CIVE5172M Chap.9 Resource Planning and Communication Plans
Resource Planning and Communication Plans
Resource Planning and Communication Plans covers two essay sections that each carry fifteen marks and each ask you to present tools and then evaluate them in practical terms. Resource planning begins with the recognition that every project starts with people, materials, plant and equipment, and that allocating them well is critical to cost effectiveness.
The chapter explains the product breakdown structure, which divides the finished facility into components, and the work breakdown structure, which divides the construction process into tasks, then shows how resources attach to tasks and feed the schedule and budget.
The questions a project manager asks before allocating resources, about skills, availability, authority and the effect on time and cost, are set out as a checklist.
Communication planning then draws on several weeks of the module: the communications management plan inside the project management plan, a communications strategy that settles how often, how and why to communicate, reports matched to their audience, and the particular weight of visual communication in construction.
A model communication plan for an operational depot rebuild shows how channels follow audiences, and self-test cards practise classifying breakdown items and choosing visual tools.
What this chapter covers
- 01
Resources: people, materials, plant and equipment
- 02
Product breakdown and work breakdown structures
- 03
Questions before allocating resources
- 04
The resource management plan
- 05
Communications strategy: how often, how and why
- 06
Visual tools, 4D models and logistics plans
- 07
Evaluating plans in practical terms
Worked example · free
Sort a canopy project into product and work breakdowns
- 1Product breakdown: the canopy divides into foundations, steel frame and roof sheets.
- 1Work breakdown: the canopy works divide into excavate and pour, erect steel and fix sheeting.
- 1Each product maps to the task that builds it, which exposes any component without a task or task without a product.
- 1Crews, plant and materials attach to the work breakdown tasks, where durations and costs can be estimated.
Key terms
- Product breakdown structure
- A hierarchy that divides the proposed facility into all its components.
- Work breakdown structure
- A hierarchy that divides the construction process into all its tasks.
- Communications management plan
- The part of the project management plan that sets out how the project communicates.
Resource Planning and Communication Plans FAQ
What is the difference between a PBS and a WBS?
A product breakdown structure divides the finished facility into its components, such as foundations and frame. A work breakdown structure divides the construction process into tasks, such as excavation and erection. Resources, durations and costs are attached to the tasks.
What should a communications strategy define?
The frequency of contact, the channel used and the purpose each message must serve. It sits within the communications plan, and it should be shaped by the audience, because reports and meetings need to match each group's level of detail and preferred format.
How are the resource and communication sections of the essay marked?
Each carries fifteen marks. The resource section asks you to present resource planning tools and techniques for the Leeds tram and evaluate them practically, and the communication section asks for a communication plan for the project with a practical evaluation of it.
Assessment move
Treat both topics as present-then-evaluate exercises. For resources, choose a small structure and draw its product breakdown and work breakdown side by side, then pair every product with the task that builds it.
Attach a crew, a plant item and a material to each task and ask the checklist questions: which skills are needed, who is available, do they have the skills, what authority is needed to free or buy in people, and how will the choice change time and cost? Write one paragraph evaluating a resource tool in practical terms, naming what it demands in effort and data and where it would struggle.
For communication, draft a plan as a table with audience, purpose, channel, frequency and owner, then test each row: would this group actually read this channel at this frequency? Include at least one visual tool and justify it, since construction relies heavily on drawings, models and charts.
Finally, evaluate the plan's weakest point honestly, such as dependence on one coordinator, because the marks reward practical judgement rather than a longer table.
Working through Resource Planning and Communication Plans in CIVE5172M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5172M Resource Planning and Communication Plans question and get a clear, step-by-step explanation grounded in how CIVE5172M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.