EVM, Closure & Reflection FAQ

What is the difference between CV/SV and CPI/SPI in EVM?

The variances are in dollars (a subtraction): CV = EV - AC and SV = EV - PV. The indices are dimensionless ratios: CPI = EV/AC and SPI = EV/PV. Both pairings work the same way — schedule is always EV against PV, cost is always EV against AC — and for either form, negative variance or an index below 1 means trouble.

How do I know if a project is behind schedule or over budget from EVM numbers?

Compute EV first. If SV < 0 or SPI < 1 you are behind schedule; if CV < 0 or CPI < 1 you are over budget. Always report both dimensions: mixed signs are common — behind but under budget often means under-resourced, while ahead but over budget often means you threw money at speed.

Why is SPI measured in dollars when schedule is about time?

EVM values everything at planned cost, so SV/SPI describe the dollar value of the schedule gap, not the number of weeks late. To convert a slip into time you use the schedule index over the critical path: ED(1) = OD / SPI_crit.

Does a Failed or Changed-priority project still get closed properly?

Yes. The closure type only describes how it ends; every type still runs the same closure tasks — finish, hand over, gain acceptance of what exists, document, archive, review and disband. Skipping lessons learnt or the archive on a failed project is a classic mark-losing assumption.

What reflective model should I use for the Project Reflection?

Two standard models are taught: 'What / So what / Now what' (describe, analyse, evaluate) for a quick structure, and the 4 Rs (Report & Respond, Relate, Reason, Reconstruct) for a deeper link to theory and re-planning. Write in the first person — it is an Engineers Australia Stage-1 competency.

Study strategy

Exam move

Treat the EVM table as a mechanical drill you can do half-asleep: lock the three columns (PV = scheduled%, EV = actual%, AC = cash), sum each, then turn the handle on CV/SV and CPI/SPI. Practise re-deriving five different small tables until the four metrics fall out without thinking, because the formula sheet gives you the equations but the marks live in the interpretation — always state both cost AND schedule, and translate the numbers into a verdict and a control action. For the forecast layer, memorise the two EAC routes (BAC-CV optimistic vs BAC/CPI realistic) and which assumption each makes. For close-out, learn the five closure types as distinct definitions (don't confuse Premature with Failed or Perpetual) and the 7 closure tasks as one chain that applies to every type, then have one reflective model (What/So-what/Now-what) ready to deploy.

A+Everything unlocked
Unlocks this Bible + all 9 of your University of Adelaide subjects - and 1,000+ Bibles across every Australian university.
Sia - your ENGI5003 tutor, unlimited, worked the way the exam marks it
The full 8-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$25/ month
30-day money-back · cancel in one tap · how it works
Unlock the full ENGI5003 Bible + 9 University of Adelaide subjects解锁完整 ENGI5003 Bible + University of Adelaide 9 门科目
$25/mo