FIT5057 · Project Management
Project Management
Project Management (FIT5057) teaches how to plan and run an information-technology project end to end — from the iron triangle and PMBOK 7, through scope and the WBS, CPM/PERT scheduling and earned value, risk and governance, stakeholders and quality, into agile delivery with Scrum. There is no traditional final exam: your grade is two 40% project assignments (a predictive plan, then an agile project) plus a 20% invigilated Quiz/Test — a short, locked-down, closed-book sitting in Safe Exam Browser that rewards fast concept recognition. This guide teaches each framework to assessment standard: the diagram or calculation the markers reward, the distinction the quiz tests, and where the marks hide.
What FIT5057 covers
Twelve teaching weeks → one exam-ready map. Each links to its free chapter guide.
How FIT5057 is assessed
| Component | Weight | Format |
|---|---|---|
| Assignment 1 — Predictive Project | 40% | Business case → charter → scope & WBS → Gantt/CPM → cost → risk → governance |
| Assignment 2 — Agile Project | 40% | Personas → backlog → sprints → Scrum-board demo + interview |
| Quiz / Test | 20% | Safe Exam Browser · closed-book, invigilated · short MCQ block testing concept recognition across all 12 weeks — confirm the exact split in your unit guide |
Critical Path Method — the signature calculation, step by step
- +2Forward pass (earliest dates): A finishes at 3; B at 3+2 = 5 and C at 3+4 = 7; E at 5+2 = 7 and D at 7+5 = 12. F waits for the later of its two predecessors, max(12, 7) = 12, then F finishes at 12+3 = 15.
- +2Backward pass (latest dates): start from the finish of 15 and work right→left: LFF = 15, LFD = 12, LFC = 7, LFE = 12, LFB = 10. Where an activity has two successors, take the minimum.
- +1Float = latest − earliest: A, C, D and F have zero float; B and E each have 3 days of total float (their path A→B→E→F is only 10 days, 5 short of 15, shared as 3 days each).
- +1State it: the critical path is the zero-float chain A → C → D → F = 3 + 4 + 5 + 3 = 15 days; this is the longest path, so it sets the deadline and has no slack.
Key terms
- Iron triangle (triple constraint)
- Scope, time and cost locked together around quality — move one corner and at least one other must give. The logic behind almost every change-request decision; quality is the centre that quietly erodes if the triangle is squeezed.
- Work breakdown structure (WBS)
- A deliverable-oriented decomposition of the total project scope into smaller, manageable work packages. It must obey the 100% rule (the children fully define the parent, no more, no less) and is built from nouns (deliverables), not verbs (activities).
- Critical path
- The longest path of dependent activities through the network, and therefore the shortest time the project can finish. Its activities have zero float — any slip on the critical path slips the whole project.
- Earned value (EV)
- The budgeted cost of the work actually completed at the data date. Compared with planned value (PV) and actual cost (AC), it yields the schedule and cost variances and indices (SV, CV, SPI, CPI) that tell you whether a project is ahead or behind, over or under budget.
- Sprint
- A short, fixed-length iteration (typically one to four weeks) in Scrum, at the end of which a potentially shippable increment is delivered. Sprints make delivery frequent and create regular feedback points — the heart of the adaptive approach.
FIT5057 FAQ
Is FIT5057 hard?
It is broad rather than deep: a postgraduate survey that spans predictive planning, scheduling and earned-value maths, and agile delivery in twelve weeks. The challenge is volume and precision — getting the distinctions crisp (scope vs WBS vs activity, review vs retrospective) for the quiz, and applying the full method correctly across the two project assignments.
How is FIT5057 assessed?
There is no traditional final exam. Your mark is two 40% project assignments — a predictive project (business case through to risk and governance) and an agile project (personas through to a Scrum-board demo) — plus a 20% invigilated Quiz/Test in Safe Exam Browser. Confirm this year's exact split in your unit guide.
What does the FIT5057 quiz actually test?
Concept recognition, fast and closed-book. It is a short MCQ block (“select the most suitable answer”) that covers content up to its week: project vs operations, PMBOK 7 principles vs the 8 performance domains, dependency types (FS/SS/FF/SF), reading a negative cost variance, risk vs issue, Scrum roles and events, MoSCoW. It does not demand a full multi-step hand calculation — those matter most for the project assignments.
Do I need to memorise PMBOK 7 and Scrum exactly?
Yes for the quiz, at the level of clean distinctions and counts: PMBOK 7 has 12 principles and 8 performance domains; PMBOK 6 has 5 process groups and 10 knowledge areas; Scrum has 3 roles, 5 events, 3 artifacts and 3 commitments. The quiz loves to swap a count or put a domain into a list of principles as the odd one out.
Is using AskSia for FIT5057 cheating?
No. AskSia is a study reference written in our own words — we host none of your lecturer's files, and Sia teaches you the method to earn the marks; it does not complete or sit your assessments.
How to study for the exam
Hold the unit on two ideas: the iron triangle (scope/time/cost around quality) and the predictive ↔ adaptive spectrum (PMBOK 7 = why, PMBOK 6 = the predictive how, Scrum = the adaptive how). For the quiz, drill crisp distinctions and counts — project vs operations, principles vs domains, FS vs SS, review vs retrospective, story points vs hours — because it is won on recognition under lockdown, not arithmetic. For the two 40% project assignments, treat the chapters as a build manual: every artefact A1 and A2 ask for (charter, scope statement, WBS, Gantt, cost model, risk register, persona, backlog, sprint plan) has a worked template, and the CPM and EVM calculations are where careful working banks marks.