Cost Estimating, Budgeting and Control

Cost Estimating, Budgeting and Control follows project cost management through its four processes: resource planning, cost estimating, cost budgeting and cost control.

It begins with the evidence that construction overruns are common and costly, from well-known public buildings to transport schemes, and with the main reasons given for them: poor scope definition, estimates that were too low from the start, unclear requirements, untested technology and weak planning.

The chapter then compares estimate classes and their published accuracy ranges, from a rough order of magnitude estimate that may sit 25% below or 75% above the outturn to a definitive estimate within minus 5% and plus 10%. Five estimating techniques are set side by side: expert judgement, analogous, parametric, bottom-up and three-point.

Principles such as life cycle costing, cash flow analysis, direct and indirect costs, sunk cost and the learning curve frame the numbers, and contingency and management reserves protect the baseline. Budgeting turns the estimate into a time-phased baseline through the work breakdown structure and schedule.

Control closes the loop by measuring work, comparing it with its allowance and acting, using systems from monthly valuation to weekly unit costing against the bill of quantities.

In this chapter

What this chapter covers

  • 01

    Why construction projects overrun

  • 02

    Estimate classes and accuracy ranges

  • 03

    Expert, analogous, parametric, bottom-up and three-point estimating

  • 04

    Life cycle costing and cash flow analysis

  • 05

    Contingency and management reserves

  • 06

    Cost budgeting as a performance baseline

  • 07

    Cost control systems and unit costing

Worked example · free

Turn an early estimate into a range

Q [4 marks]. A rough order of magnitude estimate for a bus depot is £20 million. Using the published accuracy range for this class, find the lowest and highest likely outturn, and explain what the asymmetry means for the client. The 4 marks shown are a practice weighting for this guide and not the University's official allocation.
Published accuracy ranges for each estimate class, drawn to scale around the eventual actual cost at zero: a rough order of magnitude estimate may fall 25% low Published accuracy ranges for each estimate class, drawn to scale around the eventual actual cost at zero: a rough order of magnitude estimate may fall 25% low or 75% high, while a definitive estimate narrows to minus 5% and plus 10%.Rough order of magnitudePreliminaryBudgetaryDefinitiveFinal estimate-25%0+25%+50%+75%
Published accuracy ranges for each estimate class, drawn to scale around the eventual actual cost at zero: a rough order of magnitude estimate may fall 25% low or 75% high, while a definitive estimate narrows to minus 5% and plus 10%.
  • 1The class runs from minus 25% to plus 75% of the estimate.
  • 1Lowest likely outturn: 20 × 0.75 = £15 million.
  • 1Highest likely outturn: 20 × 1.75 = £35 million.
  • 1The range is skewed upwards, so an early figure is far more likely to be exceeded than undercut, and the client should hold a reserve and refine the estimate as design develops.
The outturn could plausibly fall between £15 million and £35 million, so the client should plan funding with a reserve until a more accurate class of estimate is available.
Sia tip — Convert a percentage range into money before you comment on it; minus 25% and plus 75% of £20 million is a £20 million spread, which is the point to make.
Glossary

Key terms

Contingency reserve
Money in the cost baseline for known unknowns that can be partly planned for.
Parametric estimating
Estimating from a proven relationship between a parameter and cost, such as cost per unit of floor area.
Cost budgeting
Allocating the total estimate to individual work items to create a baseline for measuring performance.
Sunk cost
Money already spent, which should not drive a decision about future spending.
FAQ

Cost Estimating, Budgeting and Control FAQ

How accurate is a rough order of magnitude estimate?

It is prepared very early from preliminary drawings and data from similar projects, and its published accuracy runs from 25% below to 75% above the eventual cost. Its purpose is to test feasibility quickly, not to set a contract price.

What is the difference between contingency and management reserves?

A contingency reserve covers known unknowns that can be partly planned for and sits inside the cost baseline. A management reserve allows for unknown unknowns, future situations that cannot be predicted, so it cannot be tied to any planned item.

How does unit costing support cost control on site?

Each week the unit cost of an operation, such as pounds per square metre of formwork, is calculated from its labour, material and plant costs and compared with the net unit rate in the bill of quantities, so variances surface while they can still be corrected.

Study strategy

Assessment move

Build this chapter around one comparison table and one control routine. For the table, list the estimate classes with their accuracy ranges, the information each needs and who would use it, then add the five techniques with the situation in which each works best. Test yourself by converting percentage ranges into money for a few round numbers, because the asymmetry is easier to argue once you can see it in pounds.

For the routine, practise unit costing on invented weekly figures: add labour, materials and plant, divide by quantity, compare with the bill rate and name the element to investigate first. Then connect the principles: explain in two sentences why a sunk cost should not drive a decision, why life cycle costing can favour a dearer design, and why a firm running several projects needs cash flow analysis.

Keep the four processes in order and be able to say which document each produces. Finally, prepare for the presentation question on whether earned value is still needed alongside a digital controls platform by noting what traditional cost control measures and what it misses, which leads directly into the next chapter.

Working through Cost Estimating, Budgeting and Control in CIVE5172M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5172M Cost Estimating, Budgeting and Control question and get a clear, step-by-step explanation grounded in how CIVE5172M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5172M tutor, unlimited, worked the way the exam marks it
The full 5-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
CIVE5172M · Project Management Tools and Techniques - independent study guide on the AskSia Library. More University of Leeds subjects · Microeconomics across all universities