Risk Identification, Assessment and Treatment

Risk planning identifies events that might happen, rates and quantifies them, and decides how to respond. This chapter defines uncertainty, sources, hazards, risks, issues and cascading risks, compares the identification techniques taught in Week 7, and applies qualitative rating on a likelihood and impact matrix.

It then calculates exposure as probability times impact for a pre-treatment and post-treatment risk profile and explains the treatment strategies for threats and opportunities and the contents of a risk register. Risk combines vocabulary, judgement and arithmetic, which makes it a natural source of both quick recall items and short calculations.

The Week 7 tutorial builds a risk register for the first case study in a fixed order: identify risks individually and then by brainstorming, assess them qualitatively, choose treatments, quantify them, and complete the register. Following that order in an answer shows the marker that the process, not just the result, is understood.

In this chapter

What this chapter covers

  • 01

    Uncertainty, sources, hazards, risks and issues

  • 02

    Cascading risk and its treatment

  • 03

    Risk identification techniques

  • 04

    Qualitative risk assessment and the risk matrix

  • 05

    Quantitative assessment and exposure

  • 06

    Pre-treatment and post-treatment risk profiles

  • 07

    Treatment strategies and the risk register

Worked example · free

Calculating a risk profile before and after treatment

Q [4 marks]. Marks shown use an AskSia revision weighting, not an official University allocation. R1 has a 40% chance of a $50,000 impact, cut to 10% by a $3,000 treatment. R2 has a 30% chance of an $80,000 impact, cut to a $20,000 impact by a $6,000 treatment. Find both profiles.
The bars compare total exposure before treatment, the cost of treating both risks and the exposure left afterwards: spending $9,000 cuts the profile from $44,00The bars compare total exposure before treatment, the cost of treating both risks and the exposure left afterwards: spending $9,000 cuts the profile from $44,000 to $11,000.$44,000Pre-treatment$9,000Treatment cost$11,000Post-treatment
The bars compare total exposure before treatment, the cost of treating both risks and the exposure left afterwards: spending $9,000 cuts the profile from $44,000 to $11,000.
  • 1Pre-treatment exposures: $20,000 for R1 and $24,000 for R2.
  • 1Pre-treatment profile: $44,000.
  • 1Post-treatment exposures: $5,000 and $6,000, a profile of $11,000.
  • 1Compare: $9,000 of treatment removes $33,000 of exposure, so both are justified.
The profile falls from $44,000 to $11,000 for $9,000 of treatment; R1 is mitigated through probability and R2 through impact.
Sia tip — Test each treatment on its own as well as in total: a treatment that costs more than the exposure it removes is usually rejected.
Glossary

Key terms

Issue
A risk that has occurred and is now a problem to be managed.
Cascading risk
A new risk created by a treatment strategy or by an issue.
Residual risk
The risk that remains after a treatment strategy has been applied.
Nominal group technique
An identification method in which each participant lists risks individually before the group collates and discusses them.
Risk transfer
Shifting a risk's consequence to a third party through contract terms or insurance without changing its likelihood.
FAQ

Risk Identification, Assessment and Treatment FAQ

How is risk exposure calculated?

Where the impact of a risk is quantified financially, it is multiplied by the probability to give the exposure. Summing the exposures of the high-priority risks gives the pre-treatment profile, and repeating the calculation on residual risks gives the post-treatment profile.

Does transferring a risk reduce its likelihood?

No. The Week 7 slides note that transfer through contract terms or insurance shares the risk without changing its likelihood. Mitigation is the strategy that reduces probability or impact, leaving a residual risk to reassess.

What is the difference between the nominal group and Delphi techniques?

Both ask people to identify risks individually before pooling them, which stops dominant individuals setting the list. The Delphi technique also keeps participation anonymous, which helps when a risk involves a powerful stakeholder.

What is the difference between a risk and an issue?

A risk is an event that might happen, with a threat being a negative risk. An issue is a risk that has already occurred, a problem that now needs to be managed. Issues can also create cascading risks that need their own treatment.

What treatment strategies apply to opportunities?

The Week 7 slides list accept, where no specific action is taken; exploit, which actively pursues the opportunity to increase its likelihood; and enhance, which maximises its benefit by increasing the impact if it occurs.

What is the difference between qualitative and quantitative risk assessment?

Qualitative assessment judges likelihood and impact as high, mid or low and applies them to a risk matrix to rate and prioritise risks. Quantitative assessment replaces those judgements with numbers, such as a probability and a dollar impact, and calculates exposure.

Study strategy

Exam move

Write the risk vocabulary as a chain, from uncertainty to source, hazard, risk, issue and cascading risk, and give one example of each from a project you know. For identification, pair each technique with the weakness of open discussion it fixes. Then build a three-line risk register with qualitative ratings, exposures, treatments and residual exposures, and check that each treatment costs less than the exposure it removes.

Finally, sort the treatment strategies into those that change likelihood or impact and those that only move or accept the consequence, since that distinction is the most frequently tested. When you write a register line, keep the treatment and the residual assessment side by side so a reader can see exactly what the treatment bought.

Working through Risk Identification, Assessment and Treatment in PMGT5871? Sia is AskSia’s AI Project Management tutor — ask any PMGT5871 Risk Identification, Assessment and Treatment question and get a clear, step-by-step explanation grounded in how PMGT5871 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 196 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5871 tutor, unlimited, worked the way the exam marks it
The full 4-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works