The Hong Kong Polytechnic University · FACULTY OF ECONOMICS

AAE5110 Chap.7 Reliability, Maintenance and Spares

- one subject, every graph, every model, every mark
8 Chapters4-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 7 of 7 · AAE5110

Reliability, Maintenance and Spares

Reliability is performance over time

Reliability claims require a function, operating condition and time horizon. This chapter calculates failure rate from total exposure, distinguishes MTTF from MTBF and places scheduled and unscheduled work inside continuing-airworthiness requirements.

It classifies spares by restoration and control needs, compares continuous with periodic review, and derives EOQ from annual ordering and holding cost. The final page stress-tests basic assumptions against intermittent failure, long lead time and severe no-stock consequences.

Exposure includes survivors

Failure rate divides failures by total operating exposure.

Failed units contribute time until failure, while surviving units contribute the full observation window. Omitting survivor time exaggerates the rate; crediting failed units with time after failure understates it. MTTF belongs to a non-repairable item whose first failure ends its observed life. MTBF belongs to a repairable item restored between failures.

The reciprocal link with failure rate requires the constant-rate model to be stated.

Airworthiness is the boundary, not a cost item

Scheduled work follows approved time or usage limitations. Unscheduled work responds to unforeseen findings, pilot reports or events. A scheduled inspection can therefore uncover an unscheduled repair.

Maintenance tasks, licensed personnel, approved programmes and certification determine whether the aircraft may return to service. Cost optimisation begins inside that requirement.

It can compare downtime, labour, provider and spares policies, but it cannot trade away the permission boundary.

Inventory joins three clocks

Reliability creates a failure clock, maintenance creates an inspection or replacement clock, and supply creates a lead-time clock.

Continuous review can trigger replenishment after each transaction and suits costly or critical items; periodic review trades information for lower monitoring effort. Basic EOQ balances annual ordering cost DS/Q with annual holding cost QH/2. Reorder point covers lead-time demand. Intermittent failures, uncertain lead time and severe shortage consequences require more than the baseline model.

In this chapter

What this chapter covers

  • 01

    Reliability definition

  • 02

    Failure exposure

  • 03

    MTTF and MTBF

  • 04

    Scheduled maintenance

  • 05

    Unscheduled maintenance

  • 06

    Spare categories

  • 07

    Inventory review systems

  • 08

    EOQ and reorder points

Worked example · free

Balance ordering and holding cost

Q [10 marks]. Annual usage is 1,800 units, ordering cost is HKD 320 and annual holding cost is HKD 18 per unit. Find EOQ and check the cost balance. The marks are an AskSia study allocation, not a University marking scheme.
The flow begins with total exposure rather than calendar time, converts failures into the index appropriate to repairability, and ends with a maintenance or spaThe flow begins with total exposure rather than calendar time, converts failures into the index appropriate to repairability, and ends with a maintenance or spares choice. The same failure count can imply different reliability when exposure differs.Exposure timeand failuresFailure rateMTTF or MTBFMaintenance andspares decisionObserved failures become an operating decision only after exposure is countedrepairable unit → MTBF    non-repairable unit → MTTF
The flow begins with total exposure rather than calendar time, converts failures into the index appropriate to repairability, and ends with a maintenance or spares choice. The same failure count can imply different reliability when exposure differs.
  • 4Substitute demand, ordering and holding cost.
  • 3Calculate EOQ and average stock.
  • 3Compare annual cost terms.
EOQ is the square root of 2 times 1,800 times 320 divided by 18, equal to 252.98 or about 253 units. Average cycle stock is 126.5. Annual holding and ordering costs are both approximately HKD 2,277.
Sia tip — Use the same time unit for demand and holding cost, then check that EOQ balances the two annual cost terms.
Glossary

Key terms

Reliability
Probability of required performance under stated conditions for a stated time.
Failure Rate
Failures divided by total operating exposure.
MTTF
Mean operating time to failure for a non-repairable unit.
MTBF
Mean operating time between failures for a repairable unit.
Scheduled Maintenance
Work performed according to approved time or usage limitations.
Economic Order Quantity
The order quantity minimising baseline annual ordering and holding cost.
FAQ

Reliability, Maintenance and Spares FAQ

Why do surviving test units count in exposure?

They operated without failure for the full observation period and therefore provide reliability evidence about the tested population. Excluding their time would exaggerate the estimated failure rate.

How do scheduled and unscheduled maintenance interact?

A scheduled inspection can reveal an unforeseen defect that requires unscheduled rectification. The visit therefore contains a planned trigger and an additional unplanned work scope.

Why may EOQ be insufficient for a critical spare?

Basic EOQ excludes shortage cost and assumes known constant demand and lead time. Intermittent failures, a long replenishment delay and cancellation consequences require an explicit service or availability treatment.

Study strategy

Exam move

Build the exposure denominator before calculating reliability, identify repairability before choosing MTTF or MTBF, and keep approved maintenance requirements ahead of cost optimisation. For inventory, separate order quantity from reorder trigger and name the EOQ assumption most likely to fail. Practise tests with early failures and surviving units so total exposure is assembled rather than assumed.

Take one maintenance visit and separate its scheduled trigger from any unscheduled findings, then list the records and certification boundary before comparing cost. Classify an original spare as rotable, repairable, expendable or consumable and choose continuous or periodic review from value and criticality. For EOQ, calculate annual holding and ordering cost separately and use their near equality as a check.

Add lead-time demand only when finding a reorder point, and state how intermittent failures or a no-go shortage would require a stronger service model. Create a final audit where demand and holding cost initially use different time units. Convert them before EOQ and explain why a neat result with inconsistent units is still wrong.

Working through Reliability, Maintenance and Spares in AAE5110? Sia is AskSia’s AI Economics tutor — ask any AAE5110 Reliability, Maintenance and Spares question and get a clear, step-by-step explanation grounded in how AAE5110 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 24 of your subjects at The Hong Kong Polytechnic University, plus 1,000+ more Bibles across the AskSia library.
Sia - your AAE5110 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works