CIVE5941M Chap.9 Works Programme, Temporary Accommodation and Cash Flow
Works Programme, Temporary Accommodation and Cash Flow
Works Programme, Temporary Accommodation and Cash Flow turns costed projects into a dated plan.
The coursework brief gives standard durations by work type and floor area: major external repairs and major internal refurbishment close a school for about a year below 1,000 m² and two years above, minor works let it stay open, redecoration takes three or six months, and new buildings take from about 24 to 40 months, with three months of planning and permissions printed under the new-build rules.
Every closure needs pupils housed, so the chapter sizes Euro standard temporary classrooms with the brief's capacity rule and prices them with offices and toilets by the month. It then spreads each package's cost over its working months, escalates each year at 4% from the 2025 base, and tests the annual cash flow against the £10 million ceiling, using an invented programme that runs from 2027, the plan's start year.
What this chapter covers
- 01
Duration rules by work type and floor area
- 02
Closure work, open-school work and new build
- 03
A five-step sequencing method from ranking to pricing
- 04
Sizing and pricing temporary classrooms, offices and toilets
- 05
Spreading costs over working months and escalating each year
- 06
Testing the annual cash flow against the yearly ceiling
Worked example · free
Build a yearly cash flow and test it against the ceiling
- 2Spread C: two thirds in 2027 (£2.67m) and one third in 2028 (£1.33m). Split B equally: £1.5m in each of 2028 and 2029.
- 1Spread D at £96,000 a month from April 2027: 9 months in 2027, 12 in 2028, 12 in 2029 and 7 in 2030.
- 2Spending at 2025 prices by year: £7.37m in 2027, £3.99m in 2028, £2.65m in 2029 and £0.67m in 2030.
- 1Escalate with 1.0816, 1.124864, 1.169859 and 1.216653: £7.97m, £4.48m, £3.10m and £0.82m.
- 1Every year stays below £10m; 2027 is the tightest year and the escalated total is £16.38m.
Key terms
- Works programme
- Dated schedule showing when each project starts, how long it runs and whether its school stays open.
- Temporary classroom
- Hired portable teaching unit that houses pupils while their own building is closed for works.
- Planning period
- Three months for planning and permissions that the brief adds to its construction durations.
- Cash-flow profile
- Year-by-year pattern of spending produced by spreading project costs over their working months.
Works Programme, Temporary Accommodation and Cash Flow FAQ
Which works close a school in the coursework case?
Major external repairs and major internal refurbishment close the school: about a year for buildings under 1,000 m² and two years above. Minor external repairs and internal refurbishment allow it to stay open, taking a year under 1,000 m² and eighteen months above, so closures, and therefore decants, follow from the type of work you choose.
Does the three-month planning period apply to repairs?
The sentence says the period is added to all durations, but it is printed under the new-build rules. That leaves a reading choice for repair and refurbishment work. Decide which reading you use, state it as an assumption, and apply it consistently across the programme so the cash flow and the chart agree.
How many pupils fit in one temporary classroom?
Use the brief's rule: 85% of the unit's area divided by 4.1 m² for primary-age pupils or 6.1 m² for high-school pupils. A Euro standard classroom of 14.5 m by 6.5 m gives about 19 primary places or 13 high-school places once rounded down to whole pupils.
How should costs be spread across a long project?
A simple, defensible rule is to spread each package's cost evenly over its working months, leave planning months without construction spend, and then escalate each year's share at 4% from the 2025 base. State the rule once, because a different spreading pattern would move money between years.
What if one year of the cash flow exceeds the ceiling?
Reshape the programme rather than cutting the priority work. Move a package that keeps a school open into a lighter year, split a large package across two years, or start a new build slightly later, then recheck every year after inflation and confirm the total still fits the five-year limit.
Assessment move
Put the duration rules on one card and the temporary unit specifications on another, then practise reading a work type and floor area and stating the duration and whether the school closes. Draw a simple bar chart for three or four invented packages before attempting any costs, because the cash flow should come from the same dates.
Next, spread each package's cost over its months, total each year, escalate, and compare with the ceiling. For every closure, size temporary classrooms with the brief's rule, rounding places down and units up, and compare that with relocating pupils to a school with spare places. Finish by checking that each minimum standard in the brief is delivered by a package you can point to.
Working through Works Programme, Temporary Accommodation and Cash Flow in CIVE5941M? Sia is AskSia’s AI Engineering tutor — ask any CIVE5941M Works Programme, Temporary Accommodation and Cash Flow question and get a clear, step-by-step explanation grounded in how CIVE5941M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.