Lean Flow, Pull and Takt Time

Lean Flow, Pull and Takt Time covers the Toyota Production System and the arithmetic that makes flow work. The house of just in time and jidoka, resting on levelled production, standard work and kaizen, frames the eight wastes and the contrast between push and pull release.

The calculations follow: Little's law linking work in process, throughput and lead time; takt time from available time and demand; the minimum number of operators and the stations each step needs, with and without availability losses; kanban card counts with a safety factor; and Kingman's approximation, which shows queue time multiplying as utilisation approaches one and shrinking as variability falls.

The chapter ends with release control by kanban, CONWIP, drum-buffer-rope and POLCA, and with the factory physics benchmarks that compare a line with its best and practical worst cases.

In this chapter

What this chapter covers

  • 01

    The Toyota Production System house

  • 02

    Push and pull release

  • 03

    The eight wastes

  • 04

    Little's law

  • 05

    Takt time and station counts

  • 06

    Kanban sizing

  • 07

    Kingman's approximation and release control

Worked example · free

Size a kanban loop and check its lead time

Q [5 marks]. A cell uses 180 housings per day. Replenishment takes 0.4 day, the safety factor is 0.10 and a container holds 15. Find the number of cards and, using Little's law, the lead time implied if the loop holds its full authorised stock. The marks used here suggest relative effort only and are not an official university scheme.
The utilisation factor u/(1 − u) multiplies queue time: modest at 50 per cent, four times the process time at 80 per cent and nineteen times at 95 per cent.The utilisation factor u/(1 − u) multiplies queue time: modest at 50 per cent, four times the process time at 80 per cent and nineteen times at 95 per cent.4× at 80%9× at 90%19× at 95%utilisation uu/(1 − u)
The utilisation factor u/(1 − u) multiplies queue time: modest at 50 per cent, four times the process time at 80 per cent and nineteen times at 95 per cent.
  • 1Demand during the loop time is 180 × 0.4 = 72 housings.
  • 1With the safety factor, 72 × 1.10 = 79.2 housings.
  • 1Cards needed are ⌈79.2/15⌉ = ⌈5.28⌉ = 6, authorising 90 housings.
  • 1At a throughput of 180 per day, 90 housings represent 90/180 = 0.5 day of lead time.
  • 1That is an upper bound: average stock in the loop is usually lower than the authorised maximum.
Six cards authorise 90 housings, at most half a day of stock at current demand.
Sia tip — Round the card count up, then recompute the authorised stock from the rounded number; quoting 79.2 housings as the cap is a common slip.
Glossary

Key terms

Jidoka
Building in quality by stopping a process automatically or manually when an abnormality appears.
CONWIP
A release rule that holds total work in process on a line at a fixed level.
Coefficient of variation
Standard deviation divided by mean, used for arrival and service variability.
Takt time
Available working time divided by customer demand over the same period, the pace at which finished units are needed.
Little's law
Average work in process equals average throughput multiplied by average flow time, for any stable system.
FAQ

Lean Flow, Pull and Takt Time FAQ

Is takt time the same as cycle time?

No. Takt is a demand rate, how often the customer needs one unit. Cycle time in factory physics is how long a unit spends in the system. Little's law links lead time to work in process, not to takt.

Why do queues grow so quickly near full utilisation?

Queue time scales with u/(1 − u). At 80 per cent the factor is four, at 90 per cent nine and at 95 per cent nineteen, so the last few points of utilisation cost far more waiting than the first.

Which waste matters most?

The slides single out overproduction, because making more than needed creates other wastes: extra inventory to move, store, count and possibly scrap. Removing it often removes several others at once.

How do I use Little's law in a numerical question?

Identify two of the three quantities and solve for the third, keeping the units consistent. If the line holds 120 parts and completes 40 an hour, a part spends three hours inside on average. The law needs only stability, so it applies even when the arrival and service patterns are unknown.

Study strategy

Exam move

Learn the four quantities first, process time, lead time, takt and throughput, and never let them blur; the lecture's own list of common mistakes starts there. Then practise the equations in a fixed order: Little's law, takt, minimum operators, stations per step with utilisation, stations with availability, kanban cards and Kingman queue time. Do each with your own numbers and write the units beside every line.

Next, practise the qualitative items: name the waste in a short scenario, classify a system as push or pull, and say which release method suits a given shop. Finally, rework the integrated problem from the lecture without notes, because it chains several equations together exactly as an exam question would, and finish with a sentence on what the numbers mean for the line.

The quiz on Lectures 1 to 5 covers this material, so rehearse it before the quiz window closes. Work the takt time, Little's law and Kingman calculations on the same small line so you see how they connect. Then change utilisation in steps towards one and tabulate the queue time, because the shape of that table is the main argument for buffers and variability reduction.

Working through Lean Flow, Pull and Takt Time in ENG5096? Sia is AskSia’s AI Engineering tutor — ask any ENG5096 Lean Flow, Pull and Takt Time question and get a clear, step-by-step explanation grounded in how ENG5096 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 26 of your subjects at University of Glasgow, plus 1,000+ more Bibles across the AskSia library.
Sia - your ENG5096 tutor, unlimited, worked the way the exam marks it
The full 5-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works