Earned Value Management

Earned Value Management combines cost and schedule so that progress is measured by the value of work achieved rather than by money spent. The chapter shows why separate reports mislead: an expense report can suggest a project is under budget while a progress report suggests a delay, yet together they reveal a project that has spent more than it has earned.

It defines budget at completion, the budgeted cost of work scheduled that forms the S-curve baseline, the status date, percentage complete, the budgeted cost of work performed and the actual cost of work performed. From these come the schedule and cost variances, the schedule and cost performance indices, the estimate at completion based on current productivity, the estimate to complete and the budget variance.

An original highway scheme is reported at month 6 and then broken into packages, showing how project indices can hide one package that is failing behind another that is ahead.

The chapter maps the method onto Part B of the essay, which asks for a concise milestone table of BCWS, BCWP and ACWP with cost and schedule indices for each activity, and onto the presentation question about whether earned value remains necessary with real-time digital controls.

In this chapter

What this chapter covers

  • 01

    Why separate expense and progress reports mislead

  • 02

    Budget at completion and the planned S-curve

  • 03

    Percentage complete and earned value

  • 04

    Schedule and cost variances

  • 05

    Schedule and cost performance indices

  • 06

    Estimate at completion and estimate to complete

  • 07

    Package-level indices and the milestone report table

Worked example · free

Find the package that is dragging the project

Q [6 marks]. At month 6 three packages report: earthworks BCWS £150k, BCWP £150k, ACWP £165k; structures £140k, £105k, £120k; drainage £70k, £45k, £45k. Calculate SPI and CPI for each and say which package needs attention first if structures is critical. The 6-mark weighting is ours for practice and is not an official University assessment scheme.
Schedule and cost indices for the three packages in the month 6 example: earthworks is on programme but over cost, structures is behind and over cost, and drainSchedule and cost indices for the three packages in the month 6 example: earthworks is on programme but over cost, structures is behind and over cost, and drainage is on cost but furthest behind schedule.on plan 1.0EarthworksStructuresDrainage0.60.8SPICPI
Schedule and cost indices for the three packages in the month 6 example: earthworks is on programme but over cost, structures is behind and over cost, and drainage is on cost but furthest behind schedule.
  • 2Earthworks: SPI = 150 / 150 = 1.00 and CPI = 150 / 165 = 0.91, so on programme but over cost.
  • 2Structures: SPI = 105 / 140 = 0.75 and CPI = 105 / 120 = 0.88, behind and over cost.
  • 1Drainage: SPI = 45 / 70 = 0.64 and CPI = 45 / 45 = 1.00, on cost but furthest behind.
  • 1Structures comes first: it is critical and weak on both indices, while drainage may have float to absorb its delay.
Structures needs attention first because it is critical and below 1 on both indices; drainage is further behind but on cost and may sit off the critical path.
Sia tip — Divide earned value by the other quantity every time; if CPI comes out above 1 while cost variance is negative, the ratio is upside down.
Glossary

Key terms

Budget at completion
The original estimate, budget or quotation for all the work.
Earned value
The budgeted cost of the work actually performed by the status date, also written BCWP.
Cost performance index
Earned value divided by actual cost, where a value below 1 signals overspend.
Estimate at completion
A revised forecast of total cost based on productivity at the status date.
FAQ

Earned Value Management FAQ

Why is earned value better than comparing spend with budget?

Spend against budget ignores how much work the money bought. A project can appear under budget while delivering even less work than planned. Earned value measures the budgeted worth of work actually done, so cost and schedule performance can be judged at the same status date.

How is the estimate at completion calculated?

Divide actual cost by earned value to get current productivity, then multiply by the budget at completion. If a project has spent £330k to earn £300k of a £600k budget, the forecast is 1.1 times 600, or £660k, assuming productivity stays the same.

Do CI and SI in the essay brief mean the same as CPI and SPI?

Yes. The essay brief asks for the cost index and schedule index for each activity and the project at three milestones, which correspond to the cost and schedule performance indices taught in the lecture, both calculated from earned value.

Study strategy

Assessment move

Earned value rewards a fixed routine, so practise one until it is automatic. For any status date, write BAC, BCWS, BCWP and ACWP in a column before calculating anything, and label each as cumulative.

Compute the two variances, then the two indices, then the forecasts, and check every result against its partner: a negative cost variance must pair with a cost index below 1. Next, break a project into three or four packages, give each its own figures, and confirm that the package rows add up to the project row before calculating indices.

Practise writing one plain-language sentence per result for a client, for example that the job is delivering about 83 pence of planned work for each pound of planned progress. For Part B of the essay, rehearse the three-milestone table with invented data, paying attention to activities that are complete, part complete or not started.

Finally, prepare an argument for the presentation question: list what a real-time digital controls platform does better than periodic earned value reporting, and what it still needs from earned value, such as a baseline and an agreed measure of work earned.

Working through Earned Value Management in CIVE5172M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5172M Earned Value Management question and get a clear, step-by-step explanation grounded in how CIVE5172M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5172M tutor, unlimited, worked the way the exam marks it
The full 5-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
CIVE5172M · Project Management Tools and Techniques - independent study guide on the AskSia Library. More University of Leeds subjects · Microeconomics across all universities