Chapter 10 of 13 · PMGT5871

Stakeholder Engagement and Communication Plans

A stakeholder is anyone who affects or is affected by the project, and the slides note that most of a project manager's time goes on communicating with them. This chapter covers how stakeholders are identified, how the power and interest grid ranks them, and how communication differs from engagement.

It then sets out the six elements of a communication management plan, the vocabulary of methods, channels and mechanisms, and how reporting content changes for sponsors, team members and wider stakeholders. This is the last week examined in the final, and it ties the earlier plans together, because every schedule, budget, risk and quality decision has to reach the right people in the right form.

The Week 8 tutorial asks groups to identify at least ten stakeholders for the first case study, analyse them on the power and interest grid and develop a communication plan, which completes the traditional half of the group project management plan.

In this chapter

What this chapter covers

  • 01

    Defining and identifying stakeholders

  • 02

    The power and interest grid

  • 03

    Communication compared with engagement

  • 04

    Elements of the communication management plan

  • 05

    Interactive, push and pull methods

  • 06

    Direct and indirect channels and mechanisms

  • 07

    Tailoring content to each audience

Worked example · free

Turning a stakeholder map into communication actions

Q [4 marks]. This exercise uses AskSia's revision weighting, not an official marking scheme. A council is high on power and interest in a pool redevelopment, and a swim club is high on interest but low on power. Draft one communication entry for each.
Each dot places one stakeholder of a pool redevelopment by power to affect the project and by how much the project affects them; the top-right quadrant needs thEach dot places one stakeholder of a pool redevelopment by power to affect the project and by how much the project affects them; the top-right quadrant needs the most active engagement. high power, low interest high power, high interest low power, low interest low power, high interest Council State funder Swim club Tourists interest: how impacted power to affect
Each dot places one stakeholder of a pool redevelopment by power to affect the project and by how much the project affects them; the top-right quadrant needs the most active engagement.
  • 1Council content: budget and schedule performance, milestones, issues and risks.
  • 1Council method: an interactive monthly steering meeting with a written report.
  • 1Club content: closure effects on training and alternative pools.
  • 1Club method: push email at major milestones plus one consultation session.
Engage the council closely through interactive meetings and reports, and keep the swim club informed by push messages with a chance to be consulted, naming the sender of each message.
Sia tip — Write the method type next to every planned message: interactive, push or pull. If one method serves every audience, the plan is not tailored.
Glossary

Key terms

Stakeholder
Any person or group affected by the project, or able to influence the project or what it delivers.
Push communication
One-way communication initiated by the sender, such as an email.
Pull communication
One-way communication received at the receiver's discretion, such as information posted on an intranet.
Indirect channel
A channel that carries subconscious messages, such as tone, facial expression or body language.
FAQ

Stakeholder Engagement and Communication Plans FAQ

What are the two questions on the power and interest grid?

Power asks to what extent a stakeholder can affect the project. Interest asks to what extent the stakeholder is impacted by it. The position on the grid decides how much engagement each stakeholder needs and how often.

How does engagement differ from communication?

Communication is a one-way or two-way transfer of information. Engagement covers activities aimed at establishing meaningful contact or involvement, such as participation, consultation and collaboration, so it asks more of both sides than sending information.

What should a sponsor receive in project reports?

The Week 8 slides list progress against milestones, budget and schedule performance, estimates and variances at completion, issues, a quality report and emerging risks and opportunities, which is more summary and less task detail than a team member needs.

What is the difference between push and pull communication?

Both are one-way. Push communication is initiated by the sender, such as an email. Pull communication leaves receiving to the receiver's discretion, such as information published on an intranet portal that people access when they choose.

What are the elements of a communication management plan?

The slides group the plan into objectives, scope, assumptions and constraints; strategy, methods, channels and mechanisms; a plan of concrete actions; the factors that decide success; an analysis of stakeholders and the information each needs; and a way of monitoring and evaluating whether the communication works.

Why tailor reports to different audiences?

Each audience needs different information. A sponsor wants milestones, budget and schedule performance and emerging risks; a team member needs task descriptions, expectations and work-package details; wider stakeholders want to know how they are affected. One report for everyone serves none of them well.

Study strategy

Exam move

List at least ten stakeholders for a project you know, including indirect groups such as neighbours, regulators and media, then place them on the power and interest grid and note how two of them might move as the project progresses. Write a communication plan table with columns for stakeholder, content, method, mechanism, frequency and sender.

Practise classifying examples as interactive, push or pull, and as direct or indirect channels. Finish by adding a monitoring line to the plan that says how you would know the communication worked. Before the exam, practise turning one stakeholder description into a full plan row in under two minutes, naming content, method and frequency.

Working through Stakeholder Engagement and Communication Plans in PMGT5871? Sia is AskSia’s AI Project Management tutor — ask any PMGT5871 Stakeholder Engagement and Communication Plans question and get a clear, step-by-step explanation grounded in how PMGT5871 is taught and assessed. Read this chapter free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 196 of your University of Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your PMGT5871 tutor, unlimited, worked the way the exam marks it
The full 3-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$0.99 Trial
30-day money-back · cancel in one tap · how it works