Critical Path, Float and PERT Scheduling

Critical Path, Float and PERT Scheduling teaches the calculation behind every serious programme. Critical path analysis takes activities, durations, dependencies and logical end points and finds the longest chain through them, which sets the shortest possible project duration. Activities on that chain are critical; others carry total float and can slip without delaying completion.

The chapter works the forward pass for earliest dates and the backward pass for latest dates on an original footbridge network, then shows the same results against a time scale so that float becomes visible. PERT is introduced as a complementary technique, more event and time oriented, that may use optimistic, expected and pessimistic estimates instead of one figure, and suits complex, non-routine infrastructure.

Programme realities complete the picture: overlapping tasks, lead-in times, planning approval periods, contingency, weather and curing, redeployment of resources and the commercial question of who owns float after a fixed-price tender. Delays, claims and changes are covered last, because most claims arise when something in the contract changes.

The chapter equips you to explain why one late delivery matters and another does not.

In this chapter

What this chapter covers

  • 01

    Critical path definition and inputs

  • 02

    Forward pass for earliest start and finish

  • 03

    Backward pass for latest start and finish

  • 04

    Total float and merge points

  • 05

    Reading float on a time-scaled chart

  • 06

    PERT and three time estimates

  • 07

    Tender programmes, delays and claims

Worked example · free

Find the critical path of a footbridge replacement

Q [6 marks]. Survey A (2 weeks) starts the job. Design B (3) and steel order C (5) follow A. Temporary works D (2) follow B and removal E (2) follows D. New deck F (3) needs both C and E, and handover G (1) follows F. Find the duration, the critical path and the float on C. The 6 marks used here are a study weighting of our own and are not an official assessment scheme.
The footbridge activities drawn against weeks 0 to 13: critical activities A, B, D, E, F and G join end to end in orange, and steel order C ends at week 7 with The footbridge activities drawn against weeks 0 to 13: critical activities A, B, D, E, F and G join end to end in orange, and steel order C ends at week 7 with a dashed tail to week 9 marking its two weeks of total float.ABtotal floatCDEFG051013weeks
The footbridge activities drawn against weeks 0 to 13: critical activities A, B, D, E, F and G join end to end in orange, and steel order C ends at week 7 with a dashed tail to week 9 marking its two weeks of total float.
  • 2Forward pass: A 0 to 2, B 2 to 5, C 2 to 7, D 5 to 7, E 7 to 9.
  • 1F starts at the later of 7 and 9, so it runs 9 to 12, and G runs 12 to 13; the duration is 13 weeks.
  • 2Backward pass from week 13: G starts at 12, F at 9, E at 7, D at 5 and B at 2; C must finish by 9, so its latest start is 4.
  • 1C has 4 minus 2 = 2 weeks of float, and the critical path is A, B, D, E, F, G.
The bridge takes 13 weeks along A, B, D, E, F and G, and the steel order can slip by up to 2 weeks without delaying handover.
Sia tip — At a merge such as F, take the later incoming finish going forward and hand the same latest start back to every branch going backward.
Glossary

Key terms

Critical path
The sequence of activities with the longest total duration, which fixes the shortest project time.
Total float
How long an activity may be delayed while the completion date stays unchanged.
Forward pass
The calculation of earliest start and finish dates from the project start.
PERT
A scheduling technique that may use three time estimates for each activity.
FAQ

Critical Path, Float and PERT Scheduling FAQ

Is the critical path the most important work on the project?

Not necessarily. It is defined by duration: the chain of activities that adds up to the longest overall time. A modest activity such as a steel delivery can become critical if its lead time grows, while a prominent activity may sit comfortably off the path.

How does PERT differ from the critical path method?

Critical path analysis uses a single time and cost estimate for each activity. PERT is more event and time oriented and may use optimistic, expected and pessimistic time estimates without cost estimates. The two are complementary and are often combined in project management software.

Why does float matter commercially?

A contractor that wins a fixed-price job on a set number of weeks can negotiate shorter or cheaper packages with its subcontractors, building float into its own programme. Who holds that float then affects how delays and claims are argued later.

Study strategy

Assessment move

Practise the passes until they are mechanical, then spend your effort on interpretation. Draw small networks of six to eight activities with at least one merge and one burst, and work the forward pass in one colour and the backward pass in another. Always compute total float as latest start minus earliest start, and check that every critical activity shows zero.

Next, change one duration and predict the effect before recalculating: will the path move, will a float grow or shrink, will the finish week change? Redraw a solved network against a time scale, with float shown as dashed tails, because that view is the one clients understand. For PERT, be ready to explain when three estimates are worth the effort, for example on non-routine infrastructure with uncertain durations.

Collect a short list of programme realities from the lecture, such as approval periods, curing times, lead-in times and two to three weeks of contingency, and ask how each would appear in a network. In the presentation, a few sentences on which tram work packages are likely to be critical, and why, will strengthen the planning and control evaluation far more than a long activity list.

Working through Critical Path, Float and PERT Scheduling in CIVE5172M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5172M Critical Path, Float and PERT Scheduling question and get a clear, step-by-step explanation grounded in how CIVE5172M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5172M tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
CIVE5172M · Project Management Tools and Techniques - independent study guide on the AskSia Library. More University of Leeds subjects · Microeconomics across all universities