Chapter 12 of 13 · PMGT5871

Product Backlogs, User Stories and Estimation

The product backlog is the requirements source of an Agile project. This chapter explains the product and sprint backlogs, epics and personas, then the user story template with acceptance criteria and the INVEST checks.

It covers relative estimation with T-shirt sizes, the Fibonacci scale and planning poker, and finishes with value-based prioritisation, working a 100-point allocation and a paired comparison for a tutoring app of our own.

The Week 10 tutorial works through the same chain this chapter follows, using the second case study: create personas, write user stories with acceptance criteria, estimate their size as a team, then prioritise them. Done carefully, that chain produces a backlog ready to load into Jira in Week 11, which is why the quality of the stories here directly shapes Group Assignment 2.

In this chapter

What this chapter covers

  • 01

    Product backlog and sprint backlog

  • 02

    Epics and their breakdown into stories

  • 03

    Personas and how they guide priority

  • 04

    User story template and acceptance criteria

  • 05

    The INVEST model

  • 06

    T-shirt sizes, Fibonacci points and planning poker

  • 07

    Value-based prioritisation, paired comparison and the 100-point method

Worked example · free

Prioritising stories with the 100-point method

Q [3 marks]. The marks here are AskSia's revision weighting and not an official University scheme. Three members each spread 100 points over four stories: book a slot 50, 40, 45; cancel a booking 20, 25, 20; rate a tutor 10, 15, 10; profile photos 20, 20, 25. Rank the stories.
Reading down the layers, each one breaks the one above into smaller pieces, from the whole product backlog through epics and stories to the tasks a developer fiReading down the layers, each one breaks the one above into smaller pieces, from the whole product backlog through epics and stories to the tasks a developer finishes within a sprint. Product backlog Epics: large stories User stories, defects, issues Tasks and sub-tasks broad, strategic small, sprint-sized
Reading down the layers, each one breaks the one above into smaller pieces, from the whole product backlog through epics and stories to the tasks a developer finishes within a sprint.
  • 1Check each member's allocation sums to 100.
  • 1Totals: book 135, cancel 65, photos 65, rate 35.
  • 1Break the tie at 65 with a paired comparison and rank rate a tutor last.
Book a slot ranks first, cancel and photos tie and need a paired comparison, and rate a tutor ranks last.
Sia tip — Write the so-that clause of every story before sizing it; it states the value the product owner will rank.
Glossary

Key terms

Epic
A large user story, usually more than one sprint can complete, grouping stories that share a strategic aim.
Persona
A detailed fictional character representing a group of users, used to understand needs and set priorities.
Acceptance criteria
The objective conditions that decide whether a user story is done at the sprint review.
Story point
A relative measure of a story's size covering work, complexity and time for one team.
Planning poker
A consensus estimating technique in which developers reveal cards together and discuss differences before re-estimating.
FAQ

Product Backlogs, User Stories and Estimation FAQ

What is the user story template?

As a [persona], I want to [goal], so that [benefit], followed by acceptance criteria. The want-to part describes intent rather than interface features, and the so-that part explains the overall benefit the user is trying to achieve.

What does INVEST stand for?

Independent, Negotiable, Valuable, Estimable, Small and Testable. The slides put a ceiling of roughly three weeks of one person’s effort on a small story, and add that a story nobody can test can never be confirmed as done.

Why are story points not comparable between teams?

Points are relative to the team, the sprint and the complexity of the work, so a 5 for one team may not equal a 5 for another. Velocity forecasts therefore use each team's own history.

How should acceptance criteria be written?

As bullet points or in one of two formats: when an event occurs, then this should happen; or given a precondition, when an event happens, then an expected change follows. Either way they must be objective enough to decide at the sprint review whether the story is done.

How does planning poker work?

The product owner reads a story, developers ask questions and each privately chooses a card. The cards are revealed together. If the values agree the estimate is noted; if not, the team discusses the difference and estimates again until it reaches agreement.

What is the difference between the product backlog and the sprint backlog?

The product backlog lists all features, defects, issues and infrastructure needed for the final product and is updated regularly. The sprint backlog is a subset of it covering the deliverables for one time-bound sprint, with each story's details completed before the sprint starts.

Study strategy

Exam move

Write ten user stories for an app you use, each with a so-that clause and acceptance criteria in the given, when, then format, and run every one through the INVEST checks. Size them with Fibonacci points, then split any that you sized at the top of the scale. Practise the 100-point method and a paired comparison on the same set and see whether they agree.

For revision, keep a card with the backlog hierarchy from product backlog to tasks and the rule that work missing from the backlog is not a requirement. As a final step, load your ten practice stories into a simple table with points and priority, which is the shape of the backlog you will build in Jira.

Working through Product Backlogs, User Stories and Estimation in PMGT5871? Sia is AskSia’s AI Project Management tutor — ask any PMGT5871 Product Backlogs, User Stories and Estimation question and get a clear, step-by-step explanation grounded in how PMGT5871 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 196 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5871 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works