UNSW Sydney · FACULTY OF BUSINESS & ECONOMICS

GSOE9820 · Engineering Project Management

- one subject, every graph, every model, every mark
Business and Economics12 Chapters144-page Bible
Our own words - no uploaded lecturer files
Updated for this semester
The Complete Exam Bible · T2 2026

Engineering Project Management

— Worked GSOE9820 study guide for UNSW Engineering Project Management — WBS, scheduling, cost and reserves, risk, Earned Value Management and PMBOK, tuned for the PMP, interview and final Knowledge Quiz.

GSOE9820 Engineering Project Management is a postgraduate coursework course (6 units of credit, UOC) in the UNSW Faculty of Engineering, and it teaches project management as one continuous chain rather than a set of isolated topics: organisational strategy → Project Charter → scope and the Work Breakdown Structure → schedule → cost and reserves → risk → the integrated Project Management Plan (PMP) → Earned Value Management controls → change management → project success. The canonical reference throughout is the PMBOK Guide (6th Edition), taught through the convener's own C3PE planning framework, and the single genuinely quantitative topic that is heavily examined is Earned Value Management (CV = EV − AC, SV = EV − PV, CPI = EV/AC, SPI = EV/PV and the EAC forecast). Assessment (all delivered and submitted through Moodle) layers five components: an individual Scope-Definition task (Task 1, 5%), a group Project Management Plan including the Week 4–6 progress check (Task 2, 45%), a Team-Based Learning quiz series (10%), an individual interview built on a Task 3 change request (20%), and a final Individual Knowledge Quiz (20%) sat during the UNSW examination period. That final quiz is a timed, right/wrong-marked Moodle paper described as similar in style to the PMP exam and aligned to CLOs 1–4; its exact length and open- or closed-book status are marked TBC, so confirm them on the Course Outline. No component carries a stated hurdle, so the pass mark is the standard UNSW 50% (a PS grade); your GSOE9820 mark then feeds the Weighted Average Mark (WAM) that later postgraduate courses build on.

GSOE9820 · UNSW Sydney
An independent, AskSia-authored study guide. AskSia is not affiliated with, endorsed by, or sponsored by UNSW Sydney; the course code and name are used for identification only.
Contents · the whole subject, one map

What GSOE9820 covers

GSOE9820 runs across a UNSW Term following the PMBOK process groups: initiation and the Project Charter, formulating scope into a WBS, then the schedule, cost, risk, communications and resource knowledge areas that make up a full Project Management Plan, and finally Earned Value Management and project success. Assessment layers a group PMP and Week 6 progress check (45%), Team-Based Learning quizzes (10%), an individual scope task (5%), a Task 3 change-request interview (20%) and a final Individual Knowledge Quiz (20%) in the examination period. The chapters below follow that teaching order.

01Project Fundamentals and the Project LifecycleWhat a project is · PMBOK process groups · project economy · initiation · (Week 1)02Strategy, Benefits and the Project CharterOrg strategy → deliverables · business benefits · Project Charter (CLO 1) · (Week 4)03Project Scope and the Work Breakdown StructureScope statement · WBS · 100% rule · decomposition · Task 1 (CLO 2) · (Weeks 1–2)04Stakeholder Identification and AnalysisStakeholder register · power/interest analysis · engagement · (Week 4)05Selecting PM Methods: Predictive vs AgilePredictive vs iterative/agile · selecting methods to fit the project (CLO 3) · (Week 3)06Schedule Management and the Critical PathActivity logic · network diagram · Gantt · critical path · estimating time · (Week 6)07Cost, Budgeting, Reserves and ProcurementCost baseline · contingency vs management reserve · estimating · procurement · (Week 7)08Risk and Opportunity ManagementRisk register · qualitative analysis · contingency · planning for opportunity · (Week 5)09Earned Value ManagementPV, EV, AC · CV, SV, CPI, SPI · EAC/ETC · PMBOK 7.4.2 (CLO 5) · (Week 8)10Project Integration and Change ManagementEnd-to-end integration · change requests · Task 3 change · interview (CLO 4) · (Week 9)11Communications, Resources and TeamsCommunications plan · resource & HR management · teamwork · TBL · (Week 10)12Project Success and Knowledge-Quiz PrepDefining success · MVP & value · PMBOK recall · final quiz (CLOs 1–4) · (Week 10 + exam)
Assessment

How GSOE9820 is assessed

ComponentWeightFormat
Task 1 — Scope Definition (project purpose, WBS diagram, scope statement)5%Individual Moodle submission, Week 3 (Friday 5pm), CLO 2
Task 2 — Project Management Plan (PMP Components), incl. Week 4–6 Progress Check45%Group report (~20 pages) via Turnitin, PMP due Week 7 (Friday 5pm), CLOs 1–4
Team-Based Learning case-study quizzes (Wk 5 revision · Wk 8 Earned Value Management · Wk 10 revision)10%Group Moodle quizzes, in/after lecture, CLOs 1–4
Individual interview (based on the Task 3 change-request PMP)20%~8–10 min oral interview, Weeks 9–10 outside class, CLOs 4–5
Individual Knowledge Quiz (final)20%Moodle quiz during the UNSW examination period; length TBC (confirm on the Course Outline), CLOs 1–4
Worked example · free

Earned Value at a status date: variances, indices and a forecast

Q [5 marks]. A project has a Budget at Completion (BAC) of $200,000. At the status date the Planned Value is PV = $80,000, the Earned Value is EV = $70,000, and the Actual Cost is AC = $85,000. Using the PMBOK formulas, find the cost variance (CV), schedule variance (SV), the CPI and SPI, and the Estimate at Completion (EAC) if current cost efficiency continues. Then state, in one sentence, whether the project can still be delivered within budget. (5 marks)
  • +1List the base measures and the formulas. BAC = $200k; at the status date PV = $80k, EV = $70k, AC = $85k. Cost variance CV = EV − AC, schedule variance SV = EV − PV, cost index CPI = EV/AC, schedule index SPI = EV/PV, and the CPI-based forecast EAC = BAC/CPI.
  • +1Variances. CV = EV − AC = 70 − 85 = −$15k — negative, so the work done has cost more than budgeted (over budget). SV = EV − PV = 70 − 80 = −$10k — negative, so less work has been earned than was scheduled (behind schedule).
  • +1Indices. CPI = EV/AC = 70/85 = 0.82 (< 1, so cost-inefficient — getting $0.82 of value per $1 spent). SPI = EV/PV = 70/80 = 0.88 (< 1, so behind the planned schedule).
  • +1Forecast at completion. If the current cost efficiency continues, EAC = BAC/CPI = 200,000/0.82 = $243k (equivalently 200,000 × 85/70 = $242.9k). The forecast overrun is VAC = BAC − EAC = 200 − 243 = −$43k.
  • +1Management conclusion. With CPI 0.82 and SPI 0.88 the project is both over cost and behind schedule; extrapolating the current cost efficiency forecasts a completion cost of about $243k against a $200k budget — roughly a $43k (21%) overrun — so it cannot be delivered within the current budget unless cost efficiency improves or scope/reserves are re-planned.
CV = −$15k (over budget), SV = −$10k (behind schedule), CPI = 0.82, SPI = 0.88, EAC = BAC/CPI ≈ $243k with a forecast VAC of about −$43k. The project is currently over cost and behind schedule and, at the present efficiency, is forecast to overrun the $200k budget by roughly $43k — so it will not finish within budget unless performance improves.
Sia tip — Keep the sign convention straight: for CV and SV, negative = bad (over budget / behind schedule); for CPI and SPI, below 1 = bad. A fast check is that CV and CPI must agree (both signal over budget here) and SV and SPI must agree (both signal behind). If you are unsure which base measure goes where, ask Sia to walk the PV/EV/AC set-up step by step — it explains the method and checks your working rather than just handing over an answer.
Glossary

Key terms

Project
A temporary endeavour undertaken to create a unique product, service or result (PMBOK 6th Ed). Temporary means it has a definite start and finish; unique means the output has not been made in exactly this form before — the two features that distinguish a project from ongoing operations.
Work Breakdown Structure (WBS)
A hierarchical, deliverable-oriented decomposition of the total scope of work (100%) into successively smaller deliverables down to work-package level. Every element is a noun (a deliverable), child elements sum to 100% of the parent (the 100% rule), and it captures the "what", not the schedule.
Project Charter
The document that links organisational strategy to project deliverables and formally authorises the project, giving the project manager the authority to apply resources. It records purpose, measurable objectives, high-level requirements and risks, a summary milestone schedule and budget, the stakeholder list and the sponsor's authority.
Earned Value Management (EVM)
A monitoring-and-controlling technique that compares three time-phased measures — Planned Value (PV), Earned Value (EV = % complete × budget) and Actual Cost (AC) — to measure cost and schedule performance (CV, SV, CPI, SPI) and forecast the final cost (EAC). The most heavily examined quantitative topic in this course.
Critical Path
The longest path of dependent activities through a project network; equivalently, the sequence of activities with zero total float. It sets the shortest possible project duration, so any delay to a critical activity delays the whole project.
Project Integration
The end-to-end mapping between the parts of a plan — risk based on the real scope and stakeholders, budget consistent with the schedule, benefits traced to stakeholders — with few loose ends. In GSOE9820 (CLO 4) integration, and the ability to justify it, is the central idea that ties every knowledge area together.
FAQ

GSOE9820 FAQ

Is GSOE9820 hard?

It is broad and integrative rather than mathematically deep. Only one topic — Earned Value Management — is genuinely formula-driven, and its formulas (CV, SV, CPI, SPI, EAC) are simple subtraction and ratios; everything else (scope, WBS, charter, risk, stakeholders, schedule, budget) is judged craft assessed by rubric. The real challenge is that the course builds one integrated Project Management Plan and then asks you to justify and re-integrate it live in a 20% interview and to recall PMBOK across every process group in the final Knowledge Quiz, so consistency matters more than any single hard idea. Students who keep up with the weekly workshops and rehearse the WBS, risk and EVM methods steadily, rather than cramming, tend to find this course manageable — and steady work protects your Weighted Average Mark (WAM).

Can AI help me with GSOE9820?

Yes, as a step-by-step study aid. Sia is an AI tutor trained on how GSOE9820 is taught and assessed at UNSW Sydney: it can walk you through an Earned Value calculation (CV = EV − AC, CPI = EV/AC, EAC = BAC/CPI), test a Work Breakdown Structure against the 100% rule, or rehearse a power/interest stakeholder analysis one line at a time, and it checks your reasoning as you go. Bring your own workshop or past-quiz question and ask Sia to explain each step. It does not complete graded assessment for you — the group PMP, the interview and the Knowledge Quiz are your own work — and the UNSW academic-integrity and plagiarism policy still applies; use Sia to understand the method, not to produce work you submit.

Where can I find past exam papers / practice for GSOE9820?

Start on Moodle, where this course posts its lecture notes, the Team-Based Learning revision quizzes and any exam-preparation material for the final Knowledge Quiz, and check the UNSW Library's past-exam-paper collection for any released papers. Because the final quiz is described as similar in structure and timing to the PMP exam, PMP-style multiple-choice banks (especially on Earned Value and PMBOK process groups) are useful practice for the recall it tests. This guide also includes a re-authored practice section that mirrors the paper's shape — WBS judgement, risk scoring, Earned Value and PMBOK recall — with fresh numbers, and you can ask Sia to generate more practice in the same style and explain each step. Confirm what is officially provided, and the quiz length and open/closed-book status, on the Course Outline.

What are the GSOE9820 hurdles and assessment rules?

The five components are Task 1 Scope Definition (5%), the group Project Management Plan including the Week 4–6 progress check (Task 2, 45%), the Team-Based Learning quiz series (10%), the individual interview based on the Task 3 change request (20%) and the final Individual Knowledge Quiz (20%) — totalling 100%, with all submissions and quizzes handled through Moodle. No individual component carries a stated hurdle in the available course materials, so the pass mark is the standard UNSW 50% overall (a PS grade on the HD/DN/CR/PS/FL scheme; HD is 85+, DN 75–84, CR 65–74, PS 50–64). The final-quiz length and whether it is open- or closed-book are marked TBC, so confirm those, and any late-submission or special-consideration rules, on the Course Outline; do not assume a hurdle that is not stated.

What is on the GSOE9820 final exam?

The final assessment is the Individual Knowledge Quiz, a timed Moodle quiz worth 20% sat during the UNSW examination period and aligned to CLOs 1–4, so it can draw on any course topic. It is right/wrong-marked in a style described as similar to the PMP exam, which means fast recall of PMBOK definitions and process groups plus applied Earned Value questions rather than long written answers — expect the process groups and lifecycle, the Project Charter and stakeholders, scope and the WBS, scheduling and the critical path, cost baselines and the contingency-versus-management-reserve distinction, risk responses, and the EVM formulas and their interpretation. The quiz sits in the UNSW Term 2 examination period (around August); confirm the exact date, time and length on the Course Outline and your personal exam timetable on myUNSW, and confirm whether it is open- or closed-book (marked TBC).

Study strategy

How to study for the exam

Treat GSOE9820 as one integrated plan rather than a list of topics, because that is exactly what the assessment rewards. Build the plan chain in order and rehearse each link weekly: strategy → charter → scope and WBS → schedule → cost and reserves → risk → the integrated PMP → Earned Value controls → change → success. For the craft topics, drill the recurring judgements the rubric checks — a deliverable-oriented WBS that obeys the 100% rule and uses nouns; a scope statement that names its constraints; a risk register with clear triggers, responses and a costed contingency; a budget that correctly separates contingency reserve (known risks, inside the cost baseline, PM-controlled) from management reserve (unknown risks, outside the baseline). For the one quantitative topic, make Earned Value automatic: given PV, EV, AC and BAC you should be able to write CV = EV − AC, SV = EV − PV, CPI = EV/AC, SPI = EV/PV and EAC = BAC/CPI and interpret each sign without hesitation, because it recurs in the Week 8 team exercise and the final quiz. Prepare the interview by practising out loud: justify where each contingency is costed, trace tasks back to deliverables, and define success for your specific project beyond "on time and on budget" (value delivered, stakeholder satisfaction, the MVP). Cover breadth first so you can start every quiz topic, then deepen the ones you find hardest. When a step will not click, ask Sia to explain that single step a different way and set you a fresh practice question in the same style — it teaches the method and checks your reasoning, and never substitutes for your own graded work. Confirm the final-quiz date, length and open/closed-book status on the Course Outline and the UNSW exam timetable.

Study GSOE9820 with AI

Your AI Business tutor for GSOE9820

Stuck on a hard GSOE9820 question? Sia is AskSia’s AI Business and Economics tutor — ask any GSOE9820 Engineering Project Management question and get a clear, step-by-step explanation grounded in how the course is actually taught and assessed. Read this whole study guide free, then take your hardest questions to Sia.

A+Everything unlocked
Unlocks this Bible + all 8 of your UNSW Sydney subjects - and 1,000+ Bibles across every Australian university.
Sia - your GSOE9820 tutor, unlimited, worked the way the exam marks it
The full 144-page Bible + practice bank with worked solutions
Chrome extension - sync your LMS so Sia knows your deadlines
Bilingual EN / Chinese on every Bible and every Sia answer
$25/ month
30-day money-back · cancel in one tap · how it works
GSOE9820 · Engineering Project Management - independent study guide on the AskSia Library. More UNSW Sydney subjects · Microeconomics across all universities
Unlock the full GSOE9820 Bible + 8 UNSW Sydney subjects
$25/mo