FIT5057 Chap.4 Risk and Governance
Risk and Governance
This chapter governs the project under uncertainty. It walks the risk management process and the risk register, then the two ways to analyse a risk: qualitatively with the probability×impact (P×I) matrix, and quantitatively with expected monetary value (EMV = probability × impact in $).
It covers the response strategies — for threats: avoid, transfer, mitigate, accept; for opportunities: exploit, share, enhance, accept — which the quiz loves to mix up.
The governance half centres on Earned Value Management (EVM): planned value (PV), earned value (EV) and actual cost (AC) give the variances and indices (SV, CV, SPI, CPI) that say whether a project is ahead or behind, over or under budget. It closes on KPIs / RAG status and integrated change control.
EVM interpretation (a negative CV means over budget) is prime quiz material; the full calculation is project-assignment work.
What this chapter covers
- 01
6.1 The risk management process & the risk register
- 02
6.2 Qualitative analysis — the P×I matrix
- 03
Quantitative analysis — EMV (probability × impact)
- 04
6.3–6.4 Response strategies (threats vs opportunities)
- 05
Earned Value Management — PV, EV, AC and the indices
- 06
Worked EVM — a project at its data date
- 07
6.5–6.6 KPIs / RAG status & integrated change control
Worked example: reading an Earned Value snapshot
- +1Schedule variance: SV = EV − PV = 40,000 − 50,000 = −$10,000 — negative, so the project is behind schedule.
- +1Cost variance: CV = EV − AC = 40,000 − 45,000 = −$5,000 — negative, so the project is over budget.
- +1Schedule performance index: SPI = EV / PV = 40,000 / 50,000 = 0.80 — below 1, confirming behind schedule (doing 80% of planned work).
- +1Cost performance index: CPI = EV / AC = 40,000 / 45,000 ≈ 0.89 — below 1, confirming over budget (getting $0.89 of value per $1 spent).
- +1One-line read: negative variances and both indices below 1 → the project is behind schedule and over budget.
Key terms
- Risk register
- The living document that records each identified risk with its description, probability, impact, score, owner and planned response. A "good" risk is written as a cause-event-effect statement, not a vague worry — it must be specific enough to assess and assign.
- Expected monetary value (EMV)
- The quantitative value of a risk: EMV = probability × impact (in $). It converts a risk into a single dollar figure so risks can be compared and reserves sized. Used in decision-tree analysis to weigh options under uncertainty.
- Risk response strategies
- For threats: avoid, transfer, mitigate, accept. For opportunities: exploit, share, enhance, accept. The pairs mirror each other (transfer/share, mitigate/enhance), and the quiz tests whether you apply a threat strategy to a threat and an opportunity strategy to an opportunity.
- Earned value (EV) and the variances
- EV is the budgeted cost of work actually completed at the data date. With planned value (PV) and actual cost (AC): schedule variance SV = EV − PV, cost variance CV = EV − AC. Negative means behind / over; positive means ahead / under.
- CPI and SPI
- The performance indices. Cost performance index CPI = EV / AC; schedule performance index SPI = EV / PV. Above 1 is good (under budget / ahead of schedule); below 1 is bad. They normalise the variances into a ratio you can compare across projects.
Risk and Governance FAQ
What does a negative cost variance mean?
Over budget. CV = EV − AC, so a negative CV means actual cost exceeds the value earned — you have spent more than the work completed is worth. Likewise a negative SV (EV − PV) means behind schedule. The sign rule is the one thing the quiz reliably tests: negative variance = bad, and the corresponding index (CPI or SPI) is below 1.
What's the difference between a risk and an issue?
A risk is a potential future event that may or may not happen (uncertain, managed proactively with a response plan). An issue is a risk that has already occurred — it is now a current problem to be resolved. You analyse and plan for risks; you manage and resolve issues. The quiz tests this distinction directly.
How do I match a response strategy to a risk?
First decide if it is a threat (negative) or an opportunity (positive). Threats: avoid (remove it), transfer (shift it, e.g. insurance), mitigate (reduce probability or impact), accept. Opportunities: exploit (make sure it happens), share (partner to capture it), enhance (increase its probability or impact), accept. Applying "mitigate" to an opportunity, or "enhance" to a threat, is the classic mix-up.
Do I have to compute full EVM in the quiz?
Rarely the full set under time pressure — the quiz tests the interpretation (what does CPI < 1 mean, is a negative SV good or bad). The full EVM calculation at a data date is most relevant to the project assignment's governance section. Learn the four formulas (SV, CV, SPI, CPI) and the sign/threshold rules cold.
Exam move
Master the EVM sign rules above everything else here, because they are the most testable: SV and CV negative = behind / over; SPI and CPI below 1 = behind / over; positive / above 1 = ahead / under. Be able to write the four formulas and read a snapshot in one line. For risk, keep the threat and opportunity strategy lists paired and remember EMV = probability × impact.
Distinguish risk from issue, contingency from management reserve, and qualitative (P×I) from quantitative (EMV) analysis. For the assignment's governance section, you will produce a real risk register and an EVM read, so practise both end to end.