University of Birmingham · FACULTY OF MANAGEMENT

38004 Chap.7 Planning and Control, MRP and Job Sequencing

- one subject, every graph, every model, every mark
6 Chapters3-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 7 of 12 · 38004

Planning and Control, MRP and Job Sequencing

Planning across three horizons

Week 4 treats planning and control as allocating resources and activities so that processes are efficient and still follow customer demand. Long-term planning sets capacity years ahead, medium-term aggregate planning checks whether existing resources can meet demand over months, and short-term planning monitors daily work against the plan.

Control is a loop: measure what the process produces, compare it with the objective, and intervene when it drifts.

Material requirements and enterprise systems

Material requirements planning works backwards from a master production schedule. It explodes the bill of materials into gross requirements, subtracts stock and scheduled receipts to find net requirements, and offsets each order by its lead time.

Wider systems followed, from manufacturing resource planning to enterprise resource planning, which shares one database across functions and partners.

Sequencing jobs

A sequencing-rules exercise, listed in the handbook as Week 4 additional material and described in the Week 2 lecture's task list as discussed in the Week 3 seminar, compares rules for ordering jobs: first in first out, last in first out, earliest due date, and longest or shortest operation time.

Its template judges them on total time in process first and lateness second, and different rules win on different measures, so the choice depends on what the business values.

In this chapter

What this chapter covers

  • 01

    Long, medium and short planning horizons

  • 02

    The monitor, compare and correct control loop

  • 03

    MRP inputs: master schedule, bill of materials, inventory status

  • 04

    Gross requirements, netting and lead-time offsetting

  • 05

    From MRP to enterprise resource planning

  • 06

    Sequencing rules, time in process and lateness

Worked example · free

Compare shortest operation time with earliest due date for four translation jobs

Q [6 marks]. AskSia-authored practice. A translation office has four jobs: W takes 4 days and is due on day 10, X takes 7 days and is due on day 9, Y takes 2 days and is due on day 4, Z takes 5 days and is due on day 15. Sequence them by shortest operation time and by earliest due date, then compare average time in process and lateness. AskSia set the marks here for practice; they are not an official mark allocation.
Figure 7.1.Figure 7.1. The four translation jobs laid out on a day axis under two rules, with the dashed line marking job X's due date: shortest operation time finishes X on day 18, nine days late, while earliest due date finishes X on day 9 but leaves W and Z three days late each.shortest operation timeYWZXearliest due dateYXWZ0day 18
Figure 7.1. The four translation jobs laid out on a day axis under two rules, with the dashed line marking job X's due date: shortest operation time finishes X on day 18, nine days late, while earliest due date finishes X on day 9 but leaves W and Z three days late each.
  • 2Shortest operation time Y, W, Z, X finishes on days 2, 6, 11 and 18: total 37, average 9.25; only X is late, by 9 days.
  • 2Earliest due date Y, X, W, Z finishes on days 2, 9, 13 and 18: total 42, average 10.5; W and Z are each 3 days late, total 6.
  • 2Rank on time in process first, then lateness: shortest operation time wins on the first measure, earliest due date on lateness.
Shortest operation time gives the lower average time in process, 9.25 against 10.5 days, but leaves one job nine days late. Earliest due date spreads smaller delays over two jobs, cutting total lateness from 9 to 6 days and maximum lateness from 9 to 3. The better rule depends on which measure the office's customers care about most.
Sia tip — List each job's finish day in a running total before computing lateness, and treat a job that finishes early as zero late.
Glossary

Key terms

Master Production Schedule
A statement of how many finished items are to be produced in each period, from which MRP works.
Bill of Materials
The list of components, and their quantities, needed to make one unit of a product.
Net Requirement
The quantity still to be obtained after on-hand stock and scheduled receipts are subtracted from gross requirements.
Enterprise Resource Planning
Integrated software that links every function of a business to one shared database.
Earliest Due Date Rule
Sequencing jobs in the order of their promised completion dates, soonest first.
FAQ

Planning and Control, MRP and Job Sequencing FAQ

What are the steps of the MRP algorithm?

Start from the master production schedule and explode the bill of materials to get gross requirements for each component. Compare those with stock on hand and scheduled receipts to find net requirements. Then offset each net quantity by the component's lead time to find the week when the order must be released.

How do the three planning horizons differ?

Long-term planning concerns capacity and process choice and can reach five years into the future or beyond. The middle horizon, aggregate planning, typically looks three to six months forward and asks whether existing resources can meet demand and what contingencies exist. Short-term operational planning monitors daily activity against the plan and corrects deviations.

What does operations control involve?

Control monitors the outputs of a transformation process, compares them with plans and objectives, and intervenes to correct the process where results drift. It is a continuous loop rather than a one-off check, and it depends on accurate measurement, because corrections based on wrong readings make performance worse.

Which sequencing rule should be used?

No single rule is best on every measure. Shortest operation time usually minimises average time in process, earliest due date tends to reduce lateness, and first in first out simply follows the order in which jobs arrive. Decide which measure matters most to customers or costs, compute the measures for each rule, and choose accordingly.

What benefits does enterprise resource planning offer?

Because every function draws on one shared database, managers can see what is happening across the business. Adoption forces business processes to be tidied, gives a firmer basis for continuous improvement, and supports richer communication with customers, suppliers and partners further along the supply network.

Study strategy

Exam move

Work the two calculation types until they are automatic. For MRP, write your own two-level product with three components, set different lead times, add one scheduled receipt, and produce a small table of gross requirements, net requirements and release weeks; check that every release week equals the need week minus the lead time.

For sequencing, invent four jobs with processing times and due dates, sequence them under at least three rules, and calculate total and average time in process, total lateness and maximum lateness. Then write two sentences recommending a rule for a business that values promised dates, and two for one that values short waiting.

Finally, describe the control loop for one process you know, naming what is measured, the objective it is compared against, and the correction available.

Working through Planning and Control, MRP and Job Sequencing in 38004? Sia is AskSia’s AI Management tutor — ask any 38004 Planning and Control, MRP and Job Sequencing question and get a clear, step-by-step explanation grounded in how 38004 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 17 of your subjects at University of Birmingham, plus 1,000+ more Bibles across the AskSia library.
Sia - your 38004 tutor, unlimited, worked the way the exam marks it
The full 3-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
38004 · Organisational Decision Making and Operations Management - independent study guide on the AskSia Library. More University of Birmingham subjects · Microeconomics across all universities