Firm Investment, Discounting and LCOE views energy from inside a firm allocating scarce capital. It shows how discounting turns future revenue into present value, why the cost of capital is contested, and how the short-run decision to operate differs from the long-run decision to invest.

A clinic recomputes the levelised cost of wind and gas at different discount rates to show that financing, not engineering, can move most of the gap, and warns that LCOE does not measure system value. Portfolio theory and real options complete the toolkit for the investment pitch tutorial. Practice items value a solar farm at two discount rates and frame one technology for two investors with different goals.

In this chapter

What this chapter covers

  • 01

    Cost-benefit analysis and profit

  • 02

    Short run versus long run

  • 03

    Discounting and present value

  • 04

    Cost of capital and hurdle rates

  • 05

    Levelised cost of electricity

  • 06

    Portfolio theory and real options

Worked example · free

Recompute wind and gas LCOE at two discount rates

Q [6 marks]. Per kW, a wind plant costs £1,500 with £40 a year fixed O&M and produces 3.504 MWh a year; a gas plant costs £600 with £20 O&M, produces 5.256 MWh and pays £60/MWh for fuel and carbon. Both last 25 years. Find each LCOE at 5% and 10%. The marks shown are an original study allocation, not an official UCL marking scheme.
LCOE for the wind and gas examples at discount rates of 5%, 10% and 15%.LCOE for the wind and gas examples at discount rates of 5%, 10% and 15%. Wind climbs from 42 to 78 pounds per MWh while gas moves from 72 to 81, so the cost advantage shrinks as finance gets dearer.4272r = 5%5976r = 10%7881r = 15%WindGas CCGTLCOE £/MWh
LCOE for the wind and gas examples at discount rates of 5%, 10% and 15%. Wind climbs from 42 to 78 pounds per MWh while gas moves from 72 to 81, so the cost advantage shrinks as finance gets dearer.
  • 1Capital recovery factor over 25 years: 0.0710 at 5% and 0.1102 at 10%.
  • 2Wind at 5%: (1,500 x 0.0710 + 40) / 3.504 = £41.79/MWh; at 10%: £58.58/MWh.
  • 2Gas at 5%: (600 x 0.0710 + 20) / 5.256 + 60 = £71.90/MWh; at 10%: £76.38/MWh.
  • 1Wind rises by 40% and gas by 6%, so the financing rate moves the capital-heavy option most.
Wind stays cheaper at both rates, but its advantage shrinks from about £30 to about £18 per MWh as the rate doubles. Any LCOE comparison must therefore state the discount rate it uses. The marks are an original practice allocation.
Sia tip — Annualise capital with the capital recovery factor before dividing by annual output, and keep fuel per MWh outside that division.
Glossary

Key terms

Discount rate
The rate used to convert future cash flows into present value, reflecting time and risk.
Capital recovery factor
The annual payment per unit of capital that repays it with interest over a set life.
Real option
The right, but not the obligation, to expand, delay or abandon a project as information arrives.
Net present value
The present value of a project's benefits minus the present value of its costs.
Hurdle rate
The minimum return an investor requires before committing capital to a project.
FAQ

Firm Investment, Discounting and LCOE FAQ

Why does the discount rate change which technology looks cheapest?

Capital-heavy technologies such as wind or nuclear pay most of their costs upfront, so a higher rate raises their annualised cost sharply. Fuel-heavy plants pay as they go and move much less. Comparing levelised costs is only fair at a stated, common rate.

What does LCOE leave out?

It ignores when the power is produced, the balancing and network costs a technology imposes, and how its output affects the price it receives. Two plants with equal LCOE can therefore have quite different value to the system.

How should the investment pitch be structured?

Compare your technology's levelised cost with competitors using the government estimates, say whether you accept them and why, recommend what to back today and in 2035, and show how other metrics, risk or a wider system view would change the answer.

What is the difference between the short run and the long run for a power plant?

In the short run the plant exists, so it runs whenever the price covers its running cost and the capital is sunk. In the long run nothing is sunk, and a firm invests only if expected prices also repay the capital with a return. Volatile prices widen the gap between the two decisions.

What are real options and why do they matter for energy?

A real option is the right, but not the obligation, to expand, delay or abandon a project later. Modular technologies such as solar can be added step by step, while a large nuclear plant commits everything at once. When prices and policy are uncertain, flexibility has value that a simple net present value misses.

Study strategy

Assessment move

Make discounting fluent: compute present values of single sums and annuities by hand at two rates until you can predict the direction of change before calculating. Then rebuild the levelised cost formula for one renewable and one fuel-based plant and run it at three discount rates, as in the clinic.

Read the government cost estimates for your assigned technology and note every assumption that moves the result most, especially hurdle rates, load factors and fuel prices. For the pitch, prepare one slide that answers the profit-focused investor and one argument for the investor who weighs environment, security and equity, and decide in advance which partner you would approach in the second round.

The required reading is a value-for-money review of a large nuclear project; read its summary with three questions in mind: what discount rate or financing model it assumes, which risks fall on consumers or taxpayers, and how cost overruns would change the result.

For the essay, an economic lens is strongest when it turns a target into a cost or investment requirement and tests it against financing conditions, such as the rate at which developers can borrow.

A+Everything unlocked
Unlocks this Bible + all 32 of your subjects at University College London, plus 1,000+ more Bibles across the AskSia library.
Sia - your BENV0090 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works