CIVE5360M Overview

Procurement Management
— choose a contract strategy you can defend, then run it through NEC4
  • Postgraduate module
  • University of Leeds
  • Semester 1 2026/27
  • School of Civil Engineering
  • Coursework and examination

A module about deciding how to buy construction

CIVE5360M Procurement Management is a postgraduate module in the School of Civil Engineering at the University of Leeds, taught on Fridays in Semester 1 of 2026/27 through lectures, seminars or workshops and independent study. It covers two broad topics.

  • Assessed by Coursework and a January examination, 50% each.
  • Hardest step Linking a strategy decision to the NEC4 mechanism that delivers it.
  • Key case The Holyrood Inquiry on route choice, selection and fees.
  • How to prepare Plan each seminar question as explain, evidence, judge, act.
CIVE5360M · University of Leeds
An independent, AskSia-authored study guide. AskSia is not affiliated with, endorsed by, or sponsored by University of Leeds; the course code and name are used for identification only.
Assessment

How CIVE5360M is assessed

ComponentWeightFormat
Coursework50%Assesses learning outcomes 1 and 2. Brief published 2 October 2026; submit by 14:00 on 3 December 2026.
Examination50%Assesses learning outcomes 3 and 4. Scheduled in the Semester 1 examination period, January 2027.

The module page gives both weights, which total 100%. The module mark is the weighted average of the coursework and examination marks; if it is below 50%, you resit the component or components that scored below 50%. Examination length and permitted materials are confirmed through the examination timetable and Minerva.

Assessment structure

50%50%Coursework, due 3 DecemberExamination, January 2027

Segment widths reproduce the published weights: the coursework and the January examination each carry half of the module mark.

Current dates · verify in LMS

Current CIVE5360M dates

DateItemControl
2 October 2026Coursework brief publishedReleased at the start of teaching in Week 1.
3 December 2026Coursework deadlineSubmit by 14:00.
January 2027ExaminationSemester 1 examination period; check your personal timetable.

Dates are as published in the 2026/27 module assessment overview. Confirm exact deadlines and submission settings in the live LMS.

Contents · every chapter, one map

What CIVE5360M covers

Eight chapters follow the Friday schedule: six on contract strategy, from competence and roles to payment, selection, social value and decision making, then two on how NEC4 manages time, quality, payment and change.

01

Procurement Management and Competence

Lectures 1 and 2 and the Week 2 seminar: client competence, the Holyrood client bodies, procurement rules and independent advice.

Procurement Management and Competence opens the module with two Week 1 lectures, an introduction to procurement management and competence in procurement management, followed in Week 2 by a seminar that asks you to comment on competence with reference to Otim and colleagues (2025), Kyalisiima and colleagues (2024) and Fraser (2004).

  • What procurement management covers in this module
  • Competence as a property of the client organisation
  • The three Holyrood client bodies and their gaps
  • Construction experience versus political acumen
  • Knowledge of procurement rules as a leadership condition
  • Independent advice that reaches decision makers
02

Contract Strategy: Definitions, Roles and Responsibilities

Lectures 3 and 4: antecedents of a strategy, traditional and construction management routes, sponsor, project manager and NEC supervisor roles.

Contract Strategy: Definitions, Roles and Responsibilities covers the Week 2 lectures on what a contract strategy is, what comes before it and who does what once it is chosen.

  • Contract strategy as linked choices
  • Four antecedents of a strategy
  • Traditional contracting and construction management defined
  • Project owner, sponsor and manager
  • NEC project manager and supervisor
  • Collaboration between professional disciplines
03

Payment Methods and Sources of Funds

Lectures 5 and 6: NEC main payment options, percentage, lump sum and tapered fees, guaranteed maximum price and private versus public funding.

Payment Methods and Sources of Funds covers the Week 3 lectures on how contractors and consultants are paid and where project money comes from.

  • NEC main payment options
  • Percentage fees and cost overruns
  • Lump sum conversion as an incentive
  • Tapered and capped fees
  • Guaranteed maximum price late in a project
  • Private finance versus conventional funding
04

Contractor Selection and Contracting Culture

Lectures 7 and 8: restricted procedure, value for money, tender adjustment, post-tender change, debriefs and a no-surprises culture.

Contractor Selection and Contracting Culture covers Lecture 7 on how a client chooses a contractor and Lecture 8 on the culture the parties then share.

  • Restricted procedure and pre-qualification
  • Value for money rather than lowest price
  • Adjusting tenders to a comparable basis
  • Post-tender change and fairness
  • Due diligence, warranties and debriefs
  • Collaborative and adversarial contracting cultures
05

Supply Chain Management and Social Value

Lecture 9 and seminars 6 to 11: the Social Value Act, National TOMs themes, proxy values, priority weights and local supply chain spend.

Supply Chain Management and Social Value combines Lecture 9 on supply chain management with the three seminar pairs in Weeks 4 to 6 on the economic, environmental and social impacts of construction projects and how procurement can manage them.

  • The Social Value Act and a minimum reporting standard
  • Themes, outcomes and measures
  • Proxy values and fixed units
  • Priority weighting for bid selection only
  • Local value versus social value
  • Supply chain spend and carried-down commitments
06

Contract Strategy Decision Making

Lectures 10 and 11: weighting cost, time and quality, the risk spectrum of routes and the Holyrood decision record.

Contract Strategy Decision Making covers the two Week 6 lectures that close the strategy half of the module.

  • Holyrood cost and time record
  • How the route decision was taken and recorded
  • Treasury guidance on weighting objectives
  • The risk spectrum from private finance to construction management
  • Conditions for construction management to work
  • Recommendation 3 and the route of last resort
07

NEC4 Principles, Disputes, Scope and Contract Data

Lectures 12 to 15: the NEC family, clauses 10.1 and 10.2, early warning, clause 63.7, the scope under clause 20.1 and document quality.

NEC4 Principles, Disputes, Scope and Contract Data covers Lectures 12 to 15 in Weeks 7 and 8. It introduces the NEC family, which began as the New Engineering Contract in 1991 and reached NEC4 in June 2017, and its three drafting principles of clarity, flexibility and a stimulus to good project management.

  • The NEC family of contracts
  • Clarity, flexibility and good project management
  • Layers of the Engineering and Construction Contract
  • Clauses 10.1 and 10.2
  • Early warning and clause 63.7
  • The scope under clause 20.1
08

NEC4 Time, Quality, Payment and Compensation Events

Lectures 16 to 21: the accepted programme, testing and defects, payment assessment, compensation events and security at the outset.

NEC4 Time, Quality, Payment and Compensation Events covers Lectures 16 to 21 in Weeks 9 to 11. It explains why the accepted programme sits at the heart of an NEC contract: it must be accepted or rejected for a stated reason, updated normally at least monthly, and used as the basis for assessing every compensation event, with clause 64.1 applying when none is in place.

  • Compensation events and clause 60.1
  • Forecast assessment on Defined Cost
  • The accepted programme and clause 64.1
  • Timescales instead of reasonable time
  • Supervisor testing and defects
  • Payment assessment and the final account

The first, contract strategy, runs from Week 1 to Week 6 and asks how a client should organise itself and its project before any contract is signed: what competence it needs, who holds which role, how the contractor and consultants will be paid, where the money comes from, how a contractor is selected, what culture the parties will share and how the final choice of route is made.

The second topic, NEC4 contracts, runs from Week 7 to Week 11 and studies one family of standard contracts in detail, from its principles and dispute avoidance to the scope, contract data, time, quality, payment, compensation events, liabilities, insurance and termination.

Readings that carry the argument

Three readings supplied with the module do much of the teaching here.

Lord Fraser's 2004 Holyrood Inquiry report is a public record of how a procurement route was chosen for the Scottish Parliament building and what followed, including estimated costs that rose to £431m. The National TOMs 2019 guidance sets out themes, outcomes and measures for valuing social value, with a proxy value for each measure.

An introductory guide to NEC contracts explains the family, its three principles and the processes behind early warning, the accepted programme and compensation events. Each Friday morning seminar sets a question in a recognisable pattern: explain an impact or a provision, then show how procurement can manage it or what challenges it will meet. This guide follows that pattern chapter by chapter.

Worked example · free

Value a targeted recruitment offer with National TOMs proxies

Q [5 marks]. A contractor bidding for a council road scheme offers 3 local FTE jobs, 2 of them for people who were long-term unemployed, plus 1 FTE job for a person with a disability. Using the printed proxies (NT1 £28,758, NT3 £15,085.95, NT6 £13,234.70), value the offer and say how it should be reported. The marks shown are an AskSia practice weighting, not an official University allocation.
Each bar is the printed proxy value for one full-time job measure; a local hire is valued at roughly 1.8 to 2.3 times each targeted-hire measure, but the guidanEach bar is the printed proxy value for one full-time job measure; a local hire is valued at roughly 1.8 to 2.3 times each targeted-hire measure, but the guidance reports it separately as local rather than societal value.NT1 local job£28,758NT3 long-term unemployed£15,085.95NT4 NEET hire£12,776.32NT5 young offenders£15,856.88NT6 disability job£13,234.70proxy value per FTE employee
Each bar is the printed proxy value for one full-time job measure; a local hire is valued at roughly 1.8 to 2.3 times each targeted-hire measure, but the guidance reports it separately as local rather than societal value.
  • 1Local jobs under NT1: 3 × £28,758 = £86,274, reported as local value rather than social value.
  • 1Long-term unemployed hires under NT3: 2 × £15,085.95 = £30,171.90; the guidance lets these jobs count under NT1 as well.
  • 1Disability job under NT6: 1 × £13,234.70 = £13,234.70.
  • 1Social value = £30,171.90 + £13,234.70 = £43,406.60.
  • 1Report £43,406.60 of social value and £86,274 of local value separately, unweighted, with evidence such as employee postcode districts.
The offer carries £43,406.60 of social value under NT3 and NT6 and £86,274 of local value under NT1, reported as two separate figures.
Sia tip — Keep two running totals from the first line: one for social value and one for local value. Merging them is the quickest way to overstate an offer.
Glossary

Key terms

Contract strategy
The linked set of choices for a project covering procurement route, payment option, design responsibility and allocation of risk.
Construction management
A fast-track route in which trade packages are contracted directly to the client while a fee-earning consultant programmes and co-ordinates them.
Traditional contracting
A route where design is substantially complete before construction is tendered and one contractor then builds the works.
Project sponsor
The client-side role answerable for delivering the project to agreed time, budget and quality on the client's behalf.
Contract strategy report
A written evaluation of options, their risks and a reasoned recommendation, prepared before a route is chosen.
Social value
Additional economic, social or environmental benefit a contract delivers beyond business as usual, measured in TOMs through proxies.
Proxy value
A pound figure per unit of a TOMs measure, used to monetise activity such as jobs, apprenticeship weeks or carbon saved.
Deadweight
That share of a measured result which would have happened anyway without the intervention being claimed.
Engineering and Construction Contract
The NEC form for works, assembled from core clauses, a main option, a dispute option, secondary options and Z clauses.
Compensation event
Under NEC, a listed event that can change the prices or the completion date, assessed on its forecast effect.
Early warning
Notice the contractor or the project manager must give as soon as either becomes aware of anything that might affect cost, time or quality.
Accepted programme
The contractor's programme once the project manager has accepted it; the basis for assessing every compensation event.
Defined Cost
In NEC terms, the contractor's real cost, whose forecast change is used to assess a compensation event.
FAQ

CIVE5360M FAQ

How difficult is Procurement Management?

The difficulty lies in judgement and evidence rather than calculation. The examination carries half the module mark and tests learning outcomes 3 and 4, and the readings are long: the Holyrood report alone runs to hundreds of pages. Answers must link a strategy decision to the NEC mechanism that delivers it, and a module mark below 50% means resitting whichever component scored under 50%.

How is the module assessed?

Assessment has two components of equal weight. Coursework counts for 50% and assesses learning outcomes 1 and 2; the examination counts for 50% and assesses outcomes 3 and 4. The module mark is the weighted average, and any component scoring below 50% must be resat if the overall mark falls below 50%.

When is the coursework due?

The brief was published on 2 October 2026 and the submission deadline is 14:00 on 3 December 2026, a Thursday in Week 10. That falls before the final NEC4 lectures on payment, compensation events, liabilities, insurance and termination, so plan revision of those topics for the break before the January examination.

What is known about the January examination?

The module page places the examination in the Semester 1 examination period in January 2027 and says it assesses learning outcomes 3 and 4. Duration, number of questions and permitted materials should be checked on the examination timetable and Minerva. Spare calculators can be borrowed from the Student Information Point at the School of Chemical and Process Engineering.

Why does the module rely so much on the Holyrood Inquiry?

Lord Fraser's report is a rare, detailed public account of procurement decisions on one major building. It records how construction management was chosen, how the construction manager was selected, how fees were structured and how estimated costs rose to £431m, so it supplies evidence for competence, roles, payment, selection and decision making.

What is NEC4 and why is it taught in detail?

NEC4 is the 2017 edition of a family of standard contracts that began as the New Engineering Contract. It is drafted for clarity, flexibility and a stimulus to good project management, and it sets processes such as early warning, the accepted programme and compensation events. Weeks 7 to 11 work through those provisions one lecture at a time.

How is social value measured in a construction tender?

The module supplies the National TOMs 2019 guidance, which links themes and outcomes to measures with fixed units and proxy values. Units delivered are multiplied by the proxy, priority weights of up to three may be used when choosing a bidder, and delivery is later reported unweighted, with local value kept apart from social value.

How should I plan my revision?

Revise in the order the module teaches: strategy first, then NEC4. For each seminar question, write a plan that explains the issue, names a mechanism or reading, makes a judgement and ends with a procurement action. Rehearse the Holyrood figures and the key clause numbers until you can quote them exactly.

Chapter questions

Questions students ask in each CIVE5360M chapter

What does the Week 2 seminar ask about competence?
It asks you to comment on competence in procurement with reference to Otim and colleagues (2025), Kyalisiima and colleagues (2024) and Fraser (2004), among others. Use the two journal cases for evidence of what goes wrong and the Holyrood report for how a client organisation allows it. Chapter 01 · Procurement Management and Competence
How does traditional contracting differ from construction management?
Under traditional contracting design is substantially complete before construction is tendered and one contractor builds. Under construction management the design, tender and construction stages run in parallel, trade packages are contracted to the client and a consultant co-ordinates them, so price certainty comes only when the last package is let. Chapter 02 · Contract Strategy: Definitions, Roles and Responsibilities
Which NEC payment options does the module guide name?
The NEC guide says an Engineering and Construction Contract uses one of six main payment options, naming target cost, lump sum, re-measurement and cost reimbursable among them. It adds that the target cost and reimbursable options make the project manager's role one of active joint management. Chapter 03 · Payment Methods and Sources of Funds
How was the Holyrood construction manager selected?
The notice used the restricted procedure, disclosed a £50m construction budget and asked for the most economically advantageous tender, judged on price, quality and further criteria. Questionnaires went to 29 potential applicants and 15 were returned; tenders were then adjusted and interviewed. Chapter 04 · Contractor Selection and Contracting Culture
What does the Social Value Act require?
The TOMs preface explains that the Act asks public bodies to consider social value rather than demand it, seeking change through culture and innovation rather than prescriptive definition and penalty. That light touch is why a shared measuring framework became useful. Chapter 05 · Supply Chain Management and Social Value
How was construction management chosen for Holyrood?
After advice that the programme dictated a fast-track route, a design team meeting on 21 July 1998 agreed to follow construction management. Fraser noted that the decision took four lines of a three-page minute and that Ministers were never asked to decide it. Chapter 06 · Contract Strategy Decision Making
What are the three principles of the NEC?
The NEC guide says every NEC form is drafted for clarity, flexibility and a stimulus to good project management. Clarity means plain English and a modular structure, flexibility means use across sectors and strategies, and the stimulus comes from detailed project management procedures. Chapter 07 · NEC4 Principles, Disputes, Scope and Contract Data
Which events can change the prices or completion date under NEC?
Only compensation events. The NEC guide says they are listed mainly in clause 60.1, with some others in the main and secondary options, and that five of the seventeen pages of core clauses, in core clause 6, deal with them. Chapter 08 · NEC4 Time, Quality, Payment and Compensation Events
Study strategy

How to study for the exam

Work through the module in two passes. In the first, read each chapter before its Friday lecture and draft the seminar task in writing, because the morning questions set the pattern the examination is likely to reward: explain something, then show how procurement manages it or what challenges a provision will meet.

Keep a single page of evidence for each topic, with exact figures and clause numbers, such as the £431m Holyrood estimate, the four lines of minute that recorded the route decision, the NT1 proxy of £28,758 or clause 63.7 on missing early warnings.

In the second pass, after the coursework deadline on 3 December, connect the halves: for every strategy choice, name the NEC4 provision that would put it into practice, and for every provision, name the strategy problem it solves. Finish by timing yourself on extended answers, ending each paragraph with the decision or action it supports.

Study CIVE5360M with AI

Your AI Project Management tutor for CIVE5360M

Stuck on a hard CIVE5360M question? Sia is AskSia’s AI Project Management tutor — ask any CIVE5360M Procurement Management question and get a clear, step-by-step explanation grounded in how the course is actually taught and assessed. Read this whole study guide free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5360M tutor, unlimited, worked the way the exam marks it
The full 46-page Bible + practice bank with worked solutions