Cost Estimates, Budgets and Earned Value

Spending deliberately, not just spending less

The cost part of Week 4 frames project finance as estimating, securing, allocating, monitoring and forecasting the money needed to deliver value.

It helps decide whether an approach is affordable, what a change or recovery would cost, whether spending follows the plan, what the final cost is likely to be, and whether continued spending is still justified.

Layers that must stay separate

A cost estimate is not a budget, and the cost baseline is not necessarily the whole project budget.

Work-package estimates are aggregated, contingency is added for identified risks to form the cost baseline, and a governed management reserve sits outside it.

This chapter builds those layers for an original grandstand refurbishment, then covers direct, indirect, fixed and variable costs and the four estimating techniques: analogous, parametric, bottom-up and three-point.

Reading earned value

Planned value, earned value and actual cost combine scope, schedule and cost in one picture.

Comparing earned value with planned value shows schedule progress; comparing it with actual cost shows cost efficiency.

The chapter interprets a four-month status for the grandstand and closes with the practical financial control questions from Week 6.

Cost in the Team Project Plan

The plan brief asks for a planning-level estimate within the approved budget, with its basis, assumptions and a justified contingency.

This chapter's layers give that section its structure: estimate the work packages, link contingency to identified risks, keep management reserve separate, and explain any movement between cost categories.

In this chapter

What this chapter covers

  • 01

    Why project finance matters

  • 02

    Cost estimate, budget and cost baseline

  • 03

    Contingency reserve and management reserve

  • 04

    Direct, indirect, fixed and variable costs

  • 05

    Analogous, parametric, bottom-up and three-point estimates

  • 06

    Building an approved budget

  • 07

    Planned value, earned value and actual cost

  • 08

    Practical financial monitoring

Worked example · free

Build a grandstand budget from work packages, contingency and reserve

Q [4 marks]. A sports club's grandstand refurbishment has five work-package estimates: demolition $40k, structure $150k, seating $90k, electrical $60k and finishes $30k. Contingency for identified risks is $35k and management reserve is $25k. Find the cost baseline and the project budget, and say who controls each reserve. This mark allocation is for practice only and is not the university's published scheme.
Five work-package estimates add to $370k; contingency for identified risks lifts the cost baseline to $405k, and a governed management reserve outside the baselFive work-package estimates add to $370k; contingency for identified risks lifts the cost baseline to $405k, and a governed management reserve outside the baseline brings the project budget to $430k.$370kWork packages+$35k+ contingency$405kCost baseline+$25k+ reserve$430kProject budget
Five work-package estimates add to $370k; contingency for identified risks lifts the cost baseline to $405k, and a governed management reserve outside the baseline brings the project budget to $430k.
  • 1Aggregate the packages: 40 + 150 + 90 + 60 + 30 = $370k.
  • 1Add contingency for identified risks: $370k + $35k = $405k, the cost baseline.
  • 1Add management reserve outside the baseline: $405k + $25k = $430k, the project budget.
  • 1Contingency is drawn against identified risks; management reserve is released only through governance.
Cost baseline $405k and project budget $430k. Performance is measured against the $405k baseline, while the $25k reserve waits for unforeseen work and needs a governance decision to use.
Sia tip — Label every number in a budget answer with its layer, estimate, contingency, baseline or reserve; mixing them up is how a correct sum still loses the explanation marks.
Glossary

Key terms

Cost Baseline
The approved budget, spread across the schedule, against which cost performance is judged.
Contingency Reserve
Money or time set aside for risks that have been identified and given a planned response.
Management Reserve
Budget held outside the cost baseline for unforeseen work and released through governance.
Bottom-Up Estimate
An estimate built from lower-level work packages and added upward.
Earned Value
The budgeted value of the work actually completed by the status date.
Planned Value
The budgeted value of whatever work the plan said would be done by the status date.
FAQ

Cost Estimates, Budgets and Earned Value FAQ

Is the cost baseline the same as the project budget?

Not necessarily. The cost baseline includes the work estimates and contingency for identified risks; the project budget can also include management reserve held outside the baseline for unforeseen work, which is released only through governance.

When should I use a three-point estimate?

When the uncertainty itself matters. Optimistic, most likely and pessimistic values make the range visible instead of hiding it behind one number, and the gap between them shows where contingency may be needed. The estimate is only as good as its inputs.

How do I read earned value without formulas?

Make two comparisons. If earned value is below planned value, less work is done than planned, so the project is behind. If actual cost is above earned value, the completed work cost more than its budgeted value, so cost performance is unfavourable.

What makes a contingency defensible in a project plan?

A link to specific identified risks and their planned responses, plus a stated basis for its size. A contingency with no connection to the risk register, or reserve hidden inside every activity estimate, is hard to justify to a sponsor.

Study strategy

Assessment move

Set out a budget build-up for any small project in four lines, estimate, contingency, baseline and reserve, and say who controls each line. Then write three status snapshots of planned value, earned value and actual cost and interpret both comparisons for each in one sentence.

Working through Cost Estimates, Budgets and Earned Value in MGTS7527? Sia is AskSia’s AI Project Management tutor — ask any MGTS7527 Cost Estimates, Budgets and Earned Value question and get a clear, step-by-step explanation grounded in how MGTS7527 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 12 of your University of Queensland subjects - and 1,000+ Bibles across every Australian university.
Sia - your MGTS7527 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works