University of Glasgow · FACULTY OF ENGINEERING

ENG5096 Chap.9 Bills of Materials, MRP and ERP

- one subject, every graph, every model, every mark
7 Chapters5-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 9 of 15 · ENG5096

Bills of Materials, MRP and ERP

Bills of Materials, MRP and ERP explains how a plan for finished products becomes orders for every part. A bill of materials lists parents, children and quantities per parent across levels, with low-level codes so shared items are planned once. Explosion multiplies quantities down the tree, inflating only the branches that scrap output and rounding packs up before recomputing stock.

The material requirements planning record nets gross requirements against stock, scheduled receipts and safety stock, sizes the planned receipt and offsets the release by the lead time. Lot-sizing rules from lot for lot to economic order quantity, periodic order quantity, Silver–Meal and Wagner–Whitin trade ordering cost against holding cost. Safety stock and reorder points protect independent demand.

The chapter closes with capacity checks, time fences, the layers of MRP II, ERP and MES, and lessons from failed implementations.

In this chapter

What this chapter covers

  • 01

    Parents, children and low-level codes

  • 02

    Explosion, yield and pack rounding

  • 03

    The MRP record row by row

  • 04

    Offsetting and past-due releases

  • 05

    Lot-sizing rules compared

  • 06

    Safety stock and reorder point

  • 07

    MRP II, ERP, MES and implementation risk

Worked example · free

Plan a component with safety stock and a pack size

Q [5 marks]. Gross requirements are 150 in week 2 and 220 in week 4. On hand is 180, safety stock is 40, the pack size is 100 and lead time is 1 week. Find planned receipts and releases. The marks shown are for pacing practice and not a university allocation.
A three-level tree for an e-scooter: each box shows the quantity needed per parent, so one scooter needs two wheel sets and therefore four bearings.A three-level tree for an e-scooter: each box shows the quantity needed per parent, so one scooter needs two wheel sets and therefore four bearings.e-scooterdeck frame ×1wheel set ×2tube ×3bracket ×4bearing ×2level 0level 1level 2
A three-level tree for an e-scooter: each box shows the quantity needed per parent, so one scooter needs two wheel sets and therefore four bearings.
  • 1Week 2: net requirement is 150 + 40 − 180 = 10, so one pack of 100 is received.
  • 1Projected on hand after week 2 is 180 + 100 − 150 = 130.
  • 1Week 4: net requirement is 220 + 40 − 130 = 130, so two packs, 200, are received.
  • 1Projected on hand after week 4 is 130 + 200 − 220 = 110, above the safety stock.
  • 1Offsetting by one week, releases are 100 in week 1 and 200 in week 3.
Receive 100 in week 2 and 200 in week 4, releasing them in weeks 1 and 3.
Sia tip — Add safety stock to the gross requirement inside the net requirement formula, and recompute projected stock after rounding up to packs.
Glossary

Key terms

Low-level code
The deepest level at which an item appears in any bill, used to plan it once.
Scheduled receipt
An order already released and due to arrive, unlike a planned receipt.
Time fence
A boundary in the plan inside which changes are restricted or frozen.
Gross requirement
The total quantity of an item needed in a period, before on-hand stock and scheduled receipts are netted off.
Lot sizing
The rule that turns net requirements into planned orders, such as lot for lot, fixed quantity or economic order quantity.
FAQ

Bills of Materials, MRP and ERP FAQ

Where does a child's gross requirement come from?

From the parent's planned order releases, not the parent's gross requirements. Planning level by level from the finished product downward keeps the timing right and avoids counting demand twice.

Why does EOQ sometimes perform badly in MRP?

It assumes steady demand. When weekly requirements are lumpy, with zeros and spikes, a fixed economic quantity leaves stock sitting idle or forces extra orders, and period-based rules usually cost less.

What is the difference between cycle service and fill rate?

Cycle service level counts the share of replenishment cycles without a stock-out. Fill rate counts the share of demand met from stock. A modest cycle service level can still give a high fill rate.

What is the most common error in an MRP table?

Forgetting lead-time offsetting or mixing up periods. A planned order receipt in one period must appear as a planned order release one lead time earlier, and the release of a parent becomes the gross requirement of its children in that same period, multiplied by the quantity per parent.

Study strategy

Exam move

Draw two or three bills of materials from scratch, label levels and quantities per parent, and explode them for a stated quantity, adding a yield on one branch and a pack size on another. Then drill the MRP record until each row is automatic: gross requirement, scheduled receipt, projected on hand, net requirement, planned receipt, planned release.

Work a two-level problem where the parent's releases feed the child, and look out for a release that lands before the current week, which signals an infeasible plan. Next, compare lot-sizing rules on one demand stream by computing ordering and holding cost for each, and explain why the cheapest one won. Practise safety stock with fixed and variable lead time, and state the service level used.

Finally, prepare a short paragraph on ERP implementation risk, data, people and fit, because definition and judgement questions sit alongside the calculations in this block. Complete at least two MRP tables by hand with different lot-sizing rules and compare the stock carried. Then check each row's arithmetic by reading down the column for a single period, because one wrong netting step spreads through every lower level.

Working through Bills of Materials, MRP and ERP in ENG5096? Sia is AskSia’s AI Engineering tutor — ask any ENG5096 Bills of Materials, MRP and ERP question and get a clear, step-by-step explanation grounded in how ENG5096 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 26 of your subjects at University of Glasgow, plus 1,000+ more Bibles across the AskSia library.
Sia - your ENG5096 tutor, unlimited, worked the way the exam marks it
The full 5-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works