PHYS7470 Energy Audit and Management
PHYS7470 Overview
- Hong Kong Baptist University
- Semester 1, 2026-27
- Postgraduate taught master
- Closed-book final exam
What the course joins together
Energy Audit and Management has two connected halves. Carbon accounting begins with organisational and operational boundaries, follows activity data through emission factors and global warming potential, and ends with a report that can support reductions.
- Assessment Carbon project, energy work and final examination.
- Core method Boundary, evidence, conversion and decision.
- Hardest step Keeping units and comparison bases consistent.
What you get in the full PHYS7470 Exam Bible
- 8 chapters, 35 pages — every examinable topic
- 20 original practice questions, each with a model answer in the Final exam format
- 8 worked examples, solved the way PHYS7470 marks
- 8 computed figures, redrawn from the course’s own numbers
- Exam-morning plan for the Final exam (40%) — what to revise last, where marks are lost
Free on this page: assessment table, chapter map, one worked example, key terms, FAQ. The rest is in the full exam bible.
How PHYS7470 is assessed
| Component | Weight | Format |
|---|---|---|
| Carbon audit mini-project | 30% | Applied carbon-audit project |
| Energy management and audit | 30% | TPg presentation 20% plus essay 10% |
| Final exam | 40% | Closed-book, 2 hours; carbon audit 50% and energy audit 50% |
The numeric weights total 100%. Current submission settings are controlled by the course Moodle page.
Assessment structure
Segment widths reproduce the published percentage weights and total 100%.
What other students are asking about PHYS7470
- Where can I find lecture notes or study guides for PHYS7470 at HKBU?
- The PHYS7470 study guide in AskSia Library covers Energy Audit and Management in 8 chapters, with the assessment table, a chapter-by-chapter topic map, key terms and a worked example, free to read on this page.
- Is there a final exam in PHYS7470, and how much is it worth?
- Yes. In the offering this AskSia Library guide is built from, Final exam carries 40% of the PHYS7470 mark; the full split is Carbon audit mini-project 30%, Energy management and audit 30%, Final exam 40%.
- What does PHYS7470 cover on inventory boundaries and consolidation?
- In AskSia Library's PHYS7470 guide, the Inventory Boundaries and Consolidation chapter explains equity share, financial control and operational control.
- What does PHYS7470 cover on emission scopes and building inventories?
- In AskSia Library's PHYS7470 guide, the Emission Scopes and Building Inventories chapter explains direct, purchased-energy and other indirect sources.
- What does PHYS7470 cover on activity data, factors and co2e?
- In AskSia Library's PHYS7470 guide, the Activity Data, Factors and CO2e chapter explains records, factor units, gas conversion and inventory roll-up.
Current PHYS7470 dates
| Date | Item | Control |
|---|---|---|
| 2026-10-11 | Carbon mini-project due |
The Moodle submission page states the due date. Confirm exact deadlines and submission settings in the live LMS.
What PHYS7470 covers
Eight chapters connect carbon-footprint accounting, building-energy analysis, utility bills and engineering economics.
Climate Change and Carbon Footprints
activity data, emission factors, global warming potential and CO2eWhat a carbon footprint makes comparable
A carbon footprint expresses greenhouse-gas impact in carbon-dioxide-equivalent units, allowing activities recorded in litres, kilowatt-hours, kilograms and kilometres to enter one inventory.
- Carbon footprint
- Activity data
- Emission factors
- Global warming potential
- CO2e conversion
- Unit checks
Inventory Boundaries and Consolidation
equity share, financial control and operational controlThe inventory begins with an operation list
Organisational boundaries determine which operations enter a greenhouse-gas inventory and what portion of each operation is attributed to the reporting company.
- Organisational boundaries
- Equity share
- Financial control
- Operational control
- Consolidation consistency
- Included operations
Emission Scopes and Building Inventories
direct, purchased-energy and other indirect sourcesScopes describe a relationship
Operational boundaries classify included emissions as direct, purchased energy or other indirect sources.
- Scope 1
- Scope 2
- Scope 3
- Building sources
- Meter boundaries
- Biomass treatment
Activity Data, Factors and CO2e
records, factor units, gas conversion and inventory roll-upQuantification is an evidence chain
A credible inventory preserves the path from source records to activity data, matched emission factors, gas masses, global warming potential and CO2e.
- Source records
- Factor selection
- Stock balances
- Gas-specific factors
- GWP conversion
- Inventory roll-up
Base Years, Reporting and Carbon Management
recalculation triggers, reporting principles and performance ratiosA trend needs a stable comparison frame
A base year is the historical period against which an organisation tracks greenhouse-gas performance. The comparison becomes misleading when the inventory frame changes.
- Base year
- Recalculation policy
- Significance threshold
- Reporting principles
- Ratio indicators
- Offset separation
Building Energy Rules and Delivered Cost
codes, standards, audits, energy conversion and point-of-use costCodes, standards and audits do different work
Building energy codes establish minimum requirements, while standards provide technical criteria that may be voluntary until adopted into a legal or contractual framework.
- Energy codes
- Technical standards
- Periodic audit
- Energy conversion
- Point-of-use cost
- Ventilation constraint
Electricity Bills, Demand and Power Factor
energy charges, peak demand, ratchets and power-factor correctionA bill prices more than energy
Electricity bills can combine customer charges, accumulated energy, peak demand, adjustments, ratchets and power-factor rules.
- Energy charge
- Demand charge
- Demand ratchet
- Power factor
- Billed demand
- Load control
Economic Evaluation of Energy Measures
cash-flow timing, NPV, IRR, EAA, BCR and life-cycle costThe timeline is the calculation specification
Engineering economics places project costs, savings, maintenance and salvage on a common time basis.
- Cash-flow diagram
- Time value
- Simple payback
- Net present value
- Equivalent annual annuity
- Life-cycle cost
Building energy work begins with requirements and measured performance, follows utility bill structures and delivered-energy cost, and ends with economic evaluation of improvement projects.
The shared habit is traceability: every conclusion should point back to a physical record, a unit-safe conversion and a declared comparison basis.
How the carbon half develops
The opening chapters define a carbon footprint, choose a consolidation approach, classify direct and indirect sources, calculate CO2e and preserve comparability through base-year recalculation.
Reporting principles keep gross emissions separate from offsets and distinguish absolute totals from intensity indicators. A defensible inventory also keeps a source register, records factor provenance and explains exclusions.
That evidence trail makes later recalculation possible when an acquisition, disposal, methodology change or material error would otherwise break comparison with the base year.
How the energy half develops
The energy chapters separate codes from standards, connect periodic audit duties with actual building evidence, compare fuels at the point of use, decode energy and demand charges, and evaluate measures through present value and life-cycle cost.
Demand ratchets and power factor show why reducing kilowatt-hours does not always reduce the largest charge. The same evidence habit applies here: begin with meters, bills, tariff clauses and equipment performance, preserve units through every conversion, then place technical savings on a dated cash-flow timeline.
A recommendation is strongest when its physical mechanism, billing consequence and financial decision rule agree.
Worked example · free
Diagnose a billed-demand floor
- 2Compare the two candidate demands.
- 2Select 300 kW and name the ratchet as binding.
Key terms
- Activity Data
- A measured quantity of an activity that produces emissions.
- Emission Factor
- A coefficient that converts activity data into an emission quantity.
- Global Warming Potential
- A factor comparing a gas's warming effect with carbon dioxide.
- Organisational Boundary
- The operations and shares included in an inventory.
- Operational Boundary
- The emission sources included and their scope classifications.
- Base Year
- The historical period used to track emission performance.
- Demand Charge
- A bill charge based on peak power demand.
- Demand Ratchet
- A tariff floor linked to a previous peak demand.
- Power Factor
- The ratio of real power to apparent power.
- Point-of-use Cost
- Operating energy cost adjusted for conversion efficiency.
- Net Present Value
- Present benefits minus present costs.
- Life-cycle Cost
- The comparable present cost of ownership and operation.
PHYS7470 FAQ
How is the course assessed?
The published structure assigns thirty per cent to the carbon audit mini-project, thirty per cent to energy management and audit work, and forty per cent to the final examination. For taught postgraduate students, the energy component is a presentation worth twenty per cent plus an essay worth ten per cent.
What is published about the final exam?
The course overview describes a closed-book examination lasting two hours. It assigns half of the examination coverage to carbon audit and half to energy audit. Prepare both halves through the published concepts, calculations and evidence chains, and follow any later section instructions supplied on the course Moodle page.
Why do boundaries come before scopes?
Organisational boundaries decide which operations and shares enter the inventory. Operational boundaries then classify included sources as direct, purchased energy or other indirect emissions. Starting with scopes can classify a source that does not belong to the reporting entity's inventory.
What mathematics should I practise?
Practise unit conversions, activity-data and emission-factor multiplication, GWP conversion, demand and ratchet comparisons, delivered-energy cost, present value, NPV and life-cycle cost. Always print units and state the decision rule after the arithmetic.
How should electricity bills be analysed?
Separate customer, energy, demand, adjustment and tax elements. Compare corrected current demand with any ratchet floor before pricing demand. A short peak may influence later bills even when its additional kilowatt-hours are small.
How do I compare energy projects?
Draw the cash-flow timeline, choose a consistent dollar basis and rate, then select a method that matches the alternatives. NPV works on a common basis, EAA helps with different lives, and life-cycle cost favours the lowest comparable cost.
Questions students ask in each PHYS7470 chapter
- Why is CO2e used?
- It provides a common reporting unit for gases with different warming effects, allowing source results to be added after each gas is converted on a consistent GWP basis. The common unit does not remove the need to retain each activity record, factor and gas calculation underneath the total. A reviewer should still be able to trace every reported tonne back to its physical source and reporting period. Chapter 01 · Climate Change and Carbon Footprints
- Why can two boundary totals differ?
- Equity follows economic interest, while control methods include all or none of an operation according to a control test. The physical operations can be identical while attribution changes. Compare the included operation rows, not only the bottom-line tonnes, to see why the results differ. That comparison also shows which structural event could change a later base-year trend. Chapter 02 · Inventory Boundaries and Consolidation
- Is every generator Scope 1?
- No. Classification depends on whether the reporting entity controls the emitting source. A contractor-controlled generator can sit outside direct operations even when it is physically located inside the company's building. Check the operating agreement and keep the fuel record with the entity that controls combustion. If the agreement is missing, present both conditional treatments instead of inventing control. Chapter 03 · Emission Scopes and Building Inventories
- Why not treat purchases as emissions?
- Purchases can increase inventory without proving consumption or release. Opening stock, closing stock, transfers, recovery and disposal must be reconciled so the estimated activity reflects material that actually left the balance. Unknown flows remain assumptions beside the estimate rather than unexplained zeroes. This distinction prevents stored material from being assigned an atmospheric impact prematurely. Chapter 04 · Activity Data, Factors and CO2e
- When is a base year recalculated?
- Significant structural changes, methodology changes and discovered errors can trigger recalculation under the organisation's stated policy. The trigger and its effect should be disclosed rather than treated as operating performance. Organic growth normally remains visible unless the policy provides another qualifying reason. The change log should show the historical data added, removed or revised. Chapter 05 · Base Years, Reporting and Carbon Management
- How do codes differ from standards?
- Codes set minimum requirements and are enforceable within their adopted framework, while standards state technical criteria and may remain voluntary until incorporated into law, a code or a contract. An audit then measures actual operation rather than creating the minimum itself. Its findings still need a baseline, operating condition and economic evaluation. Chapter 06 · Building Energy Rules and Delivered Cost
- What is the difference between kW and kWh?
- Kilowatts measure instantaneous or interval power demand, while kilowatt-hours accumulate energy use over time. They are priced by different bill components and cannot be substituted in one another's tariff formula. Equipment sequencing can reduce the first without materially changing the second. Runtime reduction targets the energy quantity instead. Chapter 07 · Electricity Bills, Demand and Power Factor
- Why is payback only a screen?
- It ignores time value, cash flows after payback, project life and salvage. It can rank recovery speed as a screen, but it cannot replace a full economic comparison. A shorter payback can still accompany a lower NPV. State the omitted cash-flow features whenever the screen is reported. Chapter 08 · Economic Evaluation of Energy Measures
How to study for the exam
Alternate carbon and energy problems. For carbon work, write the entity, boundary, scope, activity unit, factor unit and CO2e result. For energy work, write the meter or tariff driver, technical saving, cash-flow timing and decision rule. Recompute every numerical example without notes, then explain in one sentence what the result proves and what it leaves outside the boundary.