CIVE5360M Chap.2 Contract Strategy: Definitions, Roles and Responsibilities
Contract Strategy: Definitions, Roles and Responsibilities
Contract Strategy: Definitions, Roles and Responsibilities covers the Week 2 lectures on what a contract strategy is, what comes before it and who does what once it is chosen.
The chapter treats a strategy as a linked bundle of choices, namely procurement route, payment option, design responsibility and allocation of risk, and traces each back to four antecedents from the Holyrood evidence: the client body, the project team, the true ranking of objectives and the client's risk profile.
It defines traditional contracting and construction management side by side, compares the Treasury model roles of project owner, sponsor and manager with the NEC project manager and supervisor, and finishes with the Week 3 seminar on collaboration between professional disciplines. A worked allocation shows how routine NEC duties divide between the project manager, the supervisor and the client.
What this chapter covers
- 01
Contract strategy as linked choices
- 02
Four antecedents of a strategy
- 03
Traditional contracting and construction management defined
- 04
Project owner, sponsor and manager
- 05
NEC project manager and supervisor
- 06
Collaboration between professional disciplines
Worked example · free
Read antecedents into strategy choices
- 1Client body: limited experience points away from routes that need an informed, decisive client, such as construction management.
- 1Risk profile: a fixed price before starting favours a firmer payment basis and more risk with the contractor.
- 1Objectives: cost ranked above time removes the main reason for a fast-track route.
- 1Design responsibility: with little in-house capability, transferring more design to the contractor is worth testing.
Key terms
- Antecedent
- A fact about the client or project, fixed before drafting, that narrows which strategies are sensible.
- Project owner
- In the Treasury model quoted by the inquiry, the role taking strategic decisions for the client.
- NEC supervisor
- The NEC role responsible for compliance, testing and defects, engaged by the client but acting impartially.
- Trade package
- A separately tendered portion of the works let directly by the client under construction management.
Contract Strategy: Definitions, Roles and Responsibilities FAQ
How does traditional contracting differ from construction management?
Under traditional contracting design is substantially complete before construction is tendered and one contractor builds. Under construction management the design, tender and construction stages run in parallel, trade packages are contracted to the client and a consultant co-ordinates them, so price certainty comes only when the last package is let.
What are the antecedents of a contract strategy?
The inquiry records an expert's four areas: the client body's experience and attitude to risk, the project team's capability and ability to collaborate, the real ranking of time, quality and cost, and whether a fixed price is needed before work starts.
Why is it misleading to call a construction manager the builder?
The inquiry explains that the construction manager secures and manages trade contractors who are contracted directly to the client and does no construction work itself. Calling it the contractor hides the fact that the client holds the package contracts and their risk.
Does the NEC project manager need client approval to act?
The contract requires no formal approval, but the NEC guide advises agreeing with the client where dialogue is appropriate, such as changing requirements or accepting quotations, particularly when the contractor is in effect spending the client's money.
How can procurement support collaboration between disciplines?
Clause 10.2 asks the parties to act in a spirit of mutual trust and co-operation, and Fraser recommended evaluating whether a signature architect and a local practice have compatible working cultures before appointment. Co-locating the team also helps, according to the expert evidence.
What does the supervisor's workload depend on?
The NEC guide says it depends on how much testing the scope requires, on how much of that testing the supervisor must witness directly rather than audit through the contractor's quality assurance, and on the standard of the contractor's workmanship. The role should be sized from the scope rather than from habit.
Exam move
Draw two organisation charts for the same project, one under traditional contracting and one under construction management, and mark who holds each contract and who carries interface risk. Add the NEC project manager and supervisor to the traditional chart and list their routine processes. Then answer the Week 3 seminar questions in writing, using one contract mechanism and one case finding in each answer.
Test yourself by explaining, without notes, why the construction manager is an adviser and who then holds each trade contract.
Working through Contract Strategy: Definitions, Roles and Responsibilities in CIVE5360M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5360M Contract Strategy: Definitions, Roles and Responsibilities question and get a clear, step-by-step explanation grounded in how CIVE5360M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.