Monash University · FACULTY OF PROJECT MANAGEMENT

FIT5057 Chap.3 Schedule and Cost Management

- one subject, every graph, every model, every mark
6 Chapters4-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 3 of 7 · FIT5057

Schedule and Cost Management

Schedule and Cost Management connects activity dependencies with estimates, resources and approved spending. You will read precedence networks, identify a controlling path, distinguish milestones from dependencies, and explain the trade-offs in crashing or fast tracking.

Cost practice begins with hours, rates and work packages, then builds a time-phased baseline and keeps that control reference separate from investment benefits and net present value. The chapter starts with network logic because a Gantt display cannot explain its own dates. Activities, predecessors, durations and calendars create the schedule, while milestones mark significant control points.

Original examples calculate a controlling route and show why a parallel branch can have limited flexibility without changing the finish. The cost section traces hours and rates back to work packages, reconciles period totals and makes the basis of estimate visible. It then separates authorised funding and the delivery baseline from sponsor benefits.

The investment section recomputes discounted future cash flows and tests sensitivity to a weaker benefit. Together these exercises prepare you to show how a number was obtained, what assumption drives it, and which schedule or investment decision should follow. Reconciliation protects that logic when actual progress begins to diverge.

In this chapter

What this chapter covers

  • 01

    Activities, dependencies and milestones

  • 02

    Precedence networks and critical paths

  • 03

    Schedule compression trade-offs

  • 04

    Hours, rates and basis of estimate

  • 05

    Time-phased cost baselines

  • 06

    Discounted cash flow and net present value

Worked example · free

Reconcile a three-period cost baseline

Q [5 marks]. The mark allocation attached to this reconciliation is not a University assessment scheme. A project spends $3,000 in Month 1, $4,500 in Month 2 and $2,500 in Month 3. A $600 testing activity moves from Month 2 to Month 3 without changing total scope. What are the revised period totals and project total?
Box widths equal the printed durations and horizontal positions equal earliest starts; the upper route controls the ten-day launch date.Box widths equal the printed durations and horizontal positions equal earliest starts; the upper route controls the ten-day launch date.Discover2 daysDesign3 daysConfigure4 daysTrain2 daysLaunch1 days
Box widths equal the printed durations and horizontal positions equal earliest starts; the upper route controls the ten-day launch date.
  • +1Remove $600 from Month 2: $4,500 minus $600 equals $3,900.
  • +1Add $600 to Month 3: $2,500 plus $600 equals $3,100.
  • +2Revised total = $3,000 + $3,900 + $3,100 = $10,000, unchanged because only timing moved.
  • +1Check whether the timing change affects dependencies, milestone evidence or cash availability.
The revised baseline is $3,000, $3,900 and $3,100. Total approved cost remains $10,000, but the time profile and any dependent control points must be reviewed.
Sia tip — Reconcile both by period and in total. A timing change can leave total cost unchanged while still affecting the schedule and cash plan.
Glossary

Key terms

Dependency
A logical relationship that constrains when one project activity can occur relative to another.
Milestone
A zero-duration control point marking a significant decision, approval or completion event.
Critical Path
The longest controlling activity route through the network, determining the planned finish date.
Discount Rate
The required return used to translate future cash flows into their present value.
FAQ

Schedule and Cost Management FAQ

Why is a Gantt chart not enough for schedule reasoning?

A Gantt chart displays timing, but the dependency logic explains why activities start and finish when shown. The network also reveals which route controls the finish and where limited scheduling flexibility exists.

What is the difference between a budget and a cost baseline?

A budget is authorised funding. A cost baseline is the approved time-phased reference used to monitor planned project spending. The baseline connects estimated work with the periods in which that work is scheduled.

Does a positive net present value approve a project?

It supports financial value under the stated cash-flow and discount-rate assumptions. Decision-makers must still test feasibility, strategic fit, ethics, sustainability, delivery risk and whether another option creates greater overall value.

When does a schedule compression choice make sense?

Use crashing only where additional resources can shorten controlling work at an acceptable cost. Use fast tracking only where overlap is feasible and the team accepts added coordination and rework risk. Recalculate the network after either change.

Study strategy

Assessment move

Draw small activity networks and calculate each path from the printed durations before looking at a Gantt display. For costs, rebuild totals from hours, rates and quantities, then reconcile work packages with period totals. Keep delivery funding, cost baseline and benefits in separate columns. Recompute a simple NPV with a changed benefit or discount rate and explain the sensitivity.

Finish each exercise by naming the schedule or investment assumption that most threatens the recommendation. Use five activities with at least one parallel branch. Write predecessors first, calculate earliest starts, total every route and identify the controlling path. Then change one duration and explain whether the project finish moves or only available flexibility changes.

When practising compression, state whether crashing adds cost or fast tracking adds coordination and rework risk. For the cost model, annotate the basis of each hour, quantity and rate, then phase the work into periods and reconcile the column totals with the project total. Move one activity between periods to see how timing can change while total authorised cost stays constant.

For investment value, print Year 0 with a negative sign, discount every later net cash flow and test one downside scenario. A strong answer does not stop at a positive or negative number. It explains which assumption drives the result and whether delivery feasibility, compliance or stakeholder value changes the recommendation.

Working through Schedule and Cost Management in FIT5057? Sia is AskSia’s AI Project Management tutor — ask any FIT5057 Schedule and Cost Management question and get a clear, step-by-step explanation grounded in how FIT5057 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 171 of your subjects at Monash University, plus 1,000+ more Bibles across the AskSia library.
Sia - your FIT5057 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works