CIVE5172M Chap.2 Gantt Charts and Task Dependencies
Gantt Charts and Task Dependencies
Gantt Charts and Task Dependencies covers the most widely shared planning picture on any project. A Gantt chart lists tasks as horizontal bars whose lengths are durations, placed against a time axis of days, weeks or months. Milestones appear as diamonds with a date and no duration, arrows show which task controls another, shading reports progress and a vertical line marks the status date.
The chapter explains the four dependency types, from the common finish-to-start link to the rare start-to-finish, and shows how a single mistyped link can lengthen a programme without any physical reason. Advanced features used by professional packages are then introduced: baselines that preserve the original plan, highlighted critical paths, resource assignments and progress lines.
The Week 1 tutorial case, the restoration of Manchester Town Hall, shows why heritage work produces a different task list from new build, with surveys, consents and protection appearing before any visible construction. Finally the chapter links the tutorial exercise to the group presentation, which asks each team for a high-level chart of the Leeds tram project.
An original listed-building schedule is solved step by step so that you can check your own logic.
What this chapter covers
- 01
Task bars, durations and the time axis
- 02
Milestones as zero-duration checkpoints
- 03
Finish-to-start, start-to-start, finish-to-finish and start-to-finish links
- 04
Progress shading and the status line
- 05
Baselines, critical path highlighting and resource assignments
- 06
Heritage refurbishment sequencing
- 07
High-level charts for the group presentation
Worked example · free
Schedule the early phase of a listed-building refit
- 1Survey runs from week 0 to week 4, and consent follows it from week 4 to week 10.
- 1Scaffold design is start-to-start with a two-week lag, so it runs from week 2 to week 5.
- 1Strip-out follows consent from week 10 to week 14.
- 1Boarding is finish-to-finish with strip-out, so it ends at week 14 and starts at week 12.
- 1The phase finishes at week 14; scaffold design could slip five weeks before affecting that date.
Key terms
- Milestone
- A checkpoint marked on a chart with a date but no duration.
- Baseline
- A saved snapshot of the original plan used to measure later deviation.
- Finish-to-start link
- A dependency in which a successor waits for its predecessor to be complete.
- Progress line
- A line on a chart that bends ahead of or behind the status date to show slippage by task.
Gantt Charts and Task Dependencies FAQ
How many dependency types can a Gantt chart show?
Four. Finish-to-start holds the next task until one finishes, start-to-start lets one start trigger another, finish-to-finish ties two completions together, and start-to-finish, which is rare, lets the start of one task trigger the finish of another.
Why should a milestone never be drawn as a bar?
A milestone marks a checkpoint such as an approval or handover and has a date but no duration. Drawing it as a bar suggests work is being done during that period and confuses readers about what the team is actually committing to.
What does the group presentation expect from the Gantt chart?
The brief asks for a high-level chart for scheduling the work tasks of the Leeds tram project, presented alongside a work breakdown structure and a critical evaluation of planning and control. High level means work packages rather than hundreds of site activities.
Assessment move
Learn Gantt charts by building one by hand before opening any software. Take five or six tasks from a refurbishment you can picture, give each a duration in weeks, and decide which link joins each pair. Draw the bars on squared paper and write the link type beside every arrow. Then change one link at a time and recompute the finish week, so that you feel how a finish-to-finish link differs from finish-to-start.
Once that is comfortable, add a milestone, a baseline and a status line at an imaginary week, shade each bar to show progress, and decide which tasks are behind. Practise reading other people's charts too: cover the task names and see whether the bars and arrows alone tell you the story.
For the presentation, agree the level of detail as a team before anyone draws: work packages such as consents, enabling works, track, stops and testing are enough. Assign colours by phase or responsibility and explain the choice on the slide. Finally, connect the chart to Chapter 4 by marking which chain of bars you believe sets the finish date, then check that belief with the network calculation.
Working through Gantt Charts and Task Dependencies in CIVE5172M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5172M Gantt Charts and Task Dependencies question and get a clear, step-by-step explanation grounded in how CIVE5172M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.