University of Leeds · FACULTY OF PROJECT MANAGEMENT

CIVE5360M Chap.3 Payment Methods and Sources of Funds

- one subject, every graph, every model, every mark
6 Chapters4-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 3 of 8 · CIVE5360M

Payment Methods and Sources of Funds

Payment Methods and Sources of Funds covers the Week 3 lectures on how contractors and consultants are paid and where project money comes from. The chapter starts with the NEC main payment options named in the module's NEC guide, among them target cost, lump sum, re-measurement and cost reimbursable, and the active joint management that the target cost and cost reimbursable options demand.

It then uses the Holyrood fee record: a construction management fee of 1.25% that was never converted to a lump sum, consultants paid a percentage of construction cost without limit, the Auditor General's suggestion of tapered fees and a guaranteed maximum price rejected as too costly in 2000. It closes on the early choice between private finance and conventional public funding.

Worked figures compare percentage, lump sum and tapered fees on the same overrun.

In this chapter

What this chapter covers

  • 01

    NEC main payment options

  • 02

    Percentage fees and cost overruns

  • 03

    Lump sum conversion as an incentive

  • 04

    Tapered and capped fees

  • 05

    Guaranteed maximum price late in a project

  • 06

    Private finance versus conventional funding

Worked example · free

Read the fee gap from the 1.25% chart

Q [3 marks]. Using a fee rate of 1.25% and a lump sum fixed on a £50m cost plan, find the fee on a percentage basis and on the lump sum when construction cost reaches £200m, and state the overrun reward. The marks shown are an AskSia practice weighting, not an official University allocation.
An illustrative fee at the printed 1.25% rate grows in step with construction cost, reaching £2.5m at £200m, while a lump sum agreed on a £50m cost plan stays aAn illustrative fee at the printed 1.25% rate grows in step with construction cost, reaching £2.5m at £200m, while a lump sum agreed on a £50m cost plan stays at £0.625m however far costs rise.£1m£2m1.25% fee: £2.5mlump sum: £0.625m£50m£100m£150m£200mconstruction cost
An illustrative fee at the printed 1.25% rate grows in step with construction cost, reaching £2.5m at £200m, while a lump sum agreed on a £50m cost plan stays at £0.625m however far costs rise.
  • 1Percentage basis: 1.25% × £200m = £2.5m.
  • 1Lump sum: 1.25% × £50m = £0.625m, unchanged by outturn.
  • 1Overrun reward: £2.5m − £0.625m = £1.875m paid only because cost rose.
At £200m the percentage fee is £2.5m against a lump sum of £0.625m, so £1.875m of fee depends on the overrun.
Sia tip — Compute every fee basis on the same outturn before comparing, then name who gains from the overrun.
Glossary

Key terms

Percentage fee
Payment of an adviser as a fixed share of construction cost, so the fee rises whenever cost rises.
Lump sum fee
A fixed fee agreed in advance, often on a cost plan, that does not move with outturn cost.
Tapered fee
An arrangement whose percentage falls as construction cost rises, reducing the reward for overruns.
Guaranteed maximum price
A ceiling on price offered in return for transferring cost risk, usually at a premium.
Private finance
Funding a facility through a private partner, described in the expert evidence as essentially buying a service.
FAQ

Payment Methods and Sources of Funds FAQ

Which NEC payment options does the module guide name?

The NEC guide says an Engineering and Construction Contract uses one of six main payment options, naming target cost, lump sum, re-measurement and cost reimbursable among them. It adds that the target cost and reimbursable options make the project manager's role one of active joint management.

Why did the Holyrood fee basis matter?

The consultants were paid a fixed percentage of construction cost without limit, so every cost increase raised their fees, and the client found it had no contractual right to cap them. Fraser judged that a lump sum would have given the construction manager a strong incentive to control cost.

What is a tapered fee?

The Auditor General suggested that consultants' percentage fees could have been tapered so the percentage fell as construction cost increased. Fraser agreed with that observation, adding that for the construction manager the missing lump sum conversion mattered more.

Why was a guaranteed maximum price rejected in 2000?

The progress group was advised that transferring risk while part of the design was still early would add several tens of millions of pounds. Fraser added that any such price would have far exceeded the £195m budget and raised procurement law difficulties.

Was choosing public funding over private finance wrong at Holyrood?

Fraser could not conclude it was wrong or that it caused the delay and cost. Ministers rejected private finance because it might cause unacceptable delay; the weakness lay in the later failure to analyse conventional routes properly.

When should the payment basis be fixed?

Before risk accumulates. The Holyrood construction manager offered to swap its 1.25% fee for a fixed sum once the cost plan was agreed, but the formal agreement omitted the conversion, and when the progress group later looked at a guaranteed maximum price, it was advised the risk transfer would be far too costly.

Study strategy

Exam move

Set up a small table with three fee bases as columns and three outturn costs as rows, then fill it by hand until the arithmetic is automatic. Under each table, write one sentence on who carries the overrun. Then summarise the Holyrood fee story in five dated lines and practise linking it to Treasury guidance on price certainty and to the funding decision.

Close by explaining in one paragraph why the choice of funding source does not settle the choice of route.

Working through Payment Methods and Sources of Funds in CIVE5360M? Sia is AskSia’s AI Project Management tutor — ask any CIVE5360M Payment Methods and Sources of Funds question and get a clear, step-by-step explanation grounded in how CIVE5360M is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your subjects at University of Leeds, plus 1,000+ more Bibles across the AskSia library.
Sia - your CIVE5360M tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works