Network Scheduling and Critical Paths

Compute dates from dependency logic

An activity-on-node network turns work packages into activities and dependencies. Three-point estimates provide expected durations through the PERT formula. A forward pass establishes earliest dates, using the largest predecessor finish at a merge. A backward pass establishes latest dates, using the smallest successor start at a burst.

Total float is the difference between latest and earliest dates. The longest zero-float route is the critical path that controls the earliest project finish.

Audit logic before trusting arithmetic

Every arrow is a claim that one activity constrains another. Missing links create impossible overlap, while unnecessary links make parallel work falsely serial.

Milestones can carry approval dependencies even when their duration is zero. After calculating float, change one estimate on a near-critical branch and rerun the network; the exercise shows that criticality belongs to the current plan rather than permanently to an activity. Completion probability adds uncertainty, but its interpretation should state the assumed path and any close competing route.

In this chapter

What this chapter covers

  • 01

    Activity-on-node dependency logic

  • 02

    Optimistic, most likely and pessimistic estimates

  • 03

    PERT expected duration

  • 04

    Forward pass and merge maximums

  • 05

    Backward pass and burst minimums

  • 06

    Float, critical paths and completion probability

Worked example · free

Calculate a merged activity network

Q [10 marks]. AskSia-authored practice. Two branches follow a three-day start: one lasts five then six days, the other four then three days. A two-day finish waits for both. Find duration and float. The marks shown are an AskSia study allocation, not a University marking scheme.
The critical path is a consequence of the whole network.The critical path is a consequence of the whole network. The red route is longest at sixteen days, while the lower branch carries float because it reaches the merge earlier.A 3B 5C 4D 6E 3F 2red path A-B-D-F controls the 16-day finish
The critical path is a consequence of the whole network. The red route is longest at sixteen days, while the lower branch carries float because it reaches the merge earlier.
  • 4Run the forward pass.
  • 3Run the backward pass.
  • 3Identify the path and branch float.
The longer branch reaches the merge at day fourteen and the shorter at day ten. The final activity finishes on day sixteen. The longer branch is critical and the shorter branch has four days of float under the stated logic.
Sia tip — At a merge, use the largest predecessor finish rather than adding parallel durations.
Glossary

Key terms

Activity-on-Node
A network convention in which activities appear as nodes and arrows show precedence.
Forward Pass
A left-to-right calculation of earliest activity start and finish dates.
Backward Pass
A right-to-left calculation of latest activity start and finish dates.
Total Float
The time an activity can move without delaying the project finish.
Critical Path
The longest required network route, with zero total float under the current baseline.
FAQ

Network Scheduling and Critical Paths FAQ

How can I audit a claimed critical path?

Work backward from the finish, selecting the predecessor that determines every merge, and verify each duration against its source estimate. Reperform the forward and backward passes before accepting the zero-float route. Then alter one dependency and recompute, because a logic change can affect the controlling path differently from a simple duration change.

Why does a merge use the largest predecessor finish?

A successor that requires several predecessors cannot start until all of them finish. The last required predecessor therefore controls its earliest start. Adding predecessor finishes would falsely turn parallel work into serial work and overstate the schedule.

What makes an activity critical?

Under the current network and durations, a critical activity has zero total float and sits on a route that controls the earliest project finish. Criticality can change after duration, logic or resource changes, so it should be recalculated.

What must the individual schedule include?

The current brief asks for milestones, at least seven key activities, optimistic, most likely and pessimistic durations, predecessor or successor logic, an expected-duration calculation, a simple logic diagram or table and a clearly identified critical path with an explanation.

Study strategy

Assessment move

Start with activity lists containing seven to nine activities so the network is complex enough to include a burst and a merge but still small enough to audit. Write predecessors before drawing arrows. Check for cycles, disconnected nodes and links that make parallel work falsely serial.

For every activity, calculate the PERT expected duration from optimistic, most likely and pessimistic estimates and keep the unrounded value until the convention in the question requires rounding. Run the forward pass left to right, writing earliest start and finish beside each node. At every merge, box the largest predecessor finish.

Then fix the project finish and run the backward pass, boxing the smallest successor latest start at every burst. Calculate float using both equivalent expressions as an arithmetic check. Trace the zero-float route and explain in words why it controls completion. Repeat the problem after changing one duration on a near-critical branch.

This shows that criticality is a current network property rather than a permanent activity label. Add a due date and, where the source method supplies variances, standardise it against critical-path uncertainty. State the assumption that path identity remains stable and note any close competing path.

For the current individual brief, audit that the plan includes milestones, at least seven activities, three-point estimates and predecessor or successor logic. Finish each practice answer with one management implication: which activity deserves monitoring, where float can absorb movement and what change would require a new baseline. Never present only a highlighted path; show the forward and backward evidence that creates it.

Working through Network Scheduling and Critical Paths in CDT505? Sia is AskSia’s AI Project Management tutor — ask any CDT505 Network Scheduling and Critical Paths question and get a clear, step-by-step explanation grounded in how CDT505 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 11 of your Lingnan University subjects - and 1,000+ Bibles across every Australian university.
Sia - your CDT505 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works
CDT505 · Project Management: Concepts and Tools - independent study guide on the AskSia Library. More Lingnan University subjects · Microeconomics across all universities