ENG5096 Chap.10 Scheduling and Manufacturing System Models
Scheduling and Manufacturing System Models
Scheduling and Manufacturing System Models decides the order of work on each resource once planning has said what to make. The three-field notation α | β | γ names the machine environment, the constraints and the objective, and the chapter defines completion time, lateness, tardiness, flow time and makespan.
Single-machine rules each optimise one measure: shortest processing time for total completion, earliest due date for maximum lateness, weighted shortest processing time for weighted completion, and Moore–Hodgson for the number of late jobs. Johnson's rule solves the two-machine flow shop exactly, while longest processing time first is a heuristic for parallel machines with a proven worst-case ratio.
The chapter also covers why larger problems are hard, how queue pooling cuts waiting, how levelled sequences are scored and how rank order clustering forms manufacturing cells.
What this chapter covers
- 01
Three-field notation
- 02
Lateness, tardiness and makespan
- 03
SPT, EDD, WSPT and Moore–Hodgson
- 04
Johnson's rule for two machines
- 05
LPT and the Graham bound
- 06
Complexity and heuristics
- 07
Pooling, levelling and cell formation
Worked example · free
Schedule five jobs by earliest due date and count the late ones
- 1EDD order sorts by due date: E (2), A (3), C (5), B (8), D (15).
- 1Completion times are 1, 3, 6, 10 and 15.
- 1Lateness values are 1 − 2 = −1, 3 − 3 = 0, 6 − 5 = 1, 10 − 8 = 2 and 15 − 15 = 0.
- 1Maximum lateness is 2, set by job B.
- 1Jobs C and B finish after their due dates, so two jobs are late.
Key terms
- Makespan
- The completion time of the last job in a schedule.
- Flow shop
- A shop in which every job visits the machines in the same order.
- Graham bound
- The guarantee that LPT makespan is at most 4/3 − 1/(3m) times the optimum.
- Tardiness
- How late a job finishes relative to its due date, counted as zero when it finishes early.
- Dispatching rule
- A simple priority rule, such as shortest processing time or earliest due date, used to choose the next job.
Scheduling and Manufacturing System Models FAQ
Which rule should I use on a single machine?
Choose by the objective. Shortest processing time minimises total completion time, earliest due date minimises maximum lateness, and Moore–Hodgson minimises the number of late jobs. None of them guarantees minimum total tardiness.
When is Johnson's rule optimal?
For a two-machine flow shop minimising makespan, with unlimited buffer and no pre-emption. Blocking, no-wait conditions or sequence-dependent set-ups can change the answer, and three machines make the problem hard.
How can I prove a schedule is optimal in the exam?
Show that it reaches a valid lower bound. For parallel machines the bound is the larger of the longest job and the total work divided by the number of machines; for a two-machine flow shop it involves the shortest first and last operations.
Which rule should I try first on parallel machines?
Longest processing time first is the usual starting point for makespan: sort the jobs from longest to shortest and give each to the machine that frees up first. Then compare the result with the lower bound to show how close it is.
Exam move
Start by classifying problems in three-field notation until it is second nature, because the 2019 paper gave eight marks for the model and twelve for explaining the symbols. Write the definitions of completion, lateness, tardiness, flow time and makespan with a tiny example of each. Then drill the rules on five-job sets: compute every measure for SPT, EDD and Moore–Hodgson and confirm that each rule wins on its own objective.
Practise Johnson's rule with a Gantt chart, marking idle time on the second machine and checking the lower bound. Do the same for LPT on two and three machines, and compare the ratio with the Graham guarantee. Finally, rehearse the qualitative ideas: why the number of sequences explodes, why pooling queues helps and how rank order clustering finds cells.
The lecture flags the combined LPT and Johnson problem as exam style, so redo it without notes. Write the three-field notation for each worked problem before solving it, so you can match the rule to the setting. Then time yourself on one single-machine, one flow-shop and one parallel-machine question, and always end by comparing your answer with a bound.
Keep a short list of which rule is optimal for which objective, so you can justify your choice in one line.
Working through Scheduling and Manufacturing System Models in ENG5096? Sia is AskSia’s AI Engineering tutor — ask any ENG5096 Scheduling and Manufacturing System Models question and get a clear, step-by-step explanation grounded in how ENG5096 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.