Contract Strategy Decision Making

Contract Strategy Decision Making covers the two Week 6 lectures that close the strategy half of the module. It uses the Holyrood Inquiry as an evidence base: estimates that moved from between £10m and £40m in 1997 to £431m in February 2004, a £195m cap set and then lifted, an average delay of 20 months in a 41-month period, and a route agreed in four lines of a three-page minute without Ministers.

Against that record it sets the Treasury guidance on weighting cost, time and quality and on excluding routes that cannot give price certainty, the expert's four questions and risk spectrum, and Fraser's recommendation that construction management be a route of last resort for public buildings. A worked scoring exercise shows how weights change the ranking of routes.

In this chapter

What this chapter covers

  • 01

    Holyrood cost and time record

  • 02

    How the route decision was taken and recorded

  • 03

    Treasury guidance on weighting objectives

  • 04

    The risk spectrum from private finance to construction management

  • 05

    Conditions for construction management to work

  • 06

    Recommendation 3 and the route of last resort

Worked example · free

Measure the rise in reported final cost

Q [3 marks]. Estimated final cost for the Holyrood building was reported at £241m in November 2001 and £431m in February 2004. Find the increase in pounds and as a percentage of the 2001 figure, and compare the 2004 figure with the £195m cap set in April 2000. The marks shown are an AskSia practice weighting, not an official University allocation.
The line plots each estimated final cost reported between November 2001 and February 2004, rising from £241m to £431m, while the flat orange line marks the £195The line plots each estimated final cost reported between November 2001 and February 2004, rising from £241m to £431m, while the flat orange line marks the £195m cap that Parliament lifted in June 2001.£200m£300m£400m£195m cap, lifted 2001£241m£431mNov 2001Feb 2004estimated final cost reported
The line plots each estimated final cost reported between November 2001 and February 2004, rising from £241m to £431m, while the flat orange line marks the £195m cap that Parliament lifted in June 2001.
  • 1Increase: £431m − £241m = £190m.
  • 1Percentage: £190m ÷ £241m = 0.788, an increase of about 78.8%.
  • 1Against the cap: £431m − £195m = £236m above it, more than double the capped figure.
Reported final cost rose by £190m, about 78.8%, between the two reports, ending £236m above the cap Parliament had set and later lifted.
Sia tip — Name the base of every percentage. A rise measured from the 2001 estimate tells a different story from one measured against the cap.
Glossary

Key terms

Risk spectrum
An ordering of procurement routes by how much risk stays with the client, from private finance to construction management.
Cost cap
A ceiling set on project cost; Fraser doubted that Parliament grasped how little such a cap means under construction management.
Weighted objectives
Cost, time and quality given relative importance, if appropriate numerically, before routes are compared.
Route of last resort
Fraser's summary of Treasury guidance on construction management for public building projects, since all risk lies with the client.
FAQ

Contract Strategy Decision Making FAQ

How was construction management chosen for Holyrood?

After advice that the programme dictated a fast-track route, a design team meeting on 21 July 1998 agreed to follow construction management. Fraser noted that the decision took four lines of a three-page minute and that Ministers were never asked to decide it.

What does the Treasury guidance say about price certainty?

The guidance quoted in the report says a strategy unable to satisfy an important objective may be excluded, and that if price certainty is essential before construction starts, management contracting and construction management would be inappropriate.

What did Fraser identify as the main cause of the project's problems?

He concluded that choosing construction management was the one factor behind most of the project's misfortunes, and he was highly critical of the failure to evaluate that highly risky strategy before adopting it.

What conditions does construction management need?

The expert listed an experienced, informed client, a well-led team, well-defined roles from the start, an architect who sees the whole and the detail, planning time for a no-surprises culture, a strong change process and well-managed risk, and he favoured co-locating the team.

Is there a single right contract strategy?

The guidance quoted in the inquiry says a strategy is seldom plainly right or plainly wrong, since every option has some disadvantages or risk. The test is whether the decision was evaluated, recorded and taken by the people who carry its risk.

What should a contract strategy report contain?

The Treasury guidance described in the inquiry asks for the options available, the risks attached to each and, after evaluating them, a reasoned recommendation. Fraser expected the project manager to prepare such a report and the project sponsor to insist on it before seeking the views of Ministers.

Study strategy

Exam move

Rebuild the Holyrood decision as a timeline from January 1998 to July 1998, then as a cost line from 1997 to 2004, and practise explaining in three sentences how one led to the other. Run a weighted scoring exercise for two invented clients with different priorities and record which routes the guidance would exclude.

End with an essay plan on whether the route itself or the decision process was at fault, and make sure it uses at least two dated facts and one quotation from the report.

Working through Contract Strategy Decision Making in CIVE5360M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5360M Contract Strategy Decision Making question and get a clear, step-by-step explanation grounded in how CIVE5360M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5360M tutor, unlimited, worked the way the exam marks it
The full 5-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works