Earned Value, Control and Closure

Measure performance on a common basis

Earned value management compares planned value, earned value and actual cost at one status date. Schedule performance index divides earned value by planned value, while cost performance index divides earned value by actual cost. Ratios below one are unfavourable against the baseline, but diagnosis still requires work-package evidence.

Control turns variance into forecast and action. Closure then confirms acceptance, settles obligations, transfers ownership, releases resources and preserves learning.

Keep control and closure accountable

An index summarises baseline performance; it does not reveal the cause or guarantee the forecast.

Trace variance to packages, state the forecasting assumption and process any authorised change without rewriting history. At completion or termination, screen partial work, contracts, data, assets and residual actions. Transfer each obligation to a durable owner before releasing the temporary team.

Lessons should name the failed assumption, supporting evidence and changed practice, so future planning can use the closeout record rather than merely archive it.

In this chapter

What this chapter covers

  • 01

    The control cycle and baseline integrity

  • 02

    Planned value, earned value and actual cost

  • 03

    Schedule and cost variances

  • 04

    SPI and CPI interpretation

  • 05

    Forecast assumptions and authorised change

  • 06

    Termination, acceptance and formal closeout

Worked example · free

Interpret one earned value status point

Q [8 marks]. AskSia-authored practice. At the status date PV is $120,000, EV is $90,000 and AC is $100,000. Calculate and interpret SPI and CPI. The marks shown are an AskSia study allocation, not a University marking scheme.
The three curves answer different questions.The three curves answer different questions. At the status date earned value below planned value signals delay, while actual cost above earned value signals cost inefficiency.PVEVACstatus datetimecumulative value or cost
The three curves answer different questions. At the status date earned value below planned value signals delay, while actual cost above earned value signals cost inefficiency.
  • 3Compute SPI using EV and PV.
  • 3Compute CPI using EV and AC.
  • 2Interpret without overstating calendar delay or final outcome.
SPI is 0.75 and CPI is 0.90. The project has earned less budgeted value than planned and has spent more than the budgeted value of completed work. Both dimensions are unfavourable at this date, but the ratios do not identify the cause or guarantee the final result.
Sia tip — Actual cost belongs in CPI, never in SPI.
Glossary

Key terms

Planned Value
The budgeted value of work scheduled for completion by the status date.
Earned Value
The budgeted value of work actually completed by the status date.
Actual Cost
The expenditure incurred for the work completed by the status date.
Schedule Performance Index
Earned value divided by planned value, used to compare completed and scheduled value.
Cost Performance Index
Earned value divided by actual cost, used to compare budgeted accomplishment with spending.
FAQ

Earned Value, Control and Closure FAQ

How does the final status report support closure?

Reconcile the last planned value, earned value and actual cost figures to accepted scope, then explain remaining variance without rewriting the historical baseline. List every contract, claim, asset, data set and residual action that survives closure, assign each to an operational owner and preserve the acceptance or termination authority in the closeout evidence pack.

Can actual spending show how much work is complete?

No. Spending records cost, not accomplishment. Earned value applies the approved budget to completed work, allowing progress to be compared with planned value and cost efficiency to be compared with actual cost.

Does an SPI of 0.75 mean the project is twenty-five per cent late?

It means the project has earned seventy-five cents of budgeted work for each planned dollar at the status date. It is a value ratio, not a direct measure of calendar lateness. Network and milestone evidence are needed for time impact.

What must formal closure accomplish?

Closure confirms acceptance or an authorised termination state, settles contracts and accounts, transfers records and residual responsibilities, releases resources and preserves lessons. Cancellation does not remove existing obligations, so terminated projects still need controlled closeout.

Study strategy

Assessment move

Create a time-phased budget for a small project and choose a status date. For each work package, record the budgeted value scheduled, the budgeted value of completed work and the actual cost. Sum those values to PV, EV and AC only after confirming that scope and timing use the same baseline. Calculate schedule variance, cost variance, SPI and CPI.

Write the formulas from memory and circle the denominator so actual cost never enters SPI. Interpret ratios against one without translating SPI directly into calendar lateness. Trace the unfavourable dimension to individual packages and write a cause that could be investigated.

Add two completion forecasts using different assumptions about whether past cost efficiency continues, and explain why the assumption matters more than extra decimal places. Practise the control cycle by moving from status evidence to cause, forecast, corrective action and an authorised change request. Keep the original baseline unless governance approves changed scope or conditions; never use rebaselining to hide variance.

For closure, build separate checklists for normal completion and early termination. Both should address acceptance or termination authority, contracts and invoices, partial deliverables, records, operational ownership, unused resources and lessons. Take a cancelled project and name which obligations survive the decision to stop. Finish with an oral explanation of one EVM result and one closeout recommendation.

The answer should state the measure, its meaning, the evidence needed next and the management action. That sequence connects calculation to control and control to a responsible finish.

Working through Earned Value, Control and Closure in CDT505? Sia is AskSia’s AI Project Management tutor — ask any CDT505 Earned Value, Control and Closure question and get a clear, step-by-step explanation grounded in how CDT505 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 11 of your Lingnan University subjects - and 1,000+ Bibles across every Australian university.
Sia - your CDT505 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
CDT505 · Project Management: Concepts and Tools - independent study guide on the AskSia Library. More Lingnan University subjects · Microeconomics across all universities