PMGT5891 Chap.9 Decision Trees and Risk-Informed Decisions

- one subject, every graph, every model, every mark
8 Chapters4-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
Chapter 9 of 12 · PMGT5891

Decision Trees and Risk-Informed Decisions

This chapter covers the Week 9 toolkit for choosing between options when outcomes are uncertain. You learn the standard notation, with squares for choices and circles for chance events, then solve trees by rolling back expected monetary value from right to left.

The chapter adds a break-even probability test so you can say how firm a recommendation is, reads individual paths for the chance of a loss, and shows one simple way to fold expected risk cost into a benefit-cost ratio. The Carter Racing case closes the chapter with a warning about deciding from incomplete data.

In this chapter

What this chapter covers

  • 01

    Decision nodes and chance nodes

  • 02

    Expected value of a chance node

  • 03

    Rolling back a tree from right to left

  • 04

    Break-even probability and sensitivity

  • 05

    Path probabilities and the chance of a loss

  • 06

    Benefit-cost ratio adjusted for risk

  • 07

    Carter Racing and missing data

  • 08

    Limits of decision trees

Worked example · free

Build in house or buy a package: a cost tree

Q [4 marks]. A hospital IT team can build a rostering tool in house for $120k, with a 0.4 chance of a delay that adds $100k, or buy a package for $165k, with a 0.1 chance of an integration problem that adds $50k. Using expected cost, which option should the team choose, and at what delay probability would the in-house option stop being cheaper? (AskSia practice weighting; not an official University mark allocation.)
Decision tree for a contractor choosing how to build a school classroom block, with profits in thousands of dollars: the square is the choice, each circle is a Decision tree for a contractor choosing how to build a school classroom block, with profits in thousands of dollars: the square is the choice, each circle is a chance event, and every end point shows its probability and profit (thicker lines mean likelier outcomes, and the bars on the right are scaled to profit). Rolling back from right to left gives modular construction an EMV of $280k (0.8 × $36On time: 0.8, $360kLate: 0.2, −$40kEMV $280kModularDry season: 0.6, $300kWet season: 0.4, $200kEMV $260kOn-siteBest $280k
Decision tree for a contractor choosing how to build a school classroom block, with profits in thousands of dollars: the square is the choice, each circle is a chance event, and every end point shows its probability and profit (thicker lines mean likelier outcomes, and the bars on the right are scaled to profit). Rolling back from right to left gives modular construction an EMV of $280k (0.8 × $360k plus 0.2 × a $40k loss) against $260k for on-site construction, so the on-site branch is struck out, yet only modular has an outcome that loses money.
  • +1Expected cost of building: $120k + 0.4 x $100k = $120k + $40k = $160k.
  • +1Expected cost of buying: $165k + 0.1 x $50k = $165k + $5k = $170k.
  • +1Costs are being minimised, so the decision node takes the lower value: build, saving $10k in expectation.
  • +1Break-even: 120 + 100p = 170, so 100p = 50 and p = 0.5. Above a 50% delay chance, buying is cheaper.
Build in house: its expected cost is $160k against $170k for the package. The choice reverses if the chance of delay rises above 0.5, so the team should check how reliable its 0.4 estimate is.
Sia tip — Write the break-even probability as a single sentence after your recommendation, so the reader sees how far your estimate could move before the answer changes.
Glossary

Key terms

Decision node
A decision node is a square on a decision tree marking a point where the choice is within the decision maker's control.
Chance node
A chance node is a circle marking outcomes outside the decision maker's control, each carrying a probability, with the probabilities on its branches totalling 1.0.
Expected monetary value
Expected monetary value is the probability-weighted sum of the money outcomes leaving a chance node.
Roll-back
Roll-back is the solving procedure that works from the right-hand end of a tree to the left, valuing each chance node at its EMV and each decision node at its best option.
Break-even probability
Break-even probability is the value of an uncertain probability at which two options have equal EMV, so the preferred option changes on either side of it.
FAQ

Decision Trees and Risk-Informed Decisions FAQ

Which shape stands for a decision in a decision tree and which for a chance event?

Squares mark decisions, the points where you choose between options, and circles mark chance events whose outcomes you cannot control. Branches leaving a square are alternatives; branches leaving a circle are outcomes with probabilities. Time runs left to right, so draw the tree in the order events actually happen, then solve it in reverse.

Does the option with the highest EMV always win?

Not automatically. EMV is a long-run average, so an option with a higher EMV can still carry a real chance of losing money on this occasion. List each path with its probability, report the chance of a loss, and say whether a risk-averse owner might prefer the safer option. The tree informs the decision rather than making it.

How do you adjust a benefit-cost ratio for risk?

The unit names an adjusted benefit-cost ratio but gives no single formula. One clear illustration is to divide benefits by costs plus the expected cost of the remaining risks, where expected cost is the sum of probability times impact. An option with a strong plain ratio but heavy exposure can then fall behind a safer alternative.

What is the Carter Racing case about?

A small racing team must decide within an hour whether to enter a televised race after repeated engine failures, with its mechanics disagreeing about the cause. Most groups choose to race. The case is built on the data used in the Challenger launch decision and is used to discuss bias, pressure and judging risk from incomplete information.

What are the main weaknesses of decision trees?

Trees become unwieldy quickly, because every extra option or uncertain event multiplies the branches, so they suit fairly simple choices. The bigger weakness is the input: probabilities are often judgement rather than solid data, and the answer is only as good as those estimates. Sensitivity checks such as a break-even probability help expose that weakness.

Study strategy

Exam move

Practise until you can draw and solve a two-option tree by hand in under ten minutes, because the unit says a simple tree may appear in the exam. Start every tree by writing the probabilities on each circle and checking they total 1.0. Then work right to left: compute each circle's EMV on its own line, carry the best value back to the square, and state the recommendation in words.

Finish with one sensitivity line, either a break-even probability or the chance of a loss on the preferred option. For the Carter Racing discussion, prepare two or three sentences on what data were missing and how pressure shaped the vote. Finally, rehearse the adjusted benefit-cost idea with your own numbers so you can explain why a ranking can change once risk is priced in.

Working through Decision Trees and Risk-Informed Decisions in PMGT5891? Sia is AskSia’s AI Project Management tutor — ask any PMGT5891 Decision Trees and Risk-Informed Decisions question and get a clear, step-by-step explanation grounded in how PMGT5891 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 196 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5891 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works