PMGT5887 Chap.8 Resources, Costs, Levelling and Progress Tracking

- one subject, every graph, every model, every mark
8 Chapters4-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 8 of 12 · PMGT5887

Resources, Costs, Levelling and Progress Tracking

The second Microsoft Project week adds people and money to the schedule, and this chapter covers both. It explains work, material and cost resources, the Resource Sheet and the four-tab Resource Information dialog, resource calendars, and what overallocation means when a person is booked beyond their available hours.

It shows levelling with a designer booked twice on one day, quotes the PMBOK definition the Topic 7 page uses, and rebuilds the six levelling methods from the slides around their effect on finish date and cost, with a worked choice that turns on slack.

It then sets out the routes by which cost enters a file: standard and overtime rates, cost per use, fixed costs on a task or the project, cost resources, accrual timing and the five cost rate tables per resource. The chapter ends with tracking: why a baseline is saved first, how a status date keeps actuals honest, what the Project Statistics dialog and custom tables provide, and how the PMBOK Guide describes project controls.

Two costing exercises show each route by which money enters a plan.

In this chapter

What this chapter covers

  • 01

    Work, material and cost resources

  • 02

    Resource calendars and overallocation

  • 03

    Resource levelling and its cost in time

  • 04

    Six methods to resolve overallocation

  • 05

    Rates, cost per use and fixed costs

  • 06

    Cost rate tables and accrual

  • 07

    Baselines and status dates

  • 08

    Project statistics and project controls

Worked example · free

Costing one task with three kinds of resource

Q [4 marks]. A task called Install signage uses an installer at $55 per hour for 16 hours with a $90 cost per use, 12 signs as a material resource at $40 each, and a $250 fixed cost for a council permit. What is the task cost? The practice weighting is assigned by AskSia and is not an official assessment scheme.
Levelling trades time for feasibility.Levelling trades time for feasibility. Wednesday asks for 16 hours from an 8-hour person. Delaying the style guide by one day removes the peak, and the work now ends a day later.Before: tasks overlap on Wednesday8 h availableMon8Tue8Wed16Thu8Fri8After: second task delayed one day8 h availableMon8Tue8Wed8Thu8Fri8Mon8WireframesStyle guidehours above availability
Levelling trades time for feasibility. Wednesday asks for 16 hours from an 8-hour person. Delaying the style guide by one day removes the peak, and the work now ends a day later.
  • +1Installer work: 16 x $55 = $880, plus the $90 cost per use = $970.
  • +1Material: 12 signs x $40 = $480.
  • +1Fixed cost: the $250 permit is attached to the task, not to a resource.
  • +1Task total: $970 + $480 + $250 = $1,700.
The task costs $1,700: $970 for the installer including the per-use fee, $480 for materials and $250 fixed cost.
Sia tip — List each cost route separately before adding: rate times hours, per-use fee, units times unit cost, then fixed cost.
Glossary

Key terms

Work Resource
A person or piece of equipment whose cost is driven by hours of work at a set rate.
Material Resource
A consumable supply, costed as the units used multiplied by the cost per unit.
Cost Resource
A cost item, such as travel, applied to a task with an amount entered for each assignment.
Overallocation
The state in which work assigned to a resource exceeds the hours it has available.
Resource Levelling
Adjusting start and finish dates to balance demand for resources with the available supply.
Status Date
The date as of which actual progress is recorded and compared with the plan.
FAQ

Resources, Costs, Levelling and Progress Tracking FAQ

What is the difference between a fixed cost and a cost resource?

A fixed cost belongs to a task, or to the project summary task for overheads. A cost resource is created on the Resource Sheet and assigned like a resource, and any number of them can be applied to one task.

Why does levelling often make a project longer?

Levelling resolves clashes by moving work to when a resource is free. If the moved work has no slack, the finish moves too, so cost and time should be checked before and after.

Why set the status date before entering actuals?

Progress is measured as of the status date. If it is left at today's date by default while you enter last week's figures, the comparison between actual and planned work will be wrong.

What are cost rate tables for?

Each resource has five, labelled A to E, so one person can carry different hourly and per-use rates for different kinds of work or for rates that change on a set date.

What is the difference between a baseline and the current schedule?

The baseline is a saved copy of the approved plan. The current schedule changes as actuals are entered and tasks move, and the gap between the two is the variance a manager reports.

Study strategy

Assessment move

Practise the cost routes with three short tasks until you can total each one in under a minute. For levelling, take any overallocation and ask three questions: does the task have slack, is overtime acceptable, is anyone else free; the answers pick the method. In Microsoft Project, save a baseline, set a status date and enter a few actuals to see the variance appear.

Build a small file with three resources of different types and one overallocation, then try two different levelling methods and record what happens to the finish date and the total cost each time. That comparison is the reasoning a scenario question asks you to explain in a few lines.

Working through Resources, Costs, Levelling and Progress Tracking in PMGT5887? Sia is AskSia’s AI Project Management tutor — ask any PMGT5887 Resources, Costs, Levelling and Progress Tracking question and get a clear, step-by-step explanation grounded in how PMGT5887 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 202 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5887 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works