Chapter 5 of 13 · PMGT5871

Quality Planning and the Cost of Quality

Quality planning decides how fit for purpose each deliverable must be and how the team will prove it. This chapter separates quality from grade, introduces the standards and the four principles of quality management, and contrasts quality assurance, which prevents defects, with quality control, which finds and fixes them.

It prices quality with the cost of conformance and non-conformance, explains the 1:10:100 rule, and lays out the five columns of a quality plan with measurable acceptance criteria. Quality is taught in the same week as cost because the two are planned together: every prevention or appraisal activity needs budget and schedule time, and every failure the plan does not prevent becomes rework cost.

The Week 4 tutorial ends with groups developing a quality plan for the first case study, and the standards named in the slides, the ISO 9000 family and the guideline for quality management in projects, give that plan a reference point.

In this chapter

What this chapter covers

  • 01

    Quality compared with grade and gold plating

  • 02

    Quality considerations and standards

  • 03

    Four principles of quality management

  • 04

    Cost of conformance and cost of non-conformance

  • 05

    The 1:10:100 rule

  • 06

    Quality assurance compared with quality control

  • 07

    The five columns of a quality plan

Worked example · free

Pricing the cost of quality

Q [4 marks]. Marks here follow an AskSia revision weighting, not an official scheme. A software rollout spent $12,000 on prevention and $8,000 on appraisal, then $15,000 on internal failures and $30,000 on external failures. Calculate the cost of quality and comment.
Drawn to scale, the bars show the 1:10:100 rule: a dollar spent preventing a defect avoids ten dollars of fixing it inside the project and a hundred once it reaDrawn to scale, the bars show the 1:10:100 rule: a dollar spent preventing a defect avoids ten dollars of fixing it inside the project and a hundred once it reaches the customer.$1 prevention$10 internal failure$100 external failureCost of one defectbar height to scale
Drawn to scale, the bars show the 1:10:100 rule: a dollar spent preventing a defect avoids ten dollars of fixing it inside the project and a hundred once it reaches the customer.
  • 1Conformance: $12,000 + $8,000 = $20,000.
  • 1Non-conformance: $15,000 + $30,000 = $45,000.
  • 1Cost of quality: $20,000 + $45,000 = $65,000.
  • 1Comment: most cost is failure, so shift spending towards prevention.
The cost of quality is $65,000, of which $45,000 is non-conformance; the 1:10:100 rule points to more prevention spending.
Sia tip — Ask whether an activity stops a defect being made or finds one already made: the first is QA, the second is QC.
Glossary

Key terms

Grade
A class given to deliverables that do the same job but differ in their technical features.
Gold plating
Delivering a higher grade than required, which wastes time and money.
Quality assurance
The process of auditing quality requirements and quality control results to keep products and processes acceptable.
Quality control
The process of monitoring and recording quality results, checking completed work and fixing defects.
FAQ

Quality Planning and the Cost of Quality FAQ

What is the difference between quality and grade?

Quality is how far a deliverable's inherent characteristics fulfil its requirements, in other words whether it is fit for purpose. Grade, by contrast, is a class of deliverables with the same use but different technical features. A low-grade product can be high quality.

What does the 1:10:100 rule say?

Every dollar spent preventing defects saves about ten dollars of finding and fixing them inside the project and about one hundred dollars if defective products reach customers or end users, which is why prevention over inspection is a principle of quality management.

What columns does a quality plan contain?

For each product or process the plan records the quality definition, the standards to be met, measurable acceptance criteria, the quality assurance approach that will meet the definition and the quality control approach that will find and fix defects.

Is the cost of a quality inspection conformance or non-conformance?

An inspection is an appraisal activity, so its cost is part of the cost of conformance. Any rework or scrap the inspection reveals is an internal failure cost, which belongs to the cost of non-conformance.

What are the four principles of quality management?

Customer satisfaction, so that requirements reflect customer expectations; prevention over inspection, because preventing defects costs less than fixing them; continuous improvement of the ability to meet quality objectives; and managerial responsibility for making sure those objectives are met.

What is gold plating?

Gold plating means delivering a higher grade than the requirements call for, adding features or specifications nobody asked for. The Week 4 slides treat it as waste of time and money, the opposite risk to a grade so low that the product is not fit for purpose.

Study strategy

Exam move

Make a four-cell grid with low and high grade against low and high quality and fill each cell with an example of your own; this settles the most common confusion. Next, sort a list of twenty quality activities into prevention, appraisal, internal failure and external failure, then into QA and QC. Rework the cost-of-quality calculation with different figures and always add a one-sentence comment on what the split implies.

Finally, write a quality plan row for an intangible feature such as ease of use, insisting on a criterion you could actually measure. Link this chapter to risk as well: a quality requirement that may not be met is a candidate entry for the Week 7 risk register.

Working through Quality Planning and the Cost of Quality in PMGT5871? Sia is AskSia’s AI Project Management tutor — ask any PMGT5871 Quality Planning and the Cost of Quality question and get a clear, step-by-step explanation grounded in how PMGT5871 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 196 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5871 tutor, unlimited, worked the way the exam marks it
The full 3-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works